HomeMy WebLinkAbout2000-05-23 ad Hoc School Building Committee Minutess OF Mq 5aoe 6w'a~ (SIR 310
Reading School Building Committee
Minutes of RSBC Meeting Held on May 23 2000, 7:30 p.m.
(In the Library of Coolidge Middle School)
Committee Members Attending:
Russ Graham, Chair (RG)
Alex McRae (AM)
Joe Lupi (JL)
Rich Radville (RR)
Tim Twomey (TT)
Jeff Struble (JS)
Paula Perry (PP)
Dennis LaCroix (DL)
Featured Guests:
Gene Raymond Jr., AIA (Strekalovsky & Hoit, Inc., Architects)
John Doherty, Principal (Coolidge Middle School), p/t
Dr. Harry H. Harutunian, Superintendent
The meeting started with a tour of the nearly completed Coolidge Middle School, which
began as soon as the meeting was called to order. John Doherty, Principal, conducted
the tour, during which time no group discussions took place.
At the completion of the tour, RG conveyed the Committee's thanks to Mr. Doherty for
his work on the renovation project and offered congratulations to the Coolidge Science
Olympiad team which placed ninth in the national tournament. Mr. Doherty then left,
reminding the Committee of the dedication and open house of the new facilities
scheduled for June 1.
Dr. Harutunian asked that the minutes reflect the very positive contributions
made by Mr. Doherty to the success of the Coolidge project due to the hard
work, time and effort he expended on the design and construction of the new
facilities. Like the Parker project (Dr. Jack Delaney, Principal) the
contribution of the principals helped significantly to bring the project in on or
under budget with excellent results. The Committee was happy to comply
with this request. [QED]
JL requested of Gene Raymond how the remaining unfinished items for
Coolidge were proceeding. Mr. Raymond responded that progress was slow
but steady, stating that the 5% retainage was being reduced to 21/2 % in
recognition of the contractor's progress. This remainder will be withheld until
all punchlist items are addressed. Significant sitework still needs to be done.
Dr. Harutunian added that several interior finishes must (of necessity) wait
until the students are not in residence in order to be successfully applied,
such as re-painted lockers and protective floor coatings. The soccer field
may be ready by the fall, but the surface material must dry out sufficiently
before it can be finally graded and landscaped.
Reading School Building Committee
Meeting Minutes from May 23, 2000
- Turning to the high school, RG asked Mr. Raymond for a brief overview of the
executive summary contained in the latest feasibility report prepared by his
firm for the School Committee.
- Mr. Raymond began by noting that the physical needs of RMHS are typical of
a building that has not had a major renovation in 40+ years. His team noted
the poor condition of the mechanical, electrical and plumbing systems and
the portions of the heating system that have not been recently replaced.
Their recommendation was to replace the worn-out M/E/P systems and
heating system components.
- Regarding architectural finishes, Mr. Raymond stated that ceiling, and floor
and wall surfaces as well as most teaching equipment had out-lived their
usefulness and deserved replacement. The budget they are proposing
includes this.
- Enrollment projections for the high school showed increases from the current
1100 students to between 1500-1600. Therefore, all the development
options produced in the S&H study assumed the increased student
populations.
The preferred option (as well as other options) put forward in the study
assumed the removal of non-high school uses from the building in order to
recapture space for the increased population (examples of non-high school
uses are the RISE and REAP programs and the Superintendent's offices).
Further, departmental offices that now occupy classroom-sized spaces would
be relocated to smaller areas. The options include individual teachers'
stations within the classrooms to make up for the reduced departmental
space.
An additional programmatic need identified in the study was to equalize
physical education facilities (locker rooms and access to gymnasia) for boys
and girls (Title IX issues). One idea that was later dropped was to have an
enclosed link to the field house from the girls' locker room in Building H
across the roadway between the high school and the field house (the $21/2M
cost was thought to be better used elsewhere programmatically).
Music and drama space were also major considerations in the study. The
preferred option has the present girls' gym being converted to a small
theater/drama workshop that could be used to stage productions. Also, an
addition next to the present Library would house the music department. The
current (inadequate) music space behind the stage would become drama
space.
- The preferred option also envisions remaking the current lecture hall on the
Ground floor of Building B into a multi-media/computer/instructional
technology lab.
- Cafeteria renovation in the preferred option would capture the space in the
adjacent courtyard via an addition that would allow two lunch seatings instead
of three.
Reading School Building Committee
Meeting Minutes from May 23, 2000
- Improving internal circulation within the building would be a major objective of
the preferred option. Building A (1969 addition with Math and Science
departments) would be connected to the original building through the Library
wing with a multi-story link in the vicinity now occupied by the "orange
lockers". The Library wing itself would have a multi-story link to the adjacent
(original) building (Bldg. B). The links would allow lower passing time (time
spent moving between classes), better departmental organization/flexibility
and less congestion during class changes.
The cost data contained within the S&H report was based on dollars per
square foot rather than on itemized prices for each component of each option
(which would require a level of design beyond the scope of the feasibility
study). These unit prices were current to 1999. Mr. Raymond recommended
that whatever option is pursued further, money for more accurate cost
estimating should be part of the design budget.
Dr. Harutunian then offered an update on his understanding of the pending
revisions to the State SBA program. Projects submitted to the SBAB under
the present guidelines would be processed and accepted through the 2000-
2001 school year (in effect, those projects whose designs are submitted to
the State by June 1, 2000). What may follow this is a new funding program
based on designs submitted by June 1, 2001. It is anticipated that
renovations and/or new buildings will come under closer scrutiny by the
State.
The State will give communities more latitude in scheduling partial
renovations and replacements with State participation rather than having to
wait until wholesale renovations are needed (in essence, when an entire
school building needs retrofitting or re-building). The rationale behind this (it
appears) is to allow school buildings to last longer by replacing individual
systems (roofs, M/E/P, etc.) when they need to be replaced rather than wait
for multiple systems to break down.
Having said this, Dr.Harutunian voiced his concern that RMHS still finds itself
in the latter category, namely that too many systems need replacement right
away. He feared that having a new (partial renovation/piecemeal) option
made available by the State would invite calls from within the community to
make use of it in order to reduce the large cost that would accompany a
wholesale renovation. Having had to follow the SBAB's "all-or-nothing"
guidelines of the past, this would be a new consideration for the SBC.
TT asked if Dr. Harutunian knew if any additional State funds were being
earmarked for this (new) funding program. He responded that perhaps the
State legislators were considering amounts on the order of $34M for this
purpose, but it was not clear how this money would be apportioned (just for
partial renovations or added to the overall pool of funds for school
buildings?). Of obvious concern to the State is having sufficient control over
this apportionment to ensure that partial renovations are not overwhelmed by
Reading School Building Committee
Meeting Minutes from May 23, 2000
large wholesale renovations (Waltham's recent plans to apply for $190M in
wholesale renovations was offered as an example of a cause for this
concern).
RG asked when the SBC would know when the new funding initiatives being
debated by the legislators were accepted by all affected agencies of State
government. Dr. Harutunian answered that it would become clear most likely
in July of this year when the state budget was agreed upon by both houses of
the legislature and the executive branch. He commented that both the House
and Senate proposals ignore the Executive recommendation of placing
school building funding under the direction of the Department of
Administration and Finance and keep it within the Department of Education,
which he saw as advantageous.
- RG put forward the need for the SBC to become aware of the new funding
guidelines in order to proceed with RMHS, citing past projects that were
molded by the Committee to conform to SBAB requirements as precedents.
Dr. Harutunian suggested contact with the SBAB soon after the new funding
scheme is adopted.
- RG mentioned the fact that increasing enrollments will most likely be a factor
in the RMHS project and wondered how such a criterion would be handled
under the new funding scheme. Dr. Harutunian responded that it was his
understanding that even minimal additions/renovations to accommodate
increased enrollments would be considered under the new plan, which in
itself indicated a "paradigm shift" in policy for the SBAB.
F RG contrasted this multi-option approach to identifying what a school building
project could be to the previous identification process, which was to find out
which single project would be acceptable to the SBAB and develop it for
Town Meeting's review. The ability to revamp any project and still be assured
of State funding could cause confusion and disinterest. Dr. Harutunian added
that it could split the community among rival options.
JS asked for clarification of the dates of applicability of the current guidelines,
citing concern for the Killam project and which funding scheme it would fall
under. Dr. Harutunian answered that June 1, 2000 would be the last
opportunity for projects to make use of the current funding formulae. Hence,
both Killam and RMHS will come under the new guidelines.
TT spoke about the changes in the guidelines affecting the Committee's
approach to presenting the RMHS project to Town Meeting, speculating that
a whole-building solution could be questioned in light of the possibility that
fundable partial-building solutions could exist. He advised that the
Committee must stay on top of this changing State funding system, possibly
through our legislators. Dr. Harutunian cautioned that the creation of an
administrative system to implement whatever is legislated must also occur
and will itself take some time.
Continuing on the subject of the new State funding, TT surmised that by the
time the Committee puts together a whole-building scenario and puts it before
Reading School Building Committee
Meeting Minutes from May 23, 2000
the Town, wholly new (piecemeal) options may be declared as acceptable.
To this point, Dr. Harutunian added that feasibility studies that had previously
been directed towards whole-building solutions may now have to be revised
to include menu-driven schemes, describing what various budgets will buy
(and still be reimbursable).
JS posed the suggestion of meeting with our State legislators directly in order
to get the most up-to-date information concerning revised funding. He
expressed concern over having no clearly understood financial framework
around which to build a recommendation to Town Meeting in November. Dr.
Harutunian countered that such a meeting would be premature if held before
any actual legislation was signed and reiterated his suggestion to meet with
SBAB officials after adoption of the new scheme. JS expressed frustration
nonetheless at the dependence of Committee action on the action of the
State legislature on the budget, citing last year's performance as an example
of how expected timing (like finishing in July) can go wrong. Both TT and Dr.
Harutunian pointed out that last year was an exception to normal legislative
procedures.
RG asked Dr. Harutunian if the School Administration or School Committee
was planning any further enrollment projections. He answered that the
Administration would be updating the projections internally, but not until all
relevant data was available (like 1999 birth records from the State DPH).
RG questioned how the State was going to handle enrollment problems
under the new funding scheme, particularly those that need attention quickly.
TT went further, wondering how communities would accept new additions
with up-to-date facilities placed alongside old existing buildings with
unimproved facilities. RG questioned if such a project would make economic
sense. TT posed the possibility of economic analyses of various options as
becoming standard procedure for school building committees.
PP asked Gene Raymond if the high school could be renovated in a
piecemeal fashion architecturally. Mr. Raymond responded that he would not
recommend it due to the volume of systems that would have to be addressed
and the impracticality of constructing one system at a time and trying to make
it work with outdated ones.
TT wondered if the new SBAB guidelines might force a community such as
Reading to adopt a piecemeal strategy even though the community had the
desire to adopt a wholesale one. Dr. Harutunian said that in his view, the
SBAB would not do so. The revisions to the funding plans are intended to
encourage reasonable piecemeal projects that avoid demolition of sound
buildings simply to qualify for State reimbursement. RMHS seemed to him to
qualify for wholesale renovation.
TT envisioned a political problem without State mandates for a single
solution. He could see various factions in the Town endorsing what they feel
is the proper piecemeal amount to spend on the high school (that amount
being reimbursable) and promoting it in opposition to the Committee's
recommendations.
Reading School Building Committee
Meeting Minutes from May 23, 2000
6
AM made the comment that his reading of the Executive proposals for
revised funding indicated a desire at the State level to cut costs in order to
lessen the long-term financial burden. He asked if any limit to the
(reimbursable) dollars per square foot for renovations was being put forward
as a "cap". Both Dr. Harutunian and Mr. Raymond answered that the yearly
cost figures (for both new construction and renovations) are set by analyzing
feedback from architects who submit cost data on their current projects.
They saw no indications that this procedure would change.
- RG likened the attempt to control education costs with the attempt to control
medical costs. Needs could be addressed by accountants and if one wants
quality education, one must be resigned to paying for it.
Mr. Raymond offered his opinion that the State would not deny projects with
multiple needs such as those at RMHS. He said that the main change for a
wholesale project would be justifying the needs more than had been required
heretofore. In his opinion, doing so for RMHS would not be difficult.
The political aspect of a "menu" approach was discussed further. Dr.
Harutunian said that he believed that if multiple reimbursable options had
been available for past school building projects, supporters for counter-SBC
proposals would have organized and pushed their separate agendas. TT
wondered if the SBC might go to Town Meeting in November with not only a
preferred option but also additional (less-preferred) options for Town
Meeting's consideration. PP said that the needs of RMHS should be
generally understood by the Town by then, but TT questioned that point,
stating his belief that some people will always believe that only minimal
cosmetic work needs to be done. Dr. Harutunian mentioned upcoming
accreditation reviews for the high school as possibly providing additional
needs.
RG made the point that after the S&H feasibility study sub-committee makes
its report, a tally of renovation items that absolutely must be done be made by
the Administration to help guide the SBC in its on-going work (not only for
RMHS but also for Killam). JS added that making the schools ADA-compliant
was an item that must be done (Dr. Harutunian agreed). Title IX issues were
also briefly discussed.
- With no other business appearing, AM made a motion to adjourn, which was
seconded by RR. A vote was taken and it was unanimous in the affirmative
(time not recorded).
09
Minutes prepared and submitted by: Jeffrey W. Struble, Secretary
Reading School Building Committee