HomeMy WebLinkAbout2002-11-19 ad Hoc School Building Committee Minutestole-
r
A',N CLERIK
iJING, ,MASS.
Reading School Building Committee 2U23 JAI I P 4. 2
Minutes of RSBC Meeting Held on November 19, 2002, 7:30 p.m.
(In the RMHS Guidance Career Center)
Committee Members Attending:
Russ Graham, Chair (RG)
Tim Twomey (TT)
Rich Radville (RR)
Dennis LaCroix (DL)
Bill Carroll (BC)
Warren Cochrane (WC)
Paula Perry (PP)
Jeff Struble (JS)
Alex McRae (AM)
Ray Porter (RP)
Featured Guests:
Frank Orlando (Staff)
Dr. Harry Harutunian (Staff)
Sid Bowen (Flansburgh Associates, Inc.)
Robert Peirce (Flansburgh Associates, Inc.)
Andrew Grimes (Finance Committee liaison)
RG began by saying that the purpose of this meeting was to continue the process of
making a decision as to which of the three options for the RMHS renovation should be
developed into a schematic design.
He suggested that the compiled list of negative aspects for each option be addressed to
see if they could be mitigated in any way.
Starting with Option 1:
The most obvious drawback to this option was the long phasing schedule.
RG asked if FAI saw any means to shorten this schedule. Sid Bowen replied
that they had looked at trying to provide additional swing space in and around
RMHS. They looked at the area under the Auditorium (the Civil Defense
shelter), but found that the foundations for the (closely spaced) columns were
not at a uniform elevation. The footings rose with the grade of the underlying
ledge and intruded into the space that was to be used, making the area
unusable for creating swing space. Importing modular classrooms was
considered, but the cost for the 20 portables needed would add about $2M to
the cost. Hence, that approach was abandoned. He said that conceivably,
the only way to lessen the phasing burden was by spending money for
temporary swing space, which was undesirable.
Readhi g School Building- Committee
Xketing Alinutes frwnn Alovember 19, 2002
AM asked if by temporarily relocating the Superintendent's offices and the
RISE program offsite, could the phasing be shortened (by using their present
spaces). Mr. Bowen replied that the Supt.'s office was not suitable for uses
other than administration (not classroom swing space) and as far as he knew,
there was no alternate location available for RISE.
- Disruption to students and teachers would not be able to be reduced without
more swing space that could be built to accommodate the classes that would
use it (such as laboratories).
- At this point, high school student Nick Smith presented a petition with 261
signatures from high school students that supported Option 3, noting that he
thought the decreased community space in that option could be made up by
utilizing other space in other schools (such as Coolidge Middle School).
- The high risk of contingency funds being needed was directly tied to the
amount of renovation; hence Opt. 1's large amount of renovation could not be
mitigated without changing the plan materially. The same applied to the cost
of phasing relative any long term benefits resulting from the phasing; Option 1
had the highest cost of phasing with very little benefit and couldn't be
changed.
- Regarding quality of space, Mr. Bowen pointed out that the auditorium space
could be increased in quality if desired, but it would be at an additional cost.
No improvement in supervision plans was possible in Option's 1 (or 2). Only
Option 3 presented opportunities in this area.
- Costs to maintain Option 1 were the most, due to its largest square footage.
No avenues of improvement were evident in this area.
- The cafeteria location in Option 1 was the result of considering several
locations in the design phase and finding that any other location detracted
from the programmatic organization for the building as well as from the
phasing plan, so no improvement seemed possible.
- Traffic flow could not be improved without programmatic reorganization or
additions of expensive corridor additions, which were not seen as
improvements to the project.
Regarding Option 2, Mr. Bowen remarked that mitigation of its negatives would be more
or less the same as for the negatives of Option 1.
Regarding the negatives of Option 3:
The loss of the girl's gym and the Lecture Hall were seen as the most obvious
negatives of Option 3, according to Mr. Bowen. There was no recovery of the
girl's gym possible in Option 3 (Option 2 was seen as the best scheme for
retention of that space), although the new gyms at the new elementary school
and at a renovated Barrows School could take the place of the girl's gym for
community use. The Lecture Hall's function could be replicated with an
additional 4,000 sq. ft. of space but he thought that function could be
provided in other ways in other areas of the building.
Reading, School Building Committee
1 fi<eting A. inutes fr-ono .November 19, '002
- WC noted that the auditorium and art/music/drama spaces were not as good
in Option 3 as in Options 1 and 2. He asked if there was any way to improve
Opt. 3's fine arts layout. Mr. Bowen said that in the normal progression of the
area's design, the spaces could be improved and rearranged to better them.
A basic problem in Opt. 3, however (not present in Opt.'s 1 and 2), was the
fact that the programs were on two floors rather than one.
- The highest cost of Opt. 3 was due to the high amount of new construction
and could not be mitigated without cutting the program which made use of the
new facilities.
- Regarding the disposition of the SBA on the reimbursability of Opt. 3, RG
passed out a letter from that agency (copy attached) that confirmed their
verbal assurances that Opt. 3 would be considered for review as a
reimbursable project. He read the letter aloud.
- Negatives such as possible soils difficulties and less "green" construction
were endemic to the need for new construction and could not be mitigated.
- Storage in Option 3 could be improved not by adding square footage, Mr.
Bowen conjectured, but by tightening the spaces within the current target
area and planning efficiently for adequate storage. He reasoned, also, that
the space needs for things like media storage will decrease in time due to
technology usage.
- BC led a discussion about space needs from a teacher's perspective. He
described the benefits of dedicated classrooms for each teacher yet
understood that the economics and programmatic formulae used to
determine actual classroom numbers would not make such a thing possible.
He still had concerns about the apparent reduction of teachers' space in
Option 3. A general discussion followed on the topic of Reading's culture of
funding school projects (reducing the scope of projects appears to be a
historical trend).
RG then asked if anyone on the Committee felt that Option 1 should considered as the
chosen option. No one did, so Option 1 was removed from further consideration by
consensus.
With the choice then being between Options 2 or 3, RG asked for each member's
opinion:
- BC preferred Option 3 due to its short schedule and its least disruption to the
education process for the students and staff.
- DL chose Option 3, citing his belief that it offered the best betterment to high
school education between the two choices.
- TT chose Option 3 saying that his reasons were similar to those given by
previous members. He also thought Opt. 3 would produce the best visual
improvement to the school, creating an attractive building that the community
would embrace.
Reading School Building Committee
Meeting; AIitrutes fr-oni .i1•bvernber LG, 2002
RR chose Option 3 after previously favoring Opt. 2, saying that the desirable
aspects of Opt. 2 that would be lost (Lecture Hall, the girl's gym, etc.) could
be corrected, according to FAI's suggestions for improving negatives such as
those. He also liked the fact that the school would never be without a usable
auditorium under Opt. 3.
- WC also wanted Opt. 3 for many of the same reasons mentioned by RR. He
thought that his concerns with Opt. 3's negatives would be addressed
through the continuing design process.
- PP had.favored Option 3 from the beginning, she said, and had heard from
many people in the community about the desirability of Opt. 3. She felt it had
the least surprises (in terms of the impact to students and on costs).
- JS favored Opt. 2 for several reasons. He said that he thought Opt. 3 had
less contingency space and that plans to add space in Opt. 3 to replicate
functions provided in Opt. 2 would force concessions in the overall program
to meet a budget. He felt that creating a smaller high school from a larger
one would make the possibility of adding on space in the future politically
impossible. He felt the degree of explanation necessary to justify Opt. 3
would be too much for enough voters to absorb prior to a debt exclusion
election. In general, he thought Opt. 2 was more conservative than Opt. 3.
AM chose Opt. 2 over Opt. 3 because he felt Opt. 2 was more like what the
community was expecting. He felt that losing the girl's gym under Opt. 3
would be detrimental to non-school programs and had doubts that the field
house alone would be adequate for the community. With only one chance to
do this project (owing to deteriorating State funding in the future), he thought
Opt. 2 had the best chance of being accepted.
RP expressed disappointment with the options developed by FAI, noting that
the more or less equivalent costs of all three were not what he was expecting.
He thought that a basic repair of the present school's infrastructure could
have been a beginning point for building options on, using an incremental
approach. He said he was not comfortable with voting for any of the options.
If he were to vote, he said, he would lean towards Opt. 2.
RG then asked for opinions from RMHS Principal Frank Orlando and Superintendent
Harry Harutunian.
Mr. Orlando first thanked FAI for their efforts in developing the options and
the SBC for their work on the project. He compared the various facets of
both Options 2 and 3 and explained his decision to support Option 3. He felt
that Option 3 would make it possible for Reading high school students to
achieve the greatness that they have always had the potential for achieving
(but have been hampered in doing so by outmoded facilities).
Dr. Harutunian agreed with Mr. Orlando's comments. He also added that the
reduction in size of the school would be beneficial to his budgeting for
maintenance of the facility. He thought that the phasing advantages of
Option 3 were educationally desirable and that the increased parking would
be a plus. He said he had gotten feedback at his many community
Reading School Budding Corr mittee
Meeting, M Mutes ft'om Nbvelnber 19, 2002
appearances that indicated the popularity of Option 3. Hence, he favored
that option.
RG added his opinion, saying that he favored Option 3 because he felt it was
the best educational solution over the long term. He believed that the space
reductions realized by that option could be made up elsewhere in the Town.
He thought that the only real opposition to Option 3 from the voters would be
on the basis of cost alone, not the plan itself (whichever that was).
TT then entered a motion to approve Option 3 as the recommendation to Town Meeting
for the renovation of RMHS. DL seconded the motion. RG called for any more
discussion.
JS took issue with statements that the cost differences between Options 2
and 3 were negligible. He pointed out that the difference in cost to Reading
(after reimbursement of the maximum amount or "cap" of around $50M) was
about $2.8M, which represented a 12.7% increase in the cost to Reading
over Opt. 2. He thought that would be a hurdle to get over with Town Meting
and the voters.
- JS also added that while he intended to vote for Option 2, should Option 3 be
the rest of the Committee's choice, he would endorse it.
With no further discussion appearing, a vote was taken and the results were eight in
favor, one opposed and one abstention (8-1-1); thus the motion passed.
Dr. Harutunian added that he agreed with JS's calculations regarding the cost
differentials between Opt.'s 2 and 3, but he felt that the (operational) savings afforded by
Option 3 would make up that difference.
Sid Bowen asked that he be allowed to develop ,a work schedule for the development of
Option 3 for the Committee's review at the next scheduled meeting, tentatively
scheduled for December 11, 2002. In addition, Dr. Harutunian asked permission to work
directly with FAI in assembling the required December 1st preliminary submission to SBA
(now for Option 3). Permission was granted.
RG thanked the school personnel and the other Committee members for their work to
date on the project.
RR described his recent efforts to reply to an editorial in the Reading Advocate
newspaper that had purported to question why Reading couldn't renovate its high school
for what it cost other schools in other states to renovate theirs (at lower amounts). The
editorial cited evidence from a web-site that awarded exemplary school project designs;
specifically schools in Maine, North Carolina and Colorado.
RR contacted the project architects for the North Carolina and Colorado to
discuss the costs for those projects. He found that the costs listed on the
web-site for the schools were not project costs, but construction costs. These
costs did not include furnishing, finishes, fees or equipment and in the case of
the North Carolina job, excluded site costs as well. They also were projects
- completed several years ago.
Reading School Building (.:'onanaittee
,tlectin}, Alinute.s front r' weinber 19, 2002
6
RR then produced a spread sheet (copy attached) that attempted to upgrade
those costs to account for things like inflation (2.66% per year), use of union
sub-contractors (required in MA; a 10% increase), local cost differentials
(45% increase), size differences (RMHS is larger), site costs, demolition
costs, hazardous material removal, architect's fees, "soft" costs, etc. The per
square foot costs for the adjusted out-of-state schools was around $225/s.f.
for NC and @212/s.f for CO while Opt. 3 was estimated at $198/s.f. This
contradicted the editorial's entire premise.
- He said he had. contacted the Advocate's publisher to point out this
contradiction and ask why the editor had not done similar research before
writing the editorial.
Andrew Grimes (FinCom liaison) said he had also contacted the web-site
owners and found that the costs listed were not the real focus of the web-site
(innovative design was). Discussions with the web-site owners revealed that
they were not surprised by the project costs attributed to Opt. 3 and that
some areas of the country experience costs on the order of $400/s.f. He
noted that the owners recognized FAl for their exemplary design work in MA.
JS asked Sid Bowen about the likelihood of the success of the DOE recommendation to
the legislature to make school construction projects exempt from the State's Chap. 149-
mandated requirement for filed sub-bids (made in the same advisory as the
recommendation to reduce reimbursement rates 10% across the board). Mr. Bowen
said his discussions with SBA indicated that there might be a chance that such an
exemption would be passed, but he had no more information than that.
With no other business appearing, RG called for a motion to adjourn. DL so moved and
was seconded by PP. A vote was taken and it was unanimous in the affirmative (time
10:05 p.m.).
Minutes prepared and submitted by:
Jeffrey W. Struble, Secretary
Reading School Building Committee
NOV-13-41.11J4 da:oiam F(om-SCMUUL FINANCE AND BUSINESS SERVICES 7813386530
T-438 P 002/003 F-331
The Commonwealth of Massachusetts
Department of Education
350 Main Street, Malden, Massachusetts 02148-5023
November 14, 2002
Harry K. Harutunian, Ph.D.
Superintendent of Schools
82 Oakland Road
Post Office Box 180
Reading, MA 01867
Dear Superintendent Harutunian:
Tclephene• (781) 338-3000
1 am writing as a follow-up to our recent meeting to discuss construction and renovation options
at Reading Memorial High School. You have submitted feasibility studies dated in 1997, 2000
and 2002 to document the educational and structural inefficiencies at the school. Each of these
studies,. provide recommendations for construction and renovation based on the information
available at the time.
The most recent study proposes one of three options:
1) renovation of the complete building
2) substantial renovation of the building with the demolition of the maintenance area (former
Industrial Arts and
3) replacement of the 1953 academic wing and substantial renovation of the remainder of the
building.
Based on enrollment projections, the existing square footage of the building exceeds the square
footage allowed under the School Building Assistance (SBA) regulations. The building has
many structural and educational inefficiencies, has poor circulation patterns and is in need of
major repair to meet code and educational standards. There appears to be little use of the total
square footage of the area now used for maintenance. Demolition of this wing would not impact
the space requirements of the SBA regulations and would appear to improve traffic flow and
parking. Demolition and replacement of the academic wing would allow for more efficient
phasing of the construction plan, would correct educational and structural deficiencies and would
improve safety, traffic patterns and the efficiency and circulation of the building.
All of your feasibility studies have outlined in greater detail the benefits of each of these
proposed plans. The cost for each of the three options has been estimated within a range of two
million dollars.
You have asked whether any of these three proposals could be submitted under the SBA
Program. As you know and as we have discussed, the SBA program encourages maintaining
existing school buildings through renovation projects. Based on the information before us, we
..J , - J. - J r- JJI
November 14, 2002
Harry K. Harutunian, Ph.D.
Page Two
believe that each of these options might constitute a viable, renovation plan. Although each
proposal that is submitted to meet the December 1 deadline will be evaluated based on the
criteria, process and fiscal limitations of the program, we would be willing to entertain any of
the options presented above with the appropriate local approvals.
I wish you good luck with your, construction planning and would be happy to discuss this issue
or any other issue related to the SBA application process with you at any time.
Cordially,
Christine M. Lynch
Administrator
School Building Assistance
c: Sid Bowen, Flansburgh Associates
Application File
Reading High
Cost review re Silver Creek, CO
-1 prepared by Richard Radville
11.19.02
Project cost
Reading High
area
Project Cost
/sf
Option 1
334,424
$53,059,248
$159
Option 2
324,351
$51,997,745
$160
Option 3
272,552
$53,917,745
$198
Silver Creek High School
180,000
cost
Base construction cost
$20,160,000
(includes site costs, fields, etc., but no fees
or soft costs, no equip or furnish., this is
constr. dollars for the building & site.)
running total
Add 6% inflation
1,209,600
21,369,600
Add 10% for union
2,136,960
23,506,560
Add regional costs at 17% *
3,996,115
27,502,675
Factor to same size, scheme 3
1.51
41,643,940
Add for demolition
1,998,000
43,641,940
Add for Hazmat removal
100,000
43,741,940
Add contingency at 10%
4,374,194
48,116,134
Architect Fees at 8.75%
4,210,162
52,326,295
Furnishishings at $1000/student + fees
1,452,000
53,778,295
Computers at $1200/student + fees
2,287,504
56,065,799
Other "soft" costs, actual RMHS
1,662,000
57,727,799
* source: RS Means Building Construction Cost Data, 2002
Project cost / sf, Silver
Creek in Reading
$212
Reading High
Cost review re Weddington High, NC
prepared by Richard Radville
11.18.02
Project cost
Reading High area Project Cost /sf
Option 1 334,424 $53,059,248 $159
Option 2 324,351 $51,997,745 $160
Option 3 272,552 $53,917,745 $198
Weddington High 224,100
Base construction cost
(no site costs, no fields, no fees or soft
costs, no equip or furnishings, this is ''raw'
construction dollars for the building only.)
Add 8% inflation
Add 10% for union
Add regional costs at 45% *
Factor to same size, scheme 3
Add site costs, RMHS actual
Add for demolition
Add for Hazmat removal
Add contingency at 10%
Architect Fees at 8.75%
Furnishishings at $1000/student + fees
Computers at $1200/student + fees
Other "soft" costs, actual RMHS
cost
$18,448,610
running total
1,475,889 19,924,499
1,992,450 21,916,949
9,862,627 31,779,576
1.22 38,650,544
5,900,000 44,550,544
1,998,000 46,548,544
100,000 46,648,544
4,664,854 51,313,398
4,489,922 55,803,321
1,452,000 57,255,321
2,287,504 59,542,825
1,662,000 61,204,825
Project cost / sf,
Weddington in Reading
$225
* source: RS Means Building Construction Cost Data, 2002