HomeMy WebLinkAbout2002-12-23 ad Hoc School Building Committee MinutesReading School Building Committee
Minutes of RSBC Meeting Held on December 23, 2002, 8:45 p.m.
(In the RMHS Guidance Career Center)
Committee Members Attending:
Russ Graham, Chair (RG)
Michael Scarpitto (MS)
Paula Perry (PP)
Jeff Struble (JS)
Alex McRae, (AM)
Warren Cochrane (WC)
Bill Carroll (BC)
Rich Radville (RR)
'
Dennis LaCroix (DL)
NJ
`TMj
Featured Guests:
u
tr3
Frank Orlando (Staff)
Sid Bowen (Flansburgh Associates, Inc.)
[Author's Note: This meeting began as a joint meeting with the Finance Committee held
in the Conference Room of Town Hall at 7.00 p.m. to discuss the RMHS project and the
debt exclusion it required. Refer to the FinCom minutes of 12123102 for a record of those
proceedings. After the FinCom recommended passage of the RMHS article on the
warrant for the Special Town Meeting on Jan. 13, 2003, a recess was called and the
SBC members and guests traveled and regrouped in the RMHS Guidance Career
Center at 8:45 p.m., which is where these minutes begin.]
RG began by discussing the likely presentation that the SBC will make at the Jan. 13th
Special Town Meeting. The need to explain the problems of the high school was seen
as repetitious due to the previous presentations by the full Committee (last year), the
update presented by the Chair at November's Subsequent Town Meeting and the
background material that was prepared to accompany the warrant. WC stressed the
need to point out the costs involved should Option 3 not pass (the cost of doing nothing).
Sid Bowen said his firm would prepare a summary of items that would unquestionably
require repair or replacement, but he cautioned that an obvious omission would be the
cost of updating the educational program for the school. This update was fundamental
to their charge in preparing the schematic design. He also noted that some
infrastructure updating would not be reimbursable, such as fire sprinklers (since they
would be an addition rather than an upgrade).
Mr. Bowen presented the results of the test borings made in the existing parking lot and
the courtyard to probe the sub-surface areas that would be supporting new foundations
in Option 3 (copy attached).
Reading a School.Building, Committee
Meeting A.Iifzutes5 fi~oiir .December 23, 2002
Only one boring was made in the parking lot due to uncertainty on the Town's
part on where existing underground utilities might lay. This boring showed
competent bearing material at a reasonable depth and did not encounter peat
or other deleterious strata. Mr. Bowen pointed out that this one boring did not
prove the non-existence of peat in the area, but it was sufficient to make a
reasonable prediction of foundation types to use on the project.
The courtyard boring encountered refusal at relatively shallow depths on
three separate attempts. This indicated to the directing engineer the
presence of ledge in the area. This, too, allowed a prediction of the
foundation type to be expected for the new auditorium structure.
Messrs. Bowen and Peirce passed out the State's form 645-1, which was a checklist of
required submittals for a formal SBA submission (copy attached).
FAI presented updated plans and elevations, including a site plan. He said that
discussions with the Town engineer and Town Manager about the site plan, and they
made it clear that they needed one-way traffic around the Field House during elections.
They also had concerns with access from Imagination Station and the number of parking
spaces around the school. Mr. Bowen said his team was still working on incorporating
their concerns into the site plan and would likely not have a complete solution by the
time of Town Meeting (Jan. 13th). He did say they would show a complete vehicle loop
around the Field House.
He went over the updated (CAD-drawn) plans (copies attached), showing
rearrangements with the layouts for the administrative areas and the firewalls. The main
entrances were updated to show common construction (glazing and brick). He
explained various program-improving changes that embellished ideas shown on
previous plans. Members of the Committee discussed the pros and cons of the two-
story gallery along the main "street" with FAI. The discussion continued about other
pieces of the overall design.
A discussion took place concerning the presentation of the graphic displays as accurate
representations of the finished school.
- FAI argued that the schematic design is likely to change in subsequent
design phases and what is shown now may not be what is built later.
- RG expressed concern that the elevations show what the school would look
like and it was reasonable for people to assume that when they went to vote
for it. Changes to it might be seen as being misleading.
- On the other hand, others argued, avoiding the elevations could be seen as
not being true to the assurances given during the schematic design campaign
that going to such a design level would produce a clear idea of what voters
would be voting for in a debt exclusion election. Some type of visual display
of the "look" of the high school (or possibly multiple looks) seemed warranted.
While some members suggested being very clear about the preliminary
nature of the elevations (i.e., being subject to change), others countered that
such explanations might be possible with Town Meeting, but not likely with
the general electorate. The experience with the preliminary "diagrams" for
Reading School Building Committee
Meeting Minutes fivnt December 23, 2002
the Dividence Road elementary school project being taken as final layouts by
many in the community was raised in support of this last point.
- The graphics shown were sufficient to explain to the cost estimators what the
construction would be, Mr. Bowen explained, and subsequent changes would
not materially affect the estimate.
- It was thought that a dialogue with the School Committee (who would have
the final determination of the final design and "look") would be prudent in
order to decide how much of the elevations to show to the public.
RR suggested that FAI look into the addition of more rows of seats in the new auditorium
to boost the capacity to close to 900. FAI said they would do so.
Observer Jackie Mandell asked if the contract between the SBC and FAI would end with
the approval of Town Meeting even if the SBA were to reject Option 3 for some reason.
She was answered that the contract required that FAI produce a reimbursable schematic
design and even if Town Meeting approved going to the next design phase for Option 3
(under the direction of the School Committee), if that schematic design was ruled not
reimbursable, the SBC would still hold FAI to the contract requirement to produce one
that was. The contract did not necessarily end with approval of the warrant.
RG reported that he had discussed the present high school with members of the
Historical Commission and was told that they saw no historical significance to the
existing school other than the fact that it was one of the last projects designed by a firm
headed by two Reading residents (who had done a number of other public buildings in
the Town).
Observer Kendra Cooper asked for information regarding the synthetic athletic field
surface proposed for the stadium and practice fields. Mr. Bowen reiterated the details
given to the FinCom earlier in the evening and various members presented anecdotes
about other communities who had installed such surfaces and apparently benefited from
them.
With no other business appearing, RG called for a motion to adjourn. DL so moved and
was seconded by BC. A vote was taken and it was unanimous in the affirmative (time
10:30 p.m.).
Minutes prepared and submitted by: Jeffrey W. Struble, Secretary
Reading School Building Committee
FLANSBURGH ASSOCIATES
December 23, 2002
Reading School Building Committee
C/o Mr. Russ Graham, Chairman
Architecture
18 Jade Hill Road
Master Planning
Auburn, MA 01501
Programming
Interior Design
Dear Mr. Graham:
As requested, we have reviewed the SBA Capital Grant Application process for the Reading
Principals
Memorial High School. Based on that review we have developed the following overview of the
David S. Soleau, AIA
scope of the application. This overview is intended to aid the School Building Committee, the
Alan S. Ross, AIA
Town of Reading, the School Committee, and the School Department in planning the project.
Duncan P. McClelland, ALA
Sidney R. Bowen, III
The SBA Capital Grant Application for 2003
All applications are to be submitted prior to June 30, 2003. SBA requests that the application be
Chairman
submitted by June 1, 2003, with the remaining month available for comment and correction. The
Earl R. Flansburgh, FAIR, NA
components of the application are listed in the attached SBA 645-1 checklist.
Senior Associates
The application may take one of two forms, and the Town should inform the SBA of it's
Samuel Bird, AIA
Jorge M. Cruz, AIA
intention as soon as possible. The typical `full' application includes drawings and specifications
Rose M. Fiore, Assoc. AIA
from the architect and consultants, as well as their certifications. It also includes approvals from
local building, fire, and other inspectors. Recognizing that there is often a significant delay before
Associates
communities receive a grant, and that this often results in a delayed construction, the SBA is
Valerie M. Curtis
accepting `Deferred Construction' applications. The requirements of this application are
David R. DeFilippo, AIA
marginally less rigorous. Full construction plans and specifications are not required, nor are
Vincent E.J. Dub4, AIA
certain local approvals and architect's certifications. SBA has made it clear however, that approval
James A.
m
, AIA
of the local conservation Cormnission and local Historical Commission are required. Drawings
a
bers
W. Lambert
are still required and the SBA will require that they be fairly advanced. With the Deferred
Thomas
Thomas J. Mueller, AIA
Construction application, the full documentation of the project is not required until several
Dominic I. Pedulla, Assoc. AIA
months before commencement of construction. We have attached the SBA Administrative
Robert E. Peirce, AIA
James B. Williams, Jr., AIA
Advisory 02-2., which explains the two types of application.
Scope:
The attached form 645-1, from SBA, outlines the elements of a full application. We have checked
off those items which are already complete. Of the items listed, the most difficult to achieve are;
1) Item 10: Schematic Drawings, due to the required review and approval process;
2) Item 13, due to the depth of site design and study required before the Conservation
Commission can consider approval;
3) Item 15, due to the process required by Massachusetts Historical,
4) Item 17, MEPA; due to the process of obtaining signed certification from the Secretary
of Environmental Affairs;
5) Item 29, Whether the full documents or the schematics, this requires a design process
involving the committees, the administration, the faculty, the architect and all
consultants.
The other items listed require effort, but can typically be obtained fairly easily.
Sincerely,
FLANSBURGH ASSOCIATES, INC.
Robert Peirce, AIA
Flansburgh Associates, Inc: 77 North Washington Street Boston, MA 02114-1910 T 617-367-3970 F 617-720-7873 www.faiarchitects.com
12/20/02
645 - 1 Date:
Commonwealth of Massachusetts
DEPARTMENT OF EDUCATION
School Building Assistance
School District/Code
School Building/Code
LEA Contact/Title
Address
Comprehensive Capital School Construction Grant Application/Checklist
MA Zi
Telephone
Architect
Project Information
Type of School:
` -fiype of Project
Elementary Middle Secondary
New Addition/Renovation
Conversion
Vocational Grades
. Renovation.
Acquisition-
Alternatives to Construction
This Checklist is to be used in conjunction with School Construction Regulations (603 CMR 38.00) and the
application forms package attached. ,All items must be filed with the Department of Education. If previously
_
submitted, please put date of submission to the Department. _ _ _ _ _ _ _ _ _ _ _ _ _
LEA and ARCHITECTURAL REQUIREMENTS (Please check all documentation submitted to DOE)
1. Long Range Facilities Plan with VOTE of the School Committee
2. Rationale for Capital Construction (645-3)
3. _ Inventories of Existing School Space (645-4)
4. X Enrollment Projections (10 years)
5. _ VOTE to Appoint School Building Committee
6. Certified VOTE for design or construction
7 : Educational Specifications, as approved by the School Committee (VOTE) (645-5)
8. _ Scope of Work, including description of renovation or demolition, site work and equipment
9. _ Description of planned community and educational collaborative spaces (with Director sign-off),
as applicable'
10. _ Preliminary Schematic Drawings and site plan as approved by the School Committee (VOTE)
11. _ School Committee VOTE to approve proposed site
2. _ Proof of site ownership (Deed) or eminent domain proceedings
13 Approval of Local Conservation Commission
14. Approval of Local Historical Commission
12/20/02
Checklist: Page 2
5
16
17
18.
19.
20.
21.
22.
23.
24.
25.
26.
'7.
Each site must be reviewed and approved by the MA Historical Commission and a copy of such
approval submitted to the Department. (MHC form must be signed and submitted to SBA)
Request for School. Plan Review submitted to the Architectural Access Board. Copy of the form
and Certification by the Architect to be submitted to SBA
All building proposals must file a completed MEPA Review Thresholds. If any question in the
checklist is answered "yes", a MEPA Review is required. Applicant must enclose a certificate
with this application from the Secretary of Environmental Affairs that the MEPA Review has
been completed. Copy of signed form to be submitted to SBA
Construction/Project Manager Plan (645-6)
Reimbursement Incentive Points for Capital Projects (645-7)
Priority Ranking Checklist (645-8)
Form F (645-9) - Financial Plan
Certified VOTE of authorization of total project funds with copy of warrant of the vote.
Certified VOTE of Prop. 2 - Debt Exclusion and evidence of the expiration of any referendum
period if applicable
Copies of Required Local Approvals: Submit local water service and sewage disposal approval
along with Public Health approval; Submit public safety approval from an authorized public
official; Certification by local Building Inspector that final plans meet all current state and local
building codes. (645-10)
Preventive Maintenance Plan (645-12)
Contractor Certification Evaluation Questionnaire submitted to DCAM
Architect Certifications:
Architectural Access Board Submittal (645-11)
❖ Certification of no unapproved space changes from approved preliminary plans and
education specifications (645-11)
❖ Certification of compliance with Chapter 70B Regulations (645=11)
❖ Certification from architect that the bid specifications include the correct minority hiring
language per any local agreements with MCAD (645-I1)
❖ Certification that containment procedures consistent with SMACNA Guidelines have been
included in the planning and cost estimates (645-11)
Certification of Cost Effective Design (645-13)
28
29.
The town counsel or legal representative for the school district shall provide the Department a
letter as, to whether the city/town has/has not any issues or complaints pending with the
Massachusetts Commission Against Discrimination per Executive Order 237.
Final working construction documents and bid specifications in CD format
Final Application submission: Hard Copies of Original Certified Signed Vote of Authorization of
Total Project Funding and Prop 2_ override/debt referendum, including Warrants; and Original
Signed Form F. All other documents can be scanned onto the CD.
CD Format:
Please submit copies of.all application documents on a CD. The preferred format is PDF
including the final drawings. Other acceptable formats: JPG, TIFF, DOC (word files). For
Drawing formats: PLT, DWG (R14); PDF (preferred).
S`cHOGL BUILDING ASSISTANCE PROGRAMADMINISTRATIVE ADVISORY 02-2 12/23/02 1120 AM
a,S get things done . agencies . elected officials
;.i`J.r.e.. ;c Kf.S _Y)tt't'tJp7&' 1.` a i~ f1t.,ia Ifk?2 --select Program Area--
News District/School Administration Educator Services Assessment/Accountability Family & Community
L
=r Finance/Grants
School Finance: School Building Assistance
Recent Updates
Accounting & Auditing
Administrative Advisory 02-2
Chapter 70 Program
(Foundation Budget)
> Charter Schools
May 31, 2002
;s. DOE Budget
Federal Renovation Program
Vote to Proceed with Construction
. Grants. Information
As previously reported, most projects on the waiting list can expect
Nutrition Programs
" (School Lunch)
significant delays before receiving a grant. As part of the application
r. Per Pupil Expenditure Reports
process, districts must indicate whether they plan to begin construction
,a School Building Assistance
in advance of receiving their grant. Districts which plan to start
School Choice
construction in advance of receiving their grant must submit a
School Finance Regulations
resolution voted by any one of the following: town meeting, city council,
or school committee. The resolution
town council
board'of selectmen
M Special Education
,
,
should state:
Statistical Comparisons
a Transportation
• the name of the project;
Vocational Education • that the municipality [or regional school district] intends to start
Key contacts construction on the project prior to receiving its state grant;
u Links that the municipality [or regional school district] has been advised
by the Commissioner of Education that it may not receive the
state grant within the time period allowed by statute for
temporary borrowing; and
• that the municipality [or regional school district] is legally
authorized to issue long-term bonds for this project prior to
receipt of the state grant.
The copy of the resolution submitted to the Department should be
certified by the secretary, cleric, or other appropriate official, and should
indicate the date of vote. Projects placed on the waiting list will not
receive an authorization to proceed with construction without this
submission.
Deferred Construction
Applicants who will be deferring the start of construction until at least
the end of the next fiscal year may delay the submission of their final
working construction documents and bid specifications (item 29 on the
SBA application checklist) by requesting deferred final design status.
The following procedures will apply:
litti)://fiiiatice].doe.mass.edit/sbtiildixig/adiniii_adVO2_2.htinl Page I oft
Si'I-IOOL BUILDING ASSISTANCE PROGRAMADMINISTRATIVE ADVISORY 02-2 12/23/02 11:20 AM
1. Applicants must submit a letter with their application materials
requesting deferred final design status. For current (FY02)
applicants, this means that you will not be starting construction
until FY04 at the earliest.
2. Applicants requesting deferred final design status need not submit
final working construction documents and bid specifications at this
time. In addition, any required local approvals under item 24 and
architect certifications under item 27 which require final plans and
specifications also maybe deferred.
3. Educational specifications, site plans, and building schematics will
still be required. In addition, it is expected that sufficient design
work will be completed to provide accurate project cost estimates.
4. Applications for deferred final design status which meet all other
program requirements and are approved by the Commissioner
will be placed on the waiting list. However, authorization to
proceed with construction will be withheld.
5. All deferred items must be submitted to the. Department no later
than 12o days prior to the solicitation of bids for the general
contract. Construction may not begin until such items have been
approved by the Department and the applicant has been
authorized to proceed with construction.
6. It is expected that the final plans and specifications will conform
substantially to the preliminary plans, and that the architects will
so certify. Any significant deviations in scope, size, or cost of the
project will require additional review, and may result in the
project being removed from the waiting list and treated as a new
application.
Initial grant payment amounts will not be adjusted to reflect increases
in project costs due to the delay in construction. Any such adjustments
allowable under program regulations will be made following completion
of construction and submission and review of audit material.
Sic, +t. t.vct r N47wrxt~x~: rr7:X` ~a1 u"`'1t~c7t 1t3n Search . Site Map . Privacy . Site Info . Contact DOE
hItI)://financeLdoc.mass.edu/sbit iIding/admin_adv02_2.IitmI Page 2 of 2
0S
yl y S
- J c~ t
W W z
~0
? p
o / o o~
f.
,lam \ W
~UW
p ~ t
t, a
ck
D<
CD
0 0
m m
3
M
00
Z
Q.
N
O
~
3
w
m
M
r
t V
M
m
0
w
O
oa
O
w
d
f
t-
1A
C
n
1=<
1 LZ
i 4
L
L/
a
i
9 ~ 9
December 19, 2002
Mr. Robert Peirce
Flansbutgh Associates
77 North Washington St.
Boston, MA 02114
Re: Preliminary Geotechnical Explorations
Reading Memorial High School
Reading, Massachusetts
Dear Mr. Peirce:
The purpose of this letter is to summarize the findings of the preliminary explorations conducted at
the referenced site. This work was authorized and conducted in accordance with the scope of
services and terms stated in our proposal to you dated December 3, 2002.
Background
We understand that the Town of Reading is considering constructing an addition between the field
house and the school administrative offices as well as an addition in an open courtyard area.
Concern was raised regarding the potential presence of peat lying within the area located between
the field house and the administrative offices where there are many underground utilities.
Although the original preliminary exploration program outlined by FAI consisted of 1 boring in the
courtyard and 4 borings within the lower parking area, only 2 borings were completed because of the
numerous and uncertain location of underground utilities. As a result 1 boring was taken in the
courtyard and 1 boring was taken within the lower parking area.
The location of the explorations is shown on the attached Exploration Location Plan. Soil test
boring logs were prepared by Weber Engineering Associates, LLC and are also attached to this letter
for reference. The findings are discussed herein.
Courtyard Area
Boring B-1 was conducted within the courtyard area at the approximate location shown on the
Exploration Location Plan. Three attempts were made with the hollow flight augers to drill beyond
a depth of 4.5-ft. The first attempt was terminated at a depth of 4.5-ft below ground surface when
the auger encountered refusal. In this case, refusal is the inability to advance the borehole further
without using rock coring methods.
Otis) .29- I.a ti Sz.s J fit) - 93 C3rir,rcl~ M. A
! 6
11a °e
During the second and third attempt, the borehole was first moved a distance of 5-ft and then 10-ft.
In each subsequent attempt, auger refusal was encountered at a depth of approximately Oft and 3-ft
below ground surface. In most cases, if a boulder caused refusal, when the location was moved, the
borehole could be advanced further. However, since each of these three attempts encountered
refusal at relatively the same depth, it is our opinion that the nature of the refusal material is
probably bedrock rather than boulders. Coring was not attempted to verify the nature of the
material.
Based on the limited explorations undertaken, it appears that construction within the courtyard area
might encounter bedrock at a relatively shallow depth. You should be aware however that the
bedrock surface is probably uneven and the depth to bedrock will vary.
Lower Parking Area
Because of the numerous underground utilities and their uncertain location within this area, one
boring rather than 4 borings was undertakers. Dig Safe and Town representatives declared the
location of boring B-2 free of utilities.
Similar to the courtyard area, the first borehole attempt encountered auger refusal at a depth of Sft
below ground surface. The material at this location consists of approximately 2-ft of fill underlain
by glacial till to the depth explored (5-ft). The borehole was moved approximately 5-ft and
continued to a depth of 16.5-ft below ground surface. The nature of the refusal material within this
area is probably a boulder. The material lying below the surface fill consists of very dense glacial
till and we found no visual evidence of peat at this location. Groundwater was encountered at a
depth of 5-ft below ground surface.
As explained previously these explorations were not widespread within this area because of the
utilities. The fact that we did not encounter peat at boring B.2 does not preclude the possibility that
peat could be present closer b the field house. If peat was encountered and it was to be removed
from within the building footprint, the presence of a high groundwater level will require a
dewatering effort. Dewatering might also be required during construction even if peat is not present
depending upon the building grades.
We are pleased to have this opportunity to assist. If you have any questions regarding this letter or
need additional information, please do not hesitate to call.
Very truly yours,
WEBER ENGINEERING ASSOCIATES, LLC
Richard P. Weber, P.E., Manager
Attachments:
Exploration Location Plan
Test Boring Logs
(51 08) 8 S +i ~ 4 92 B1' . i t 1 . 1' `1 k. , l , ion . M.
B-1B
B-IA
B-1
(Three attempts)
School
Administration
Building
B-2, B-2A (Two attempts)
40 4D
Notes:
1. Drilling conducted by Soil Exploration Corp. on December 19, 2002.
2. Locations of explorations based on tape measurement and are approximate.
Weber Engineering Associates, LLC No Scale Exploration Location Plan
Geotechnical Engineers December 2002 Reading Memorial High School
Holliston, Massachusetts I I Reading, Massachusetts
t
TEST BORING LOG
Sheet 1
Weber Engineerin
Associates
LLC
,
g
GeotechnicaI Engineers
Reading High School
BORING NO. B-i
Holliston, Massachusetts
Reading, Massachusetts
DATE: 12/19/02
Groundwater Observations
Ground Elev
ti
a
on:
Date Started: 12/19/02
Date
Depth
Casing
Stabilization Time
Date Finished
12/19/02
(ft)
:
Driller: Soil Exploration Corp
12/19
Dry
At completion
Depth
S
Sample
(ft)
No.
Pen
Depth
Blows 6"
Type
Strata
Visual Description
Note
Rec.
0
1
1
24/18
0-2
11-7-12-18
Ss
Fill
6" topsoil to brown fine to medium SAND little Silt
2
little Gravel
3
4
3' to 4.5'_
Auger grinding at 4' depth. Auger refusal at 4.5'.
5
Move 5' and continue
6
7
B-1 A Grinding at 3' depth. Auger refusal at 4'.
8
Angular gravel in spoils. Move 10' and continue
9
10
B-1B Grinding at 2' depth. Auger refusal at 3'.
11
12
Possible bedrock or boulders.
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
Notes:
Sample Type/ Field Test
Proportioned Used
ss = split spoon
Trace 0 - 10%
Casing
Sampler
Core
A = Auger
Little 10 - 20 %
Type
HSA
s s
U = Undisturbed
Some 20 - 35%
Tv = Pocket Torvane
And 35-50%
ID
4
1-3/8"
Pp = Pocket Penetrometer
Hammer
140 Ibs.
TEST BORING LOG
Sheet 1
Weber Engineering Associates, LLC
G
h
i
l E
Reading High School
BORING NO. B-2
eotec
n
ca
ngineers
Holliston, b'lassachusetts
Reading, Massachusetts
DATE: 12/19/02
Groundwater Observations
Ground Elevation:
Date Started: 12/19/02
Date
Depth
(ft)
Casing
Stabilization Time
Date Finished: 12/19/02
12/19
5
5'
During sampling
Driller: Soil Exploration Corp
Depth
Sample
(ft)
Pen /
"
Type
Strata
Visual Description
Note
No.
Depth
Blows / 6
R
Rec.
0
1
1
24/18
0-2
7-16-21-26
Ss
Fill
4" topsoil to tan fine to medium SAND some Silt, 2"
2
-2'-.
topsoil
3
4
Glacial Till
5
2.
4/2
5-5.3
1004"
SS
_5'_
Wet brown / gray fine SAND and SILT trace Gravel
6
7
Auger refusal at 5'. Possible boulder
8
9
10
Moved boring 5' and continued
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
Notes:
Sample Type / Field Test
=
li
Proportioned Used
0
T
101/
Casing
Sampler
Core
ss
sp
t spoon
race
-
o
A = Auger
Little 10- 20 %
Type
HSA
ss
U = Undisturbed
Some 20 - 35%
ID
4
1-3/8"
Tv = Pocket Torvane
And 35-50%
Pp = Pocket Penetrometer
Hammer
140 lbs.
TEST BORING LOG
Sheet i
Weber Engineering Associates, LLC
Reading High School
BORING NO. B-2A
Geotechnical Engineers
Reading, Massachusetts
DATE: 12/19/02
Holliston, Massachusetts
Groundwater Observations
Ground Elevation:
Date
Depth
Casing
Stabilization Time
Date Started: 12/19/02
(ft)
Date Finished: 12/19/02
r
ti
C
S
il E
l
ill
D
12/19
5
In
During sampling
p
ora
on
o
o
xp
er:
r
Depth
Sample
ti
i
l D
Note
Type
Strata
on
escr
p
Visua
(ft)
No.
Pen /
Depth
Blows / 611
.
Rec
0
I
Auger to 5'
2
3
4
5
6
1
18/6
5-6.5
24-48-43
Ss
Wet brown fine SAND little Silt some angular Gravel
7
8
9
Glacial Till
10
11
2
18/0
10-11.5
20-30-38
Ss
No recovery
12
13
14
15
16
3
18/18
15-16.5
39-39-30
Ss
-16.5'_
Brown fine SAND some Silt little angular Gravel
17
18
Bottom of boring
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
Notes:
Sample Type / Field Test
Proportioned Used
Casing
Sampler
Core
ss = split spoon
Trace 0- I0%
A = Auger
Little 10 - 20 %
Type
HSA
ss
U = Undisturbed
Some 20 - 35%
0
1D
4
1-3/8"
Tv = Pocket Torvane
And 35-50
1.
Pp = Pocket. Penetrometer
Hammer
140 lbs.
Lr'
Il^` ,
r, V
.-t
3i
S
6
R
Hl
g
lU
0
0
Q
Q-
71
0
0
Q
~i
5
a
Hi
F,L.,
r.
,
Lz,`
r'
f:°
F ,
F'
I!si:'
5.;.
~ ~
Q
0
0
8
~
~
~ ~
~
s
~
~
~
~t
~
~
~
~
r ~
O
C
O
O
O
~ g
~
4
S
Proposed - Article:
Complete renovation of the 1970 Areas of RMHS (Science Wing, Library Wing and
Field House) and replacement of the 1953 areas with new facilities to include
reorganization of interior space to meet all educational program requirements
This proposal is the result of an extensive evaluation of existing physical conditions at
RMHS as well as a thorough assessment of educational program space needs. This
evaluation, undertaken with the assistance of Flansburgh Associates, Inc. was one of the
charges to the School Building Committee (SBC) by Town Meeting on April 25, 2002.
The SBC has made this proposal after extensive review of and public comment on three
alternative approaches to address the physical and educational deficiencies identified in
this assessment. Alternative approaches included:
1. Complete renovation of the existing facilities, reorganization of interior space to
meet all educational program requirements. This option provided that no new
space would be constructed.
2. Complete renovation of all existing facilities with the exception of the original
arts/industrial arts wing that would be demolished. A new cafeteria would be
constructed to connect the 1953 portion of the building with the 1970 library
addition. Interior space would be reorganized to meet all educational program
requirements.
3. Complete renovation of the 1970 Areas of RMHS (Science Wing, Library Wing
and Field House) and replacement of the 1953 areas with new facilities to include
reorganization of interior space to meet all educational program requirements.
(The Proposal)
When the project is completed, RMHS will provide the needed facilities for the current
and anticipated educational program for a projected student population of as many as
1480 students. This includes the projected high school population (grades 9-12) as well
as the RISE pre- school program. The 275,000 square foot completed facility will be
approximately 55% renovated space and 45% new space.
Included in the proposal is the substantial upgrading of athletic facilities to include
replacement of the football stadium with a new state-of-the-art multi-purpose stadium to
support football, soccer and other field sports. Off-street parking will be increased to
accommodate 600 cars (there are 270 spaces today).
Renovations within existing facilities will include replacement of virtually all
mechanical, electrical and plumbing systems. Windows will be replaced with insulating
glass; roofs and walls will be repaired to increase thermal efficiency to current codes and
standards.
40
Primary attributes of the Proposal
The Proposal, Option 3, was determined to be the best alternative among the three
principally due to the fact that while each option requires extensive construction, the
Proposal will result in the least disruption of the ongoing educational program, will not
require extensive relocation of students and teachers and will, when completed, provide a
more easily managed, lower operating cost facility with spaces designed to match the
educational and community needs of the Town of Reading.
The following is an outline of the key attributes of the Proposal:
• Completed facility: 273,000 SF
• 56% Renovated Space, 44% New Construction
• 31-33 Months Construction
• $54 million total cost, $24.5 million Town of
Reading cost
• All elements of the educational program are included and in the proper relationship to
other programs (Math is next to Science; Administration is adjacent to the main entry;
etc.)
• All spaces meet MAAB/ADA requirements for accessibility.
• All classroom spaces meet program space goals.
• Science Labs, Music, Art and Drama programs will be supported through new and or
better facilities, furniture and equipment.
• Media Center consolidates on one floor, improving control and use.
• Cafeteria (new construction) creates new school "Commons".
• Access issues of older facilities are eliminated by consolidation in new space and
connection to Field House.
• Auditorium is replaced with design to serve music and drama use as well as community
uses.
• New separate entry for Auditorium will be created with new adjacent off-street parking.
Access control will be improved.
• Incorporation of structured artificial turf on multipurpose field and one practice field will
substantially improve field capacity.
• Automobile access will be improved by relocating curb cuts onto Oakland Road.
Substantial additional parking will be created on site.
• Demolition and replacement of "1950's building" will increase first cost while reducing
long-term maintenance costs.
• Educational program will not occupy space under construction. Single relocation to new
space will be completed after new construction.
• Administrative Offices will maintain control of primary entrance locations during all
phases of construction.
• Inconvenience/distraction for teachers and students is lower during construction -ala
Parker Middle School project.
• Opportunities for Contractor to fail in meeting schedule are lower due to two simpler
construction phases. Failure to complete a phase would have no impact on users.
Budget:
Gross SF 273,000
Construction Cost
$38,500,000
Contingencies
$ 6,600,000
Professional Fees
$ 3,500,000
Furniture & Equipment
$ 1,500,000
Technology
$ 2,300,000
Other Project Costs
$ 1,600,000
TOTAL
$54,000,000
11~~
SBA Reimbursement $29,500,000
Reading Cost $24.500,000
Town of Reading
16 Lowell Street
Reading, MA 01867-2685
FAX: (781) 942-9070 TOWN MANAGER
Email: townmanager@ci.reading.ma.us (781) 942-9043
MEMORANDUM
TO: School Committee
School Building Committee
Bylaw Committee
FROM: Peter 1. Hechenbleikner
DATE: December 20, 2002
RE: Warrant - Special Town Meeting
Attached is the Warrant for the Special Town Meeting on January 13, 2003. Please get all
background material to me by noon on December 24, 2002.
COMMONWEALTH OF MASSACHUSETTS
Middlesex, ss. Officer's Return, Reading:
By virtue of this Warrant, I, on notified and warned the
inhabitants of the Town of Reading, qualified to vote on Town affairs, to meet at the
place and at the time specified by posting attested copies of this Town Meeting Warrant
in the following public places within the Town of Reading:
Precinct 1
Precinct 2
Precinct 3
Precinct 4
Precinct 5
Precinct 6
Precinct 7
Precinct 8
J. Warren Killam School, 333 Charles Street
Registry of Motor Vehicles, 275 Salem Street
Reading Police Station, 15 Union Street
Joshua Eaton School, 365 Summer Avenue
Town Hall, 16 Lowell Street
Alice M. Barrows School, 16 Edgemont Avenue
Reading Library, Local History Room, 64 Middlesex Avenue
Charles Mobil on the Run, 1330 Main Street
The date of posting being not less than fourteen (14) days prior to January 13. 2003, the
date set for the Special Town Meeting in this Warrant.
I also caused an attested copy of this Warrant to be published in the Reading
Chronicle in the issue of
Daniel W. Halloran Jr., Constable
A true copy. Attest:
Cheryl A. Johnson, Town Clerk
1
SPECIAL TOWN MEETING
(Seal)
COMMONWEALTH OF MASSACHUSETTS
Middlesex, ss.
To any of the Constables of the Town of Reading, Greetings:
In the name of the Commonwealth of Massachusetts, you are hereby required to
notify and warn the inhabitants of the Town of Reading, qualified to vote in elections and
Town affairs, to meet at the Reading Memorial High School Auditorium, 62 Oakland
Road in said Reading, on Monday, January 13, 2003, at seven-thirty o'clock in the
evening, at which time and place the following articles are to be acted upon and
determined exclusively by Town Meeting Members in accordance with the provisions of
the Reading Home Rule Charter.
ARTICLE 1 To hear and act on the reports of the Board of Selectmen, Town
Accountant, Treasurer-Collector, Board of Assessors, Director of Public Works, Town
Clerk, Tree Warden, Board of Health, School Committee, Contributory Retirement
Board, Library Trustees, Municipal Light Board, Finance Committee, Cemetery Trustees,
Community Planning & Development Commission, Conservation Commission, Town
Manager and any other Board or Special Committee.
Board of Selectmen
Background: This Article appears on the warrant of every Town Meeting. There are no
known reports to be given under this article.
Finance Committee Report: No report.
Bylaw Committee Report: No report.
ARTICLE 2 To choose all other necessary Town Officers and Special
Committees and determine what instructions shall be given Town Officers and Special
Committees, and to see what sum the Town will raise by borrowing or transfer from
available funds, or otherwise, and appropriate for the purpose of funding Town Officers
and Special Committees to carry out the instructions given to them, or take any other
action with respect thereto.
Board of Selectmen
Background: This article is included on the warrant for all Town Meetings. One
instruction may be given, which would to be to extend the deadline for passing papers
for the sale of the former landfill. At this time it is expected that the passing of papers
will be on or about January 15, 2003
Finance Committee Report: No report.
Bylaw Committee Report: No report.
2
ARTICLE 3 To see if the Town will vote to amend the FY 2003 - FY 2012,
Capital Improvements Program as provided for in Section 7-7 of the Reading Home Rule
Charter and as previously amended, or take any other action with respect thereto.
Board of Selectmen
Background: This article appears on the warrant for every Town Meeting. At this Town
Meeting, an amendment to the adopted Capital Improvements Program will be needed
by adding project
"BL-S-19 NEW ELEM. SCHOOL ADDITIONAL FUNDING 2500 CO",
which indicates an increase in debt authorization in the amount of $2,500,000, subject to
a debt exclusion vote. This is the subject matter of Article 6 on this Warrant.
The Capital Improvements Program attached to this report shows the change that would
be required.
No change is needed for the RMHS project, which is already in the Capital Improvement
Program (B-S-011) in two line items for a total of $59.5 million. This amount is greater
that that proposed in Article 5.
Finance Committee Resort:
Bylaw Committee Report: No report.
ARTICLE 4 To see if the Town will vote to raise by borrowing, whether in
anticipation of reimbursement from the State under Chapter 44, Section 6,
- Massachusetts General Laws, or pursuant to any other enabling authority, the sum of
one million eight hundred thousand dollars ($1,800,000) for the improvement to Walkers
Brook Drive and related areas pursuant to the approved PWED grant for this purpose, or
take any other action with respect thereto.
Board of Selectmen
Background: The Town is the successful recipient of a Public Works Economic
Development grant from the Commonwealth of Massachusetts (PWED) in the amount of
$1,800,000 for the improvements to Walkers Brook Drive as part of the development of
the landfill site. We have received the grant announcement, and have executed all
documents related to the grant. The grant is given as a reimbursement to the Town, and
we therefore need to set up the project exactly like a Chapter 90 project. We do not
expect to sell any debt for the project, but need the authorization in the event that
reimbursements are not made in a schedule that we need.
Finance Committee Report:
Bylaw Committee Report: No report.
ARTICLE 5 To see what sum the Town will raise by borrowing, or transfer
from available funds, or otherwise, and appropriate for the purpose of making
extraordinary repairs and/or additions to the Reading Memorial High School at 62
Oakland Road, including the costs of engineering and architectural fees, plans,
documents, cost estimates, and related expenses incidental thereto and necessary in
connection therewith, said sum to be expended by and under the direction of the School
Committee; and to see if the Town will vote to authorize the School Building Committee,
3
the School Committee, or any other agency of the Town to file applications for a grant or
grants to be used to defray the cost of all or any part of the cost of the project; and to
see if the Town will vote to authorize the School Committee to enter into all contracts
and agreements as may be necessary to carry out the purposes of this Article; provided
however that any borrowing authorized by this Article and any appropriation subject to
this Article shall be contingent upon the passage of a debt exclusion referendum
question under General Laws Chapter 59 s 21c within 90 days of the close of this
Special Town Meeting; or take any other action with respect thereto.
School Building Committee
Background:
Finance Committee Report:
Bylaw Committee Report: No report.
School Building Committee Report:
ARTICLE 6 To see what additional sum the Town will raise by borrowing, or
transfer from available funds, or otherwise, and appropriate for the purpose of
constructing a new school and associated recreational facilities:
On land off Dividence Road shown on Reading Board of Assessor's Rev.
January 1, 1981 Map 207 as Lot 3 consisting of 2.0 acres and Lot 4 consisting
of 9.6 acres, which land was acquired by the Town for school and recreation
purposes by order of taking dated April 13, 1970, recorded in the Middlesex
South District Registry of Deeds in Book 11831, Page 432,
including the costs of original furnishings and equipment, landscaping, paving and other
site improvements, engineering and architectural fees, plans and specifications,
inspection fees, relocation costs, contingencies and related expenses incidental thereto
and necessary in connection therewith, said sum to be expended by and under the
direction of the School Committee, as an addition to, and in conjunction with, the sum
authorized by vote under Article 4 of the Warrant for the Special Town Meeting of
December 7, 1998; and to see if the Town will vote to authorize the School Committee or
any other agency of the Town to file applications for a grant or grants to be used to
defray all or any part of the cost of construction and related matters of said new school
and associated recreational facilities, and to see if the Town will vote to authorize the
School Committee to enter into all contracts and agreements as may be necessary to
carry out the purposes of this Article; provided however that any borrowing authorized by
this Article and any appropriation subject to this Article shall be contingent upon the
passage of a debt exclusion referendum question under General Laws Chapter 59 s 21 c
within 90 days of the close of this Special Town Meeting; or take any other action with
respect thereto.
School Committee
Background:
Finance Committee Report:
4
Bylaw Committee Report: No report.
School Committee Report:
ARTICLE 7 To see if the Town will vote to amend one or more of the votes
taken under Article 12 of the Warrant of the Annual Town Meeting of April 22, 2002,
relating to the Fiscal Year 2003 Municipal Budget, and see what sum the Town will raise
by borrowing or transfer from available funds, or otherwise, and appropriate as the result
of any such amended votes for the operation of the Town and its government, or take
any other action with respect thereto.
Board of Selectmen
Background: In the event that either or both of Articles 5 and 6 are approved by Town
Meeting, the Board of Selectmen has voted to hold a Special Election in February for the
voters to determine whether or not to approve the debt exclusions for either or both of
these two projects.
The Town has approved a budget for the current fiscal year for elections and registration
based on the 3 scheduled elections. There is no money in the budget for a Special
Election.
Therefore, an amendment to the existing Elections and Registration budget in the
amount of $13,500 will be needed to fund the cost of a special election.
The funding of the Election would be from Free Cash, which has a current balance of
over $1,200,000.
Finance Committee Report:
Bylaw Committee Report: No report.
and you are directed to serve this Warrant by posting an attested copy thereof in at least
one (1) public place in each precinct of the Town not less than fourteen (14) days prior to
January 13, 2003, the date set for the meeting in said Warrant, and to publish this
Warrant in a newspaper published in the Town, or by mailing an attested copy of said
Warrant to each Town Meeting Member at least fourteen (14) days prior to the time of
holding said meeting.
Hereof fail not and make due return of this Warrant with your doings thereon to
the Town Clerk at or before the time appointed for said meeting.
Given under our hands this 17th day of December, 2002.
Camille W. Anthony, Chairman
Matthew Cummings, Vice Chairman
Richard W. Schubert, Secretary
George V. Hines
Gail F. Wood
SELECTMEN OF READING
Daniel W. Halloran Jr., Constable
6