HomeMy WebLinkAbout1993-01-26 ad Hoc School Building Committee MinutesSCHOOL BUILDING COMMITTEE
MEETING MINUTES
JANUARY 26, 1993
The meeting was called to order at 7:10 PM.
Those in attendance were: M. Cowell, R. D'Antona, D. Farnham, R. Graham, R.
Grasso, J. Lupi, B. Poock, R. Sanstad, D. Williams and Architect D. Finney.
David Finney presented the cost estimates for the elementary school projects
(attached). After considerable discussion, it was felt that the significant cost
growth required further definition and clarification. Of particular concern is the
MEP portion of the Joshua Eaton project. Mr. Finney will provide the committee
with additional detail at the February 16th meeting. In the interim, R. Sanstad
agreed to set-up a meeting with Fire Chief Don Wood regarding the potential
requirement for a full sprinkler system in both schools at a cost in excess of
$225K. (Note: Following the SBC meeting, D. Farnham and R. Sanstad met the Fire
Chief in the corridor of Town Hall and initiated discussion on the subject. It was
agreed that only the new construction would require the sprinklers (already
planned) and that the attic area of Eaton would have sprinklers installed. This
will result in a significant savings to the project.)
R. Sanstad will set-up a meeting with the Town Manager and Treasurer to review
the bonding options and strategy. R. D'Antona and R. Graham will also
participate in this meeting. In addition, R. D'Antona will communicate the new
cost information to M. Cummings and Dr. Munnelly. It is important to note that
these costs are considered preliminary and have not yet been fully analyzed.
They do, however, provide us with enough information that we can now begin our
planning process.
Joe Lupi presented the results of his sub-committee on screening the submitted
proposals for the Parker project. They have narrowed the final list of architects
down to six candidates (attached list). The sub-committee will contact these
six and schedule them in for the full committee to interview. It is planned that
three will come in on February 2nd and three on February 9th. After all
interviews are completed, the full committee will make the final selection. The
committee agreed to invite Jack Delaney, Principal of Parker Middle School, to
participate in the interview process.
The meeting was adjourned at 10:00 PM.
M
January 26, 1993
To Reading School Building Committee:
The following firms are recommended for further consideration on
the Parker School Project:
1) TAMS Consultants, Inc.
38 Chauncy Street
Boston, Ma. 02111
2) Keys Associates
one Moody Street
Waltham, Ma. 02154
3) DiNisco Kritsch and Associates
87 Summer Street
Boston, Ma. 02110
4) The Design Partnership of Cambridge
88 Sherman Street
Cambridge, Ma. 02140
5) Symmes, Maini and McKee Associates
1000 Mass. Ave.
Cambridge, Ma. 02138
6) Earl R. Flansburgh and Associates
77 N. Washington Street
Boston, Ma. 02114
Joe Lupi
David Williams
Margaret Cowell
Bob Grasso
rch. & Struct.
posts Reading Elementary Schools
1/25/92 Birch Meadow School
B. Essential
A. Bask Costs for
Renovation
Area-SF Unit Cost
Growth
Costs
C. Combined Costs
New Construction:
1
Arch & Struct
8,100$66
$534,600
$534,600
Entry Stairs, rails &
2
canopy
$28,600
$28,600
Renovation
1
Demolition for renovation
$36,800
$36,800
2
Remove VAT at renov areas
$4,000
$4,000
3
Rough Construction
$30,700
$30,700
interior ramp
$3,200
Partitions
$12,600
Doors & Frames
$14,900
4
Kitchen Equip-rework existing
$10,000
$10,000
Finish (renov. areas only)
1
Vinyl Tile Flooring
$5,300
$5,300
2
Resilient base
$1,000
$3,000
$4,000
4
Interior paint
$6,000
$6,000
5
Ceilings
$5;600
$5,600
6
Casework &specialties
$7,000
$7,000
Windows
1
Reglaze plastic windows
1520$12.50
$19,000
$19,000
4
Paint windows & trim
$10,800
$10,800
5
Replace Exterior Doors
$36,600
$36,600
Exterior
1
Roof penetrations
$4,000
$4,000
Flashing & sealing at new
2
construction
$7,000
$7,000
3
re-point masonry (partial)
$1,000
$1,000
4
Expansion joint
$4,000
$4,000
Handicapped
Accessibility
1
Corridor door hardware
$11,200
$11,200
2
Interior paired doors
$11,200
$11,200
3
Toilet access. & parts.
$3,900
$3,900
Toilet room doors &
4
frames
$4,800
$4,800
OTALS $747,500 $33,800 $781,300
9205ESTi3.XLS Page 1
Reading Elementary Schools
Mech, Elec &
Plumbing Costs Birch Meadow School
1/25/93
S. Other
A. Basic Costs for
Renovation
Growth
Costs
C. Combined Costs
New Construction
Heating & Ventilating
$80,000
$80,000
Plumbing
$32,000
$32,000
Electrical
$48,000
$48,000
Fire Protection
$20,000
$20,000
Total New Const.
$180,000
$180,000
Renovation
Heating & Ventilating
$50,000
$50,000
Plumbing
$20,000
$20,000
Electrical
$100,000
$100,000
Fire Protection
$115,000
$115,000
replace oil tank
$30,000
$30,000
new water service
$10,000
$10,000
Total Renovation
$325,000
$325,000
- --..TOTAL M/E/P/FP
$505,000
$505,000
S. Other
Landscape Costs
A. Bask Costs
Renovation
(note 1)
costs
C. Fulf Renovation Costs
Clear/grub/Site Prep
$6,500
$6,500
Paving & Earthwork
$0
$40,000
$40,000
Curbs
$6,000
$6,000
Bike racks
Planting
$10,000
$10,000
Lighting
$7,500
$7,500
Site drainage
$12,500
$12,500
Loam & Seed
$0
$7,500
$7,500
Sidewalks (includes paved
play)
$0
$10,500
$10,500
Ledge (allowance
$60,000
$0
$60,000
Total Site Cost
$79,000
$81,500
$160,500
Note 1: This reduced scope is carried over from the 1989 estimate.
Work:
- Replacement of corridor ceilings
- Removal & replacement of Vinyl Asbestos the (except at altered areas).
- New kitchen equipment
- Removal of contaminated soil at Oil tank, if required
- Asbestos removal (except selected VAT)
- Roof repair
- Painting of ceilings
- Repair of classroom cabinets
9205ESTB.XLS Page 2
Cost Est. Summary Reading Elementary Schools
1/25/92 Birch Meadow School
A. Basic Costs for
Growth
C. Full Renovation Costs
Construction Costs
Arch & Struct Costs
$747,500
$781,300
M/E/P/FP Costs
$505,000
$505,000
Site Costs
$79,000
$160,500
TOTAL RAW COSTS
$1,331,500
$1,446,800
G.C. OH&P (15%)
$199,725
$217,020
Contingency (12%)
$159,780
$173,616
TOTAL CONST. COST
$1,691,005
$1,837,436
Indirect Costs
Site Exploration
Survey
$5,000
$5,000
Borings
$2,000
$2,000
Design Costs
Arch/Eng.
$188,000
$204,000
Food Service Cons.
$3,000
$3,000
Fum & Equip Cons.
$4,000
$4,000
Bidding
Bid Sets
$6,000
$7,000
Bond counsel
$10,000
$10,000
Construction
Clerk (pt time, 15 mo)
$30,000
$30,000
Furniture & Equipment
(new Const only)
$40,000
$50,000
TOTAL PROJECT COSTS
Birch Meadow School
$1,979,005
$2,152,436
9205ESTB.XLS Page 3
Arch. & Struct. Costs
1/25/92
New Construction:
1
Arch & Struct
Entry Stairs, rails &
2
canopy
Renovation
1
Demolition for renovation
Demolition windows &
2
glass block
Remove VAT at renov
3
areas
4
Rough Construction
Built-up floors
Partitions
Doors & Frames
5
Crawl space
vents & vapor barrier
floor insul
meth ventilation
crawl space stnxx.
attic vents
6
KAchen Equip
Finish (renov. areas only)
1
Vinyl Tile Flooring
2
Resilient base
3
Acoust ceilings
4
Interior paint
5
CT wainscote
Windows
1
Replace Metal windows
replace glass block w/ Kal-
2
wall
Wood windows-add
3
storms
4
Paint windows & trim
Replace ext louvers &
5
enlarge m.o"s
Exterior
1
Roof penetrations
Flashing & sealing at
2
new construction
3
re-point masonry
4
cupola
paint, caulk, repair flashing E
siding
Structural repairs
Handicapped
Corridor door
Accessibility
1
hardware
2
New exterior doors
3
New int, door pairs
TOTALS
Area-SF Unit Cost
12,300$70
1070 $36
$14,000
$1,000
Reading Elementary Schools
Joshua Eaton School
B. Essential
A. Bask Costs for Renovation C. Combined
Growth costs costs
$35,000
$57,300
$7,000
$5,000
$10,900
$2,000
$11,700
$15,600
$1,300
$33,900
$19,900
$8,300
$8,000
$4,000
$15,000
$861,000
$35,000
$57,300
$7,000
$8,400
$67,500
$66,200
$5,000
$10,900
$2,000
$11,700
$15,600
$1,300
$38,520
$33,900
$19,900
$8,300
$11,000
$8,000
$4,000
$15,000
$15,000
$18,100
$10,500
$3,900
$1,197,400 $137,620 $1,335,020
9205ESTA.XLS Page 1
Mech, Elec & Plumbing Costs
1/25/93
New Construction
Renovation
TOTAL M/E/P/FP
Landscape Costs
Total Site
Heating & Ventilating
Plumbing
Electrical
Fire Protection
Total New Const.
Heating & Ventilating
Plumbing
Electrical
Fire Protection
TotalRenovation
Site Prep
Paving & Earthwork
Building Edge
Curbs (conc. on one side
of drive)
Bike racks
Planting
Lighting
Site drainage
Loam & Seed
Relocate play equip
Courtyard
Sidewalks (includes paved
play)
$99,350 $165,850
Note 1: This provides only 1 coat asphalt over existing paving for drives, parking & bus bop.
This includes new paving requested by the Fire Chief.
Items not in Project Scope of Work:
- Replacement of condor ceilings
- Removal & replacement of Vinyl Asbestos tile (except at altered areas).
- New kitchen equipment
- Oil tank removal & replacement
- Asbestos removal (except in crawispace and selected VAT)
- Roof repair
Reading Elementary Schools
Joshua Eaton School
e. other
A. Basle Costs for Renovation
C. Combined
Growth
costs
costs
$123,000
$123,000
$49,200
$49,200
$73,800
$73,800
$30,750
$30,750
<$i£I`>
$276,750
<<
$453,000
$188,000
$188,000
$302,000
?3t<=
><<
$113,000
$1,056,000
$1,332,750
$1,332,750
S. Other
Renovation
C. Full Renovation
A. Basle Costs
Costs
Costs
$8,500
$8,500
(note 1) $0
$50,000
$50,000
$15,000
$15,000
$4,000
$4,000
$0
$1,600
$1,600
$0
$15,000
$15,000
$0
$15,000
$15,000
$24,000
$24,000
$0
$9,000
$9,000
$5,000
$5,000
$10,000
$10,000
$0
$8,750
$8,750
9205ESTA.Xt_S Page 2
t
Cost Est. Summary
Reading Elementary Schools
1/25/92
Joshua Eaton School
A. Bask Costs for C. Full Renovation
Growth
Costs
Construction Costs
Arch & Strict Costs
$1,197,400
$1,335,020
M/E/P/FP Costs
$1,332,750
$1,332,750
Site Costs
$66,500
$165,850
TOTAL RAW COSTS
$2,596,650
$2,833,620
G.C. OH&P (15%)
$389,498
$425,043
Contingency (12%)
$311,598
$340,034
TOTAL CONST. COST
$3,297,746
$3,598,697
Asbestos Removal
Related Costs
(crawlspace)
Pipe insulation
<>*C
$67,000
contaminated soil
$47,500
Re-locate 2 temp.
classrooms
$29,000
$29,000
Indirect Costs
Site Exploration
Survey
$5,000
$5,000
Borings
$2,000
$2,000
Design Costs
Arch/Eng.
$334,200
$357,500
Asbestos Cons.
$11,000
$11,000
Food Service Cons.
$3,000
$3,000
Fum & Equip Cons.
$5,500
$5,500
Bidding
Bid Sets
$7,000
$7,000
Bond counsel
$10,000
$10,000
Construction
Clerk (pt time, 15 mo)
$30,000
$30,000
Furniture & Equipment
(new Const only)
$53,000
$53,000
TOTAL PROJECT COSTS
Joshua Eaton School
$3,901,946
$4,226,197
TOTAL PROJECT COSTS
Birch Meadow School
$1,971,005
$2,116,766
TOTAL PROJECT COSTS
both schools
$5,872,95.
$6,342,963
9205ESTA, LS Page 3