HomeMy WebLinkAbout2002-08-07 ad Hoc School Building Committee Minutesv
oEcEl\
]ED
Reading School Building Committee
(}IN CLERK
ADINGA MASS.
Minutes of RSBC Meeting Held on August 7, 2002, 7:30 p.
(In the RMHS Guidance Career Center) W. 3Q
202 SEP 23 P
Committee Members Attending:
Russ Graham, Chair (RG)
Michael Scarpitto (MS)
Bill Carroll (BC)
Warren Cochrane (WC)
Tim Twomey (TT)
Jeff Struble (JS)
Alex McRae (AM)
Featured Guests:
Frank Orlando (Staff)
Sid Bowen (Flansburgh Associates, Inc.)
Robert Peirce (Flansburgh Associates, Inc.)
Jane Wolfe (TMP Consulting Engineers)
Roger Wardwell (TMP Consulting Engineers)
RG began by saying the Committee should take up the subject of the contract with
Flansburgh Associates, Inc. for producing the schematic design for RMHS.
RG said that the architect and members of the SBC had revised the original
draft of the contract in accordance with many of the comments made on that
document by Committee members and had produced a revised draft. This
draft had been sent to SBC members prior to the meeting and had been
reviewed by Town Counsel (who had no further revisions to make).
RG asked Sid Bowen to summarize the substantive revisions made to the
contract. Mr. Bowen said that the biggest change was to delete specific costs
of various consultants (a range of costs was given initially) as additional fees
above the base fee paid to the architect. The RFQ required that the architect
hire those consultants. Consequently, the consultant costs were identified
and added to the architect's base with the understanding that the consultants
were to be directed by the architect, not the SBC. Hence, only one fee
($418K) was stipulated in the revised contract. RG noted that this amount
was less than the $425K amount published in the RFQ (and less than the
$450K approved by the Town) in order to hold some monies for contingency
testing and/or research. Mr. Bowen added that a desired goal of the
schematic design process was to produce information about RMHS that
could be used for alternate schemes should the Town reject the preferred
option outright. The contingency money could be used to augment the
database produced with additional facility assessments and investigations.
- RG called for any comments on the revised draft from Committee members.
Reading, School Building- Committee
1 leeting Minutes from August 7, 2002
AM felt that the revised draft was much improved over the first one, but
wondered if the scope of work was sufficiently described to avoid large
cost items that might appear from overlooked areas. He specifically
asked if the contract offered enough protection for the Committee against
errors and omission in the areas of hazardous material review and
geotechnical engineering, two areas specifically excluded from the
architect's liability coverage. Sid Bowen answered that it was the nature
of renovations to have unforeseen costs appear as the project goes
forward, due to the fact that all necessary "fixes" to all components of the
building could not be known until all those components were uncovered.
The amounts given in the contract for work that was needed to identify
what systems should be fixed were a best estimate.
AM clarified that he wanted to know was if it was reasonable to require
the Committee to have to pursue subcontractors for unbudgeted costs
due to their errors and omissions when the contract for such work
originated with the architect. Mr. Bowen said that usually, separate
contracts are made between hazmat and geotechnical consultants and
the Owners which do not involve the architects. In the case of this
schematic design study, the Committee made it clear that they wanted all
consultants to be hired by, FAI directly. Consequently, FAI has required
those consultants to carry the same amount of liability insurance that they
do, thus ensuring adequate coverage. TT added that the contract allows
the Committee to pursue those consultants directly for errors in the
content of their work provided they have liability coverage equal to FAI's.
If they do not have that level of coverage, the contract then transfers
, liability back to the architect, who is regardless responsible for the
coordination of those (and all) consultants.
AM asked that the revisions made in the scope of work (The appended
RFQ) be briefly explained. Mr. Bowen remarked that section A-2-d was
revised to avoid broad descriptions of building components and
investigations and specify those items that would be sufficient to satisfy
the intent of assessing the condition of the existing building. Similar fine-
tuning was done in section A-2-f. Other examples were given.
- AM suggested amending section 9.5 to correct a typo and list the year for
completing the Basic Services as 2003 (not 2002) and also revising the
incorrectly labeled Section 9.3.4 to 9.2.4 (another typo). No objections
were raised.
- JS asked if the 45-day grace period for payment of the architect after
invoicing (before interest charges were levied) specified in Section 8.5
was reasonable. TT answered that that amount was recommended by
the Town Accountant as being a comfortable period for processing
payments through his office.
- With no other comments being offered concerning the contract, RG called for
a motion of acceptance. TT moved that, "The School Building -Committee - - -
authorize the Chair of the School Building Committee (on behalf of the School
Building Committee) to sign this contract with Flansburgh Associates." WC
seconded the motion.
Reading Sehool.Building Committee
i keting illinutes front ,-Jugatst 2002
RG called for further discussion.
AM asked that his amendments be made part of the motion, which was
accepted by the motioner and second.
- RG remarked that RP was not in attendance but had indicated to him
earlier that had he been present, he would not have voted to accept the
contract. His reasons concerned his previous motion during the voting for
choosing the architect that called for further reference checks of FAI.
Observer Jackie Mandell asked if the new draft of the appended RFQ
adequately required the establishment of existing floor-to-floor heights.
Mr. Bowen said it did and that the earlier draft had been changed to
eliminate redundancies. She also questioned whether having the
architect begin work on the project and then negotiate a contract was
contrary to the requirements of the RFQ. TT responded that it was typical
for architects to begin prior to signing a contract in order to meet
schedules. He reiterated FAI's earlier statement that the architect
assumes the risk in such an arrangement (should no contract be agreed
to, the Committee is not obligated to pay for the work performed during
negotiations).
With no further discussion being offered, RG called for a vote on the
amended motion. The results were seven in favor, none opposed or
abstaining (7-0-0) and the motion passed.
RG announced that the next meeting of the SBC (August 21, 2003) would begin with a
joint meeting with the Board of Selectmen to appraise them of the Committee's progress
to date. After that meeting, the SBC would continue its deliberations in a separate
working session.
Robert Peirce of FAI began the design team's assessment to date of the existing
conditions of the RMHS mechanical systems, based on the draft Preliminary
Mechanical, Electrical, and Plumbing Existing Conditions Report dated 08/02/02 which
was distributed earlier to Committee members (copy attached).
- Roger Wordwell and Jane Wolfe of TMP Consulting Engineers gave
summaries of the contents of the various sections of the draft including,
- Fire protection: there are no existing systems to assess.
Plumbing: the existing plumbing systems in the original (1952) portions of
the building are at or beyond their useful life. Any systems that are
chosen to remain will require increasing maintenance each year.
Examples: pipes are corroded, valves are unreliable or inoperable,
fixtures are antiquated, and the central hot water system is wholly
unacceptable. The 1969 portions are not as bad, but will require steady
maintenance to make them last longer.
- WC noted that a great deal of work would be required to bring the
plumbing up to present day Code standards, which would increase
the amount of fixtures "per person" and would likely trigger re-piping to
provide sufficient flow capacities for the added fixtures. Sid Bowen
Reading School Building- Committee
illeetin}; Mimes i,om August 2002
remarked that an added objective of the existing conditions
assessment is to provide a list of system deficiencies that could be
prioritized for correction should the overall project not be approved
(such as plumbing issues). AM voiced his appreciation of that
objective and asked if drawings would accompany a later version of
the report. Mr. Peirce said there would be drawings. TT
recommended that capital cost estimates associated with system
replacement choices be supplemented with estimated operating costs
in order to help the Committee better evaluate their worth.
JS asked if any of the plumbing could be salvaged, particularly the
sanitary lines in the 1969 addition. Mr. Wardwell responded that
although the piping shown on the existing drawings has the ability to
last longer in theory, reports of problems with those lines indicates the
need to replace them. Reportedly, the quality of Reading's water
supply prior to the building of the water treatment plant was very
harsh and as a result, iron waste lines were known to degrade quickly.
Similar piping was installed for the storm drain system, but no real
problems have been reported with it; hence it is assumed the storm
lines can be salvaged. Both systems use buried pipes, however, and
cannot be visually inspected.
HVAC Systems: The heating plant itself is in fairly good condition owing
to the replacement of two boilers and their ancillary equipment in 1995
and 1998. The boilers serve two different heating systems; low-pressure
steam for the 1952 buildings and forced hot water for the 1969 additions.
- Many unit ventilators (UV's) in the 1952 section were replaced when the
boiler work was done, but the 1969 UV's were not. The hot water
circulating pumps that were installed with the 1969 addition have reached
the end of their serviceable lives. The hot water distribution piping is 40
years old with much of the main feeders underground and unobservable
(presumed to be in poor condition). Ventilation equipment that was
original to the 1952 and1969 buildings (fans, UV's, H&V units, etc.)
is at the end of its serviceable life and require replacement. Some interior
spaces have no ventilation at all (such as corridors). The school has a
contract for full-time heating system maintenance with an outside vendor.
This vendor's work will be increasingly necessary as the system ages
without repair or replacement.
TT asked if TMP would be identifying the major decisions that the
Committee would have to make regarding repairs and upgrades of the
HVAC system. Ms. Wolfe responded that they would and the first
such decision was whether to add air conditioning to the building and
to what degree. This decision would then allow TMP to tailor HVAC
systems to the schematic design options.
Mr. Bowen pointed out that the decision about air conditioning must
also be made in the context of producing cost estimates that could be
-
M. - - - useful should the overall schematic design not go forward. He
illustrated this point by pointing out that supplementary heating coils in
the classrooms were 50 years old, but going to a fully air conditioned
school would make any work on them unnecessary. If, however the
full project (with air conditioning) was rejected, the cost of replacing
Reaclin .School _building Committee
A<leeting, Minutes ftom, Abig ust 2002
those coils would be unknown because no scheme was developed
that re-employed them.
MS said that he thought that the actual costs resulting from the
inefficiency of the antiquated heating system should be investigated
and presented to illustrate the need for its replacement. WC
cautioned that adding ventilation would also add heating
requirements. To this point, Mr. Bowen added that realistically, the
need to heat and then exhaust fresh ventilating air (due to required
fresh air exchanges) would match or exceed any savings realized
from improving the insulating efficiency of the building. In his
experience, operating costs generally rise after full-scale renovations.
- TT still hoped that after multiple permutations of combining various
HVAC systems with each other, two or three schemes would present
themselves that would produce the most cost-effective improvement
to the educational environment at RMHS.
- AM inquired if the design team was laying the groundwork for
assigning costs to the choices for HVAC upgrades. Robert Peirce
said they were and were moving from assembling piecemeal
requirements for individual spaces and zones to composing "system
strategies" that would put together HVAC systems that would satisfy
the piecemeal requirements and produce the best solution to the
needs and goals of the school.
- To help this strategizing, Mr. Peirce said that two immediate school-
wide questions needed to be answered; 1) is RMHS intended to serve
as an emergency shelter for the Town and, 2) what are the Committee
and School Department's desires regarding air conditioning at the
school? As to emergency shelter, Mr. Peirce contacted the Reading
Fire Department and found that the high school is indeed intended to
serve as one (although presently it can only be a Priority II shelter due
to its lack of air conditioning and handicap access). The need for a
decision on air conditioning (AC) is because the differences between
AC and non-AC HVAC systems are pronounced and produce very
different design criteria (and choices to make) when one system is
chosen.
- TT made the point that comfortable air quality and temperatures are
crucial to maintain in a sustained learning environment, to which Mr.
Peirce added that good acoustics are also important. He noted that
unit ventilators are acoustically inferior to (central) air conditioning.
RG asked Frank Orlando (Principal - RMHS) to what extent the
school was used over the summer. Mr. Orlando replied that teacher
curriculum and administrative work was on going through the summer
months and the Recreation Department conducted several town-wide
programs in certain sections of it. It is not used as heavily as it is
during regular school months, he said. Individual AC units are
presently installed in offices that are continually occupied.WC asked
Mr. Peirce if FAI could survey the school's summer usage and identify
Reading School Building Committee
Meeting Allinutes, f ,om August 2001
those areas that were used the most. Mr. Peirce replied that they
would.
Sid Bowen advised that the decision to air-condition or not should
take into consideration the fact that 50 or so new unit ventilators had
been installed 5-8 years ago and that if AC is to be used school-wide
in a the renovation, those units would have to be abandoned. TT
remarked that the School Committee acknowledged such a possibility
when it authorized the purchase of those new UV's. WC also noted
that when discussing AC for the school, possible re-installation of
heating pipes might be necessary to be able to handle both heating
and cooling water volume (cooling lines must be larger).
RG asked the design team if other school districts were adopting air
conditioning in their renovations, perhaps in recognition of eventually
going to a 12-month school year. Jane Wolfe cited two of her projects
of similar scope that were split on the decision to air-condition their
schools (one did, one didn't) and some that included it as an add-
alternate in the bid documents. Mr. Bowen recalled projects that had
air-conditioned only certain spaces (offices, auditorium, library, etc.)
while not providing it for classrooms. One had out-and-out rejected
AC on the basis of cost.
Jane Wolfe said that air-conditioned systems allowed choices from a
variety of equipment and explained some of the possibilities. RG
asked if TMP could compile costs for a range of systems that
- incorporated AC in varying amounts. Ms. Wolfe replied with her own
request that the Committee prioritize the spaces that would need AC
the most (auditorium, computer rooms, library, etc.), to which RG
relied that such priorities would be discussed.
- TT asked that the health issues associated with various systems be
presented with the system choices so that they may be taken into
account when deliberating the merits of each system. Ms. Wolfe
remarked that ventilation and the replenishing of fresh air had the
most effect on users' health.
Sid Bowen initiated a discussion about creating healthy learning
environments through control of not only fresh air and temperature,
but also sound (noise), upon which the choice of ventilation system
played a large part. TT contributed comments about the choice of
materials in classrooms affecting acoustics as well as air quality
issues, such as carpeting. Mr. Bowen pointed out that carpeting has
advantages but only if it is maintained well, which is often left undone
due to facility budget constraints.
Observer Jackie Mandell asked Mr. Bowen if AC would be
reimbursable by the SBA. He answered it would be. She also asked
- if the design team was aware of the-Peat-Marwick recommendations
for Town-wide building maintenance. TT explained the Peat Marwick
study and their recommendations that serve as a guideline for building
maintenance in Reading. This precipitated a discussion about the
relative importance of maintenance to renovated (and new) schools,
School Building Committee
Reading
Ifeeting Minutes fr,o»i.August i, 2002
with the result being an acknowledgement that committing to build a
school project carries with it a need to commit to its on-going
maintenance in order to sustain the educational benefits realized by
the project.
Observer Kendra Cooper raised a point about new building systems
requiring the hiring of skilled technicians to use and maintain them,
which would be an operating expense. Ms. Wolfe responded that
their specifications for the new systems include mandatory training of
a Town-designated individual to comprehend their workings and
requirements. She also mentioned that certain proprietary systems
could work with those systems' building management subsidiary that
could monitor the systems off-site on a contract basis and perform
corrective work as needed. Ms. Cooper suggested that increased
operating expenses be estimated as part of the design team's work
(Ms. Wolfe said such information would be provided). She also cited
examples from other school renovation projects of acoustical
problems arising with new ventilation systems in large spaces, with
the equipment operating too loudly when used for public gatherings.
Ms. Wolfe responded that TMP designs central ventilating systems to
operate at low to medium airflows to minimize the systems' ambient
noise levels.
Robert Peirce and Sid Bowen commented on the efficacy of providing
training for an on-site building manager only to lose the knowledge
gained in the training when that manager leaves. Mr. Bowen said that
outsourcing such tasks to contracted facilities management
companies could reduce the risks taken with training an individual.
AM thought it was of value to identify and declare the added operating
expenses of the replacement building systems as valid criteria for
judging the relative worth of each system. Sid Bowen agreed, citing
an example of a high school building committee that insisted on a
high-maintenance solar hot water system for its renovation and had
trouble when the individual hired to maintain it was laid off in a budget
squeeze (instead of teaching personnel). Observers Jackie Mandell
and John Russo voiced their agreement concerning the identification
of added operating expenses for the options presented.
TT asked if FAI was going to let the Committee know what decisions its needs
from them and when they need them. Robert Peirce said that they needed
decisions quickly on AC, but acknowledged that FAI had some more background
work to do with the school department first. More immediately, FAI had put
together a list of additional testing suggested by the members of the design team
that the Committee should consider, which was passed out (copy attached).
Mr. Pierce began by stating that the tests on the list were of two types: those
that should to be done to determine the scope of necessary work and those
- -
that should be done to improve the comprehensiveness of theexisting
conditions report (shown in italics on the list). He addressed each numbered
test individually.
School Building Committee
Reading
1l1eeting A4inutes from ,4 ugxtst 2002
Test 1 was to perform infrared testing of certain locations on the existing
roof, particularly on the field house. Moisture was noticed on the
undersides of the roof deck at these locations, which indicates water
penetration. The extent of this penetration cannot be known without an
infrared scan (uses infrared readings to identify boundaries of wet/cool
and dry/warm decking below the roof surface) and the extent of possible
repairs will have overall cost significance. Should the results warrant it,
selective demolition may be called for to physically observe the degree of
damage the water penetration may have caused to the roof decks.
TT informed the Committee that such a scan was used to diagnose roof
problems at the Joshua Eaton School, which led to a successful repair
project being undertaken a few months ago. RG inquired of TT if the
School Committee was moving forward with the transfer of ownership of
the field house to them from the Board of Selectmen. TT responded that
Town Counsel was investigating this subject, but it was hoped that the
transfer could move forward without obstacles.
- Test 2 was an on-site assessment of the local water supply network's
ability to support the addition of a fire suppression system to the school
(sprinklers). An independent contractor would do this, since it is outside
the scope of any Town department (water or fire).
Test 3 would seek to test the existing domestic water supply piping
thought excision of test specimens for measurement and evaluation. This
test would not be necessary if the full renovation project were to proceed,
- since such piping would be totally replaced (hence it is only needed to
better complete the existing conditions information).
Test 4 would be similar to Test 3 but applied to the storm drainage piping.
Roger Wardwell explained that the corrosion that might have resulted
from acid rain affected the vertical lines more seriously than the horizontal
ones mainly because those lines were always covered by finished wall
surfaces. Leaks in the vertical pipes were therefore more damaging (the
horizontal lines occurred in the crawlspace areas and were not so
damaging and accessible for repair). He said that TMP would
recommend replacement of the vertical lines due to their age in any
renovation scheme, so testing them would only supplement the existing
building information.
- Test 5 would be the same as Test 3 for the sanitary lines, but those lines
would be scheduled for replacement in the full project. Hence, testing
them would only be for completeness of the existing building assessment.
- Test 6 would test the condition of the water service entry pipes, meter and
valves, which would be replaced in a full renovation. Again, the impetus
for doing the test would be for completeness of the assessment.
- - Test 7 includes indoor air quality testing -which-the Committee had -
already acknowledged needing, so its inclusion on the list is a reminder.
Reading School BtfildinA Committee
Afeeting illirattter fi^om Aat~;z~st 002
Test 8 checks the condition of the hot water system valving and pumps,
which is believed to already be covered under the contract for the heating
maintenance vendor (already paid for).
- Test 9 is similar to Test 3 for the low-pressure steam lines, which would
be replaced in a full renovation. Again, the impetus for doing the test
would be for completeness of the assessment.
- Tests 10, 11 and 12 (testing the emergency generator, the normal
building electrical distribution system, and the electrical panels,
respectively) fell into the same category of Test 3. The tests would only
be of use if the full project did not go forward and could be used for
alternate project planning.
A discussion ensued among several members concerning the need to have
more complete system information right away or to wait until it was known if
the full project would not go forward. If the project failed, the contingency
money ($32K minus any spent for testing beforehand) could be used for
some of the italicized tests to improve the knowledge base of the systems'
existing conditions. Consequently, a general consensus was arrived at that
tests of systems that were scheduled to be replaced in the full renovation
need not be done right away. This left Tests 1, 2 and 7 as tests to be done to
help establish the schematic design scope of work.
Robert Peirce remarked that for the purposes of the design team's progress,
only the first part of Test 1 (est. cost $2,500 - $4,000) and Test 2 (est. cost
$1,400) would be needed to be done right away and he asked for formal
approval to authorize the tests. He said that the costs would not be more
than the range listed. The costs for Test 7 (IAQ) could be better established
for later approval.
TT then moved that the SBC approve a maximum of $4,000 to do the Infrared
Scan of the Existing Roofs (first part of Test 1) and to authorize a maximum
of $1,400 to do the Water Flow Test (Test 2) as per FAI's August 7, 2002 list
of tests. JS seconded the motion. RG called for further discussion. With
none appearing, a vote was taken and it was unanimous in the affirmative
(7-0-0) and thus, the motion passed.
RG asked TT to discuss air conditioning of RMHS with the School Committee so that the
decision could be made quickly as to its extent in the project.
RG reported that the Town Manager (TM) had asked the Committee for a projected
schedule of needed funds should the renovation project be approved (how much in
which fiscal years). He did so in order to update the 10-year Capital Plan and compile
an aggregate effect on property taxes from all contemplated capital projects that require
debt exclusions, of which the high school project would be the largest. Since the TM
required this information right away, RG asked JS to make an assumption of what
amounts would be needed and when based on the timeline he had produced for the
construction phase of the project. He asked Sid Bowen-to-review JS's results. - - -
- JS explained that his assumptions were based on the stated desire of the
School Administration for a construction period of 30 months and on the
approval of the project by the community at large in April of 2003. This would
Reading School Building C'onnnittee 10
Meeting Minutes ftom August 2002
lead to final design and bidding of the project, with construction beginning in
the spring or early summer of 2004.
With fiscal years ending on June 30t", JS fitted his estimates into four
separate fiscal years (FY04 through FY07), assigning $3M for architect's fee
and 5% of project costs in the first one, and 45%, 40% and 10% of those
costs in successive FY's, respectively. The TM used a total cost of $59M to
apportion to the fiscal years, since that is what is now being carried in the
Capital Plan. He passed out copies of his mark-up of the timeline to
Committee members (copy attached) for their review.
AM questioned Sid Bowen about SBA reimbursement rates for Reading and the status
of so-called incentive points (like maintenance) for school districts applying for
assistance. Mr. Bowen said that due to the volatility of the SBA's policies, what should
be counted on at the moment was only the base rate plus any points for renovation
(around 55%). AM asked if there was any indication of how large a project the State
would support. Mr. Bowen responded that based on current guidelines, the indications
were that the current footprint of the high school was of a size acceptable to the State for
consideration. What was not clear at the moment was the disposition of the Field House
in terms of reimbursement.
AM asked if FAI would identify the cost level above which the State would not contribute
in its preparation of options. Mr. Bowen said that each option's cost would reflect the
expected participation of the State and any overage that would have to be paid by
Reading alone.
AM wondered if the Capital Plan being developed by the TM from the assumptions given
would be accurate, given the unknowns in terms of reimbursement and total cost. RG
responded that the Capital Plan only reflects the knowledge of the projected projects at
the time it is updated, and at present, no more accurate information is available. It would
be updated again before it is to be approved by Town Meeting.
Observer Jackie Mandell asked if space previously identified in feasibility reports as
excess square footage as well as the Field House space would not be considered
reimbursable. She asked if that was the case, why would transfer of ownership of the
Field House from the BOS to the SC be necessary? Sid Bowen replied that until a
project was developed and brought before the SBA for discussion/negotiation, definitive
answers to what was and what was not reimbursable could not be made. RG noted that
the need (or lack thereof) to transfer ownership of the Field House should its renovations
not be reimbursable by the State was a question to be answered by Town Meeting.
The subject of approving or amending minutes was deferred until a later date.
With no other business appearing, RG called for a motion to adjourn. TT so moved and
was seconded by MS. A vote was taken and it was unanimous in the affirmative (time
unrecorded).
Minutes prepared and submitted by: Jeffrey W. Struble, Secretary
Reading School Building Committee
FLANSBURGH ASSOC IATVS
August 5, 2002
Reading School Building Co ittee
C/o Superintedent's Office
82 Oakland Rd.
Reading, MA 01867
RE: Agenda: Meeting of ugust 7, 2002
Reading Memorial Hi h School Study
FAI Project No. 2204100
We are in the process of finalizing the full existing conditions draft report. In
preparation for Wednesday evening's meeting, we have attached a preliminary
Mechanical, Electrical, Plu ing report. The focus of our presentation will be
the Building Systems, partic larly heating, ventilating, and air conditioning.
There are options and altern tives for these systems. Each of these alternatives has
implications for the Indoor Air Quality, Building Comfort, Renovation Cosc, and
Life Cycle Cost. Representa Ives from TMP Consulting Engineers will attend the
meeting for a preliminary di cussion of these issues.
We will also outline tests
consider in fully exploring
Agenda
Progress Report
+ Building Systems
Electrical
Plumbing
Heating Ventilating F
• Tests and Procedures
Other Items
Sincerely,
FT,ANSBURGH ASSOCIA
Robert Peirce
Associate
invasive explorations which the committee could
condition of the existing facility.
Air Conditioning
INC.
Preliminary Mechanical, Electrical, and Plumbing Existing Conditions Report
EXISTING CONDITIONS
1. INTRODUCTION
The following report c
and Fire Protection sysi
sses the existing conditions of the Mechanical, Electrical, Plumbing
within the Reading Memorial High School.
This assessment is bas d upon meetings with facility personnel, sitc visits on 06/25/02, 07/16/02,
and 07/23/02, as well s a review of the existing plans that have been made available. This in-
cludes the 1969 additio plans, and some of the 1952 plans.
The School is made u of approximately 325,000 gsf, which consists of 153,000 square feet for
the original 1952 coast ction and an additional 172,000 square feet from the 1969 Work.
II. NEATING VENTTLA ING AND AIR CONDITIONING
A. Summary:
1. The h sting system is a combination of low pressure steam and hot water (hy-
dronic . In general, the original 1952 construction is served by the steam system
and th 1969 additions are served by the hot water system. With proper steam
trap maintenance and positive results from pipe testing, this dual system can be
2. The boilers are new (1995-1998) and can last at least 20 years with proper main-
tcnan . The. fuel source is #4 oil from a 30,000 gallon underground fuel oil tank
install d in 1969. The school should convert to natural gas or install low NOX
burner . Future use of the underground storage tank is per the Reading Eire Mar-
shall' approval.
3. A pas report mentioned a possible need for another boiler. Future plans will
dete ine this need.
4. The ( 995-1998) classroom unit ventilators should function for another 15-25
years ependant upon yearly maintenance. The 1969 vintage hot water unit ven-
tilators should be replaced. All other ventilation equipment (H&V Units and
Fans) are original 1952 and 1969 and should also be replaced.
51 The ilding Automatic Temperature Control (ATC) system should be upgraded
to ne technology.
8. General:
1. This tview AC report is based on site visits made on July 16 and 25, 2002, as well
as a of the original plans H-1 through H-10 dated May 20, 1952 and the
1
1969 ddition plans, H-I through H-19, dated 9-15-69. Plans for the 1995-1998
renova ions were not available. TMP also met with Dominic Cacciapouti, the
acting Director of Facilities, and Steve Mitton from INVBNSYS.
C. Heating:
1. The R ading Memorial High School (RMHS) is heated by (2) large steel firetube
low p ssurc steam boilers located in the original (1952) Boiler Room in area
"A
s,.
•
2. Boiler
# I was installed in the summer of 1995. The boiler is a Superior boiler
model
"MS6-X-1000-S15-IOOF-A5", sold to Industrial Combustion (IC), who
packs
ed their burner with the boiler and sold it to Rcading under the "high-
lander
name. The Highlander boiler is a "Scotch Marine" wet back type rated at
200 b
iler horsepower, with (86) 2-1/2" tubes. The 1C burner is a model MM-
84P,
hick utilizes #4 oil and has full modulation control capability and natural
gas pil
t.
3. Boiler
i# 2 was installed in 1996. This boiler is a packaged steel firetube boiler
from
leaver-Brooks, model CB-200. This boiler is also rated at 200 horse-
power
The forced draft burner, configured to fire #4 oil, also has full modula-
tion c
trol and natural gas ignition.
4. These
boilers provide the equivalent of approximately 40 BTUH per S.F. of
heatin
for the facility.
5. A ne%
condensate receiver, with triplex boiler feed pumps, was installed with the
new
filers. (Pump #1 serves Boiler #1, Pump # 2 serves Boiler # 2, and Pump #
3 acts
as a standby for either P-1 or P-2.) There is also a vacuum feed pump lo-
cated
n this boiler room which might serve the domestic hot water system (see
below)
.
6. The b
etching from the boilers is new, double-walled and was installed with the
boilers
. The breeching tuns to the existing chimney (1952), located in the north-
west
orner of the Soiler Room. The condition of the chimney is unknown and
shoul
be tested prior to the final report.
7. The fuel oil is stored in an underground 30,000 gallon storage tank installed
durin the 1969 addition construction. A duplex fuel oil transfer pump system is
locate in the northwest corner of the 1969 Boiler Room building addition to area
"As"• The # 4 oil is pumped to the new boilers which have been provided with
electric heaters at the burners to maintain oil flow during the cold winter months.
The iginal 1952 fuel oil pump set is abandoned in the southwest corner of the
1952 oiler Room near the electric switchgear.
8. As m rationed above, there are two (2) Boiler Rooms in RMHS. The first was
built n 1952 during the initial construction of the school and houses the newer
steam firetube boilers described above. The second Boiler Room was built in
1969 and houses (3) abandoned (moth-balled) cast iron sectional H.B. Smith
boilers. These (3) boilers generated hot water to provide the heating for the new
addit' ns indicated on the 1969 plans. There are (5) (original 1969) circulating
2 08/02/02
located in the 1969 Boiler Room. They are still in use and serve (3)
zones.
9. Zone is the Field House and is served by P-1 and P-2. (P-2 is a stand-by for P-
1). P- supplies 225 GPM of hot water at 90' head pressure and has a 10HP, 208
volt, 3 phase motor.
10. Zone is the 1969 addition indicated as-areas "BI" and "C". Pump P-3 serves
Zone and supplies 350 GPM of hot water at 110' head pressure and has a 15
HP, 2q8 volt, 3 phase motor.
11. Zone is the addition indicated as area "A," (the Cafeteria addition and "new"
kitcht) and also the Industrial Arts addition to the original Boiler Room (area
"As"). Pump P-5 serves Zone 3 and supplies 225 GPM of hot water at 134' head
pressu a and has a 15 HP, 208 volt, 3 phase motor.
12. Pump P-4 serves as a stand-by for Pump P-3 or P-5.
13. ni-N firetube boilers supply steam to the original 1952 buildings ("A2",
"A4", nd partial "As") and to a steam-to-hot water converter installed in 1995.
This c nverter is also located in the 1952 Boiler Room section of "As". Hot wa-
ter is upplied to the original (5) pumps located in the 1969 Boiler Room section
of "AT'. Expansion tanks, air separator and all hot water specialties are original
to the 1.969 construction. The firetube boilers also supply steam to four domestic
hot w ter storage heaters. (For information on these storage tanks refer to the
Plum ' g Section of this report.)
14. The s earn and hot water is distributed throughout the buildings via a series of
crawl spaces and underground direct buried piping. Original hazardous piping
insula ion is reported to have been removed from most of the piping with the ex-
cepti of pipes located within the crawl spaces. Equipment and some piping
withi the boiler rooms have not been re-insulated after the abatement.
15.. Neati g for the classrooms, in the 1969 addition indicated as area "C" (Zone # 2)
is via hot water classroom unit ventilators and finned tube radiation. This wing
house the Math and Science classrooms and has a crawlspace under most of the
buildi g for hot water distribution to the Ground Floor equipment. Piping loops
at the ceiling of each floor serve the floor above i.e., Ground Floor piping serves
the F rst Floor, First Floor piping serves the Second Floor equipment. This
equipment is original 1969.
16. Heating for the Library and Lecture Hall wing (area "B"), also Zone # 2, is via
duct r[lounted rc-heat coils.
17. Heati g for the detached field House addition, Zone # 1, is via a direct buried
hot ter piping loop which serves finned tube radiation at exterior walls, cabinet
unit eaters in entryways and coils in the Field Nouse H&V units.
18. Heat ientilators, g for the Cafeteria addition and Kitchen (area "A,") is hot water piped to
unit finned tube radiation, cabinet unit heaters and a hot water coil in
3
the Ki
hen make up air H&V unit. This equipment is original to 1969 and is part
of the
one # 3 hot water system.
19.
Thee
isting (1952) Cafeteria is heated via steam unit ventilators. These UV's
were r
placed in 1995-1998, at the same time the firetube boilers were installed.
20.
The C
ssroom wing, between "A," and "A3" overlooking the Courtyard and ad-
jacent
to the Cafeteria, is original.1952 construction and is heated by low pres-
sure st
eam piped to classroom unit ventilators. These UV's have also been re-
placed
during the 1995-1998 renovations. The existing 1952 supplemental heat,
steam
onvcctors, was left in place in the classrooms. Existing (1952) stairwell
steam
finned tube radiation and convectors remain.
21.
The w
ng indicated as "AZ" is the original 1952 Auditorium and is still utilized as
such.
The heat for this section is steam. The Auditorium, Dressing Rooms, and
Music
Practice Rooms have original convectors and a 1995-1998 classroom unit
ventila
tor.
22.
Area '
A3" is original 1952 and houses the Main Entry (Lobby), Administration
Offic
, Health Suite and miscellaneous classrooms. This area is heated via low
press
a steam finned tube radiation, convectors and classroom unit ventilators.
The
's were replaced during 1995-1998, as well as some of the finned tube
radiat'
on on the first Floor. Existing (1952) convectors, and cabinet unit heaters
in the
Wrwell and entries, remain.
23.
Area
A4" is original 1952 construction. This area houses the Girl's Locker
Roo
and a Gymnasium. The heating medium is steam, piped to unit ventila-
tors,w
hich were replaced in 1995-1998. Supplemental convectors for heat and
finne
tube radiation are original to 1952.
24.
Area
AS" as discussed earlier, houses the (2) Boiler Rooms and the Industrial
Arts a
ddition constructed in 1969. The addition is part of Zone # 3 and is served
by th
hot water system. The finned tube radiation, unit heaters, H&V units and
classr
oom unit ventilators are original 1969.
25.
The b
eating equipment indicated on the plans for the toilets has been removed
duet
vandalism.
D. Ventilation:
1. Venti ation air for all classrooms is via the floor mounted unit ventilators. The
unit ventilators are connected to exterior wall louvers through a series of various
detail based on the architectural configuration of the area. Exhaust air is via
shaft to roof mounted exhaust fans, which are original to 1952 and 1969.
2. The afeteria ventilation is similar to that of the classrooms - floor mounted unit
venti tors connected to exterior wall louvers, with roof mounted exhaust fans.
The Kitchen cooking hood and associated exhaust fan is original 1969. This
hood exhaust fan is located in a fan room over the corridor adjacent to the Audi-
torium on the Second Floor. The exhaust is ducted to an exterior wall mounted
4 08/02/02
3. Large yeas, such as the Auditorium, Gymnasium, Field House, Library, and
Lcctur Hall, have been provided with H&V (heating and ventilating) unite for
ventil ion requirements. Exhaust fans relieve the pressure and exhaust areas
such the Locker Rooms, Weight Room, Toilets and Janitor Closets. TIv>P will
investi ate the age and capacities of these units to determine actual physical con-
dition d fresh au quantities at a later date.
4. There is no mechanical ventilation provided for the Administrative Offices,
Heal Suite, and Guidance areas. These areas must rely on operable windows
for fre h air. This tends to be problematic in winter.
5. The ccHdors also have no ventilation.
E. Air
1. There is no central air conditioning at the RMHS. Miscellaneous window units
provi cooling for Offices. There is a condensing unit suspended from the out-
side will of the Library. The Library Offices and TV Studio were not accessible
at the ime of the site visits. TM? will investigate this unit for capacity and func-
tion, a a later date.
F. Temperature Clontroi:
1. The a tomatic temperature control system is pneumatic. An existing (1969) air
comp ssor is located in the 1952 Boiler Room and was probably replaced during
the 19 9 renovations. A second compressor has recently been added in the area
below the Auditorium (referred to as the Civil Defense Area by school person-
nel). is compressor was added to supplement the control system at the furthest
end o the high school.
2. The b ilers have their own packaged controls and operate as lead/ lag unless it is
very Id, at which time both boilers are required. A three way valve in the hot
water ystem provides hot water temperature reset control based on outdoor tem-
3. Pricus atic thermostats in each classroom control the unit ventilators and inter-
loeke fresh air dampers. A time clock provides for night temperature set back -
occup ed / unoccupied control.
4. Space thermostats control the re-heat coils in the ductwork in the Library and
Lectu Hall.
5. At the present time, RMHS has signed a contract with INVENSYS Controls
(form fly SEIBF. Controls) to maintain and operate the school. Steve Mitton is
assi ed to the school full time and is on site every day to check on equipment,
and p ovide maintenance as needed, rNVENSYS has replaced some malfunc-
tions control valves, performed some steam trap maintenance, replaced motors
in no -functioning equipment and acted as a building operator.
5 06/02/02
G. Miscellaneous:
1. A sep ate 500 gallon diesel fuel oil tank is located in the area between the two
boiler ooms. This tank serves the existing emergency generator and appears to
be abo t 5 --10 years old.
2. The ustrial Arts program, as originally configured, has a dust collection sys-
tem, ieh appears to be abandoned in place.
3. Air q lity testing has been performed in the past, when complaints have been
received.. No specific problems were detected, but a full testing of the school
shout be performed in the Fall as described in Part N.
4. Boiler Room ventilation and water treatment need to be provided for the steam
and h water systems.
H. Conclusions add Recommendations:
1. The h ating system is in fairly good shape. Much of the central plant steam
equipment and some of the terminal units have been recently replaced. The re-
main it 1969 and older equipment, such as the hot water pumps and specialties,
shout be replaced. This equipment is 30 years old and nearing the end of useful
life a ctancy (based on ASHRAE published information). The new hot water
equipment should be moved into the existing 1952 Boiler Room. The Boiler
Room can then be consolidated into the 1952 space. The 1969 addition space
can b freed up for other uses. The boilers should be converted to natural gas, or
provi d with new low NOX (pollution control) burners. The existing chimney
shout be inspected and approved for use by the Relating Fire Marshal.
2. The v ntilation system, all original 1952 and 1969 fans and H&V units, have
reach the end of their useful life and should he replaced with more efficient
equip ent. Cooling (air conditioning) should be provided for the Library / Lec-
ture 11 units. Cooling for the auditorium and Cafeteria should be considered.
All i erior spaces should be provided with Massachusetts Building Code re-
quire ventilation. TMP recommends cooling be provided as well. Toilet ven-
titatio and Corridor ventilation must be upgraded to meet new code require-
ments Indoor air quality testing; should be performed in the Fall when students
and f ulty return to determine any additional ventilation requirements.
3. The o iginal steam piping is 50 years old and should be performance tested to
dete ine a reasonable remaining "life expectancy". If corrosion inside the pipe
is shown to be extensive, this pipe loop should be replaced. Damage to the
buildi g structure and the cost of continued maintenance on a leaking pipe sys-
tem s ould be considered.
4. The Wilding automatic temperature control system should be updated to the
ncwe technology the Town of Reading can afford. An Energy Management /
Building Management system should be installed. The cost of energy will only
get hi her. The RMHS building efficiency should be improved to save future op-
eratio costs. There are rebate programs offered by utility companies, which
6 08/02/02
might
provide monies for some of the recommended improvements. This should
be inv
tigatcd during the design phase.
III. FIRE PROTECTION
A. Summary:
1. There
are no "sprinkler" or standpipe systems evident in the building, and the
existin
water service into the building would not support such systems.
2. The 1
69 drawings indicate a CO2 system serving the kitchen exhaust hood and
assoei
ted ductwork. This system is active and is tested once a year.
B. Conclusions
Recommendations:
1. If the
cnovation scheme turns out to be "substantial", according to Article 34 of
the M
ssachusetts Building Code, those substantially renovated areas would
probab
ly be required to be sprinkled.
2. A spri
er system could also be triggered by any of the following issues:
a.
Owner's desire.
b.
Fire nepartment requirement.
C,
Relative level of cost.
(In other words, if the cost of the sprinkler system was "low", relative to
the total cost of the renovation work. There is no "defined" percentage
trigger however, costs less than 10%, or so, are usually considered low.)
d.
Opportunity.
(In other words, if it would be "relatively easy" to install the sprinkler
system, without a lot of associated disruptive building costs, a system
could be warranted. The biggest trigger here is "ceilings". if the ceilings
are being removed for other work, an opportunity is usually perceived
and presented for the installation of a sprinkler system.)
N. PLUT MING
A. Summary:
1. The pl
umbing systems are 50 years old in the original portions of the facility, and
are "
or beyond" their useful life. Items that are retained in any renovation
schem
e, will require a dedicated maintenance budget that will increase each year.
2. Pipin
is corroding and exhibiting leaks; valves are not very accessible, and are
not r
iable for positive shutoff; and fixtures are antiquated, general y not acces-
siblc
o the disabled and do not meet any of the water conservation goals of the
curve.
It codes.
7 08/02/02
3. In add tion, the condition of the central domestic water heating plant is deplor-
able, r.-suiting in elevated and dangerous temperature conditions in an effort to
provid for sanitary (hot water) conditions at the (remote) Food Handling area.
H. General:
1. This rite-up is based on site visits and a review of existing addition Design
Drawl gs P-1 through P-16, dated 9/15/69, and original drawings P-1 through P-
10 dat d 5/20/58. In addition, there is information herein from Watson Plumbing
& He 'ng, a local Contractor who has done work over the years on the plumbing
syste s. Awall plaque in the corridor lists building areas as 153,000 SF for the
1952 ilding and 172,000 SF for the 1969 additions. The crawl spaces were not
survey d due to the reported presence of hazardous insulation.
C. Roof Storm
1. The r (of storm watcr systems arc piped from roof drain inlets and appear to be
separ a from the building sanitary systems. The Site Utilities Plan (U-1) indi-
cates ost drains leaving to the west (rear) of the main building.
2. All stem appears to leave the facility by gravity.
3.
The (
)69) Plumbing Specification indicates the use of extra heavy cast iron pipe
and fit
ings, bell and spigot, with neoprene gaskets.
4.
Input
rom Watson Plumbing & Heating indicates that any problems with the
storm
ystem are sporadic, and not perceived to be excessive.
D. Sanit
ary,
1.
Build'
g sanitary systems appear to be piped separately from the storm systems.
2.
The
awings and specifications indicate a separate (glass/durion) "acid waste
pipin
system" from the Science areas in Unit "C". This is piped through an out-
side "
ilution chamber" and then into the sanitary sewer system.
3.
There
is an outside "Gasoline Trap" (outside Unit "A5"), which was added with
the 15
,69 Work. This appears to take the drainage from the two "garage areas",
with
a discharge connecting to the existing sanitary system. The 1952 draw-
ings a
lso indicate an "inside" gasoline trap, also in Unit "AS". This appears to
have
con maintained with the 1969 work, but with service only from one floor
drain
tom one original garage area on the first floor.
4.
The
1969) drawings indicate that the Kitchen is not piped with a dedicated
grease
waste piping system. Kitchen drains and waste inlets, therefore, tie into
the bu
ilding's "general sanitary system" in that portion of the building. There arc
two "
int-of-use" grease traps denoted on the 1969 plans; one for the pot sinks
and o
e for drainage from the dishwasher conveyer tray.
8 08/02/02
5. There re two "drip sinks" indicated on the 1969 plans in the crawl space. One
takes the indirect wastes from various Kitchen equipment and the other is located
in "A0, and appears to serve the drainage from Biology Room aquariums.
6. The (1969) drawings indicate all sanitary lines leaving the building by gravity,
witho t pumping.
7. It is reported that there have been some problems with sanitary lines in the crawl
spaces It is difficult to connect to the lines due to deterioration and some piping
(5' an 10' here and there) has been replaced. It is possible that this could have
been ontributed to by the town water system; well water, which was "aggres-
sive" r so many years prior to the upgrades to the water treatment plant in the
early 's.
8. Pipin is indicated in the (1969) specifications to be extra heavy cast iron pipe
and ft ings for all buried lines and all lines above grade 3" and larger in size.
Watson Brothers Plumbing Contractors have indicated that there are a lot of
block ge, corrosion, and leak problems with drainage piping from the urinals,
and th it associated "stacks", especially in the 1952 building. Drains and stacks
serving the drinking fountains are also reported to be in poor condition.
9. Floor rains do not have any automatic trap primers and need to be "manually"
prim to maintain sanitary water seals.
E. Natural Gas:
1. The s hool has a small gas service (3" i) with three inside meters, located in the
origin 1 Boiler Room. There is a regulator that is vented to the outside.
2. Gas currently serves: Cooking, the Science Room gas cock outlets, pilots on the
heating boilers and the "summer" domestic water boiler. Gas is also piped to
some angcs in the old Home Economics areas in Units "Al" and "AS", but these
are n longer used. There are also two (2) old gas incinerators that are no longer
used, ne on the lower level of Unit "A4" and one on the first floor of Unit "A 1
These unused devices result in abandoned gas pipe runouts, which are actually
'live'r
3. The isting gas service would not support a conversion to gas for building
heati . It is reported that a new line was put in Birch Meadow Drive, when gas
was u graded for the YMCA, Coolidge Middle and the Elementary School. This
line as reportedly sized to also handle the gas conversion expectations for the
High chool.
4. Gas r the 1969 Science areas is indicated on the drawings as being piped
throu "Master Gas Shut-Off Valves" (MGV's). However, it appears that the
origi 1 "open" room configuration was changed, at some point, by adding corri-
dors/ ails. This puts some of the MGV's "outside" of the actual classroom
space that are being served. In addition, some spaces arc indicated as not having
9
08/02/02
5. Pi
F. Domestic W
is indicated in the (1969) specifications as being "black steel", threaded
ale iron with screwed joints.
1. The 1452 drawings indicate a 6" water service from (an 8" line in) Oakland
Drive. There was no access to the domestic water service entry - locked access
panel o the crawl space. This is reported to be metered, with the meter located
in the crawl space of Unit "A3", toward the front of the building (Oakland
Drive). It is assumed to be the original meter and valving (1952).
2. The ain water distribution, and original valving, is located in the pipe space
below Unit "A3". The main (5" and 6") domestic cold water lines are indicated
as bei R "cement lined" cast iron".
3. The size of the water mains in the surrounding streets, looping and pressure char-
acteri tics are not known. Approval for water flow tests is being pursued and
shout be scheduled in the near future.
4. The S cifications indicate gate type valves were to be installed. These are, for
the st part, original. When replacements have been done over time, hall
valve have been utilized.
5. The 1 69 specifications call for air chambers and shock absorbers on the domes-
tic w er systems, to handle shock from water hammer. Access to shock absorb-
ers w s not found. The 1952 piping systems are assumed to contain only (inop-
erativ) air columns/chambers, at the top of the risers. The only reported prob-
lems of this nature were noted in the Kitchen area; piping shalring/rattling due to
quick losing valves.
6. Most threaded outlets (hose bibbs, sill cocks, service sinks, etc.) do not contain
vacuurn breakers. The dishwasher does not have backflow protection.
7. Science areas are fed from the "potable" water systems.
81 The mcstic water piping is indicated in the (1969) Specifications to be copper,
with 5/5 soldered joints. The original (1952) domestic water piping is stated by
Watson Brothers to also be copper, but would be assumed to be made up with
5015 lead solder joints. Pipe joints are occasionally beginning to exhibit leak
9. The 4:C 69) drawings indicate that the Field House is fcd from buried CW, HW
and piping from Unit "A5".
G. Domestic
1. Dom tic hot water is produced in two, 1969 vintage heaters, for the Field House
and a Girls Locker/Showers and, in two original 1952 vintage heaters, for the
rema der of the facility. Both systems are horizontal, steam-to-water storage
type caters. The only reported problems are with some corrosion/weeping at the
stean bundles.
10 08/02/02
2.
two
seas(
lems
that t
3. For
used.
One c
that d
to cor
water
"cross
This v
the summer months, there is a gas-fired domestic water boiler, which
tes domestic hot water, Typically, one horizontal heater (in each of the
stems) is valved off, utilizing just one tank (per system) during this off-
period. It is reported that there are fewer "cross-flow temperature" prob
;hen the summer boiler is used, as versus the steam heating boilers; and
summer boiler is run "most of the time" now.
original 1952 areas, there arc two old (non-working) base-mounted, do-
water circulators, and a mixing valve, which existed in 1969 and was re-
It was reported that there are problems with hot water at the (remote)
t, and that the circulators have not been operable for quite some time.
culator has been removed and is being re-built. Due to this, it is reported
mestic hot water is generated at high temperatures, up to 180°F, to attempt
pensate for the circulation problems and shortages, yet still provide proper
emperatures at the Kitchen. This is reported to be causing temperature
flow" problems at sinks, etc., with hot water coming from cold water taps.
)uld be an expected problem for this type of high temperature condition.
4. There~is an electric, 54kW (Hubbel) booster heater in the Kitchen at the dish-
washe .
5. Dome tic hot water and recirculation lines feed the showers in the Field House
throw buried piping. There is a reported shortage of HW in the Field Housc. It
has en reported that there have been problems with the circulation pump on
this s stem that could be the reason for the hot water issues.
6. In the Field House, (Boys) column showers are fed with tempered water from
master mixing valves. One column in each shower area is fed with hot and cold
water, for manual mixing at the shower valves.
7. The domestic hot water systems do not contain expansion tanks.
8. Emer ency showers and eyewash units are not piped with tempered water, as
woul be required now.
9. In th Unit "M" (Girls) locker/shower area, showers are shown to be fed with
hot cold water, for manual mixing at the shower valves.
H. Fixtures:
1. The xtures that were installed in 1969 will be almost 40 years old when any
repo tions are complete, offer minimal accessibility, do not meet ADA and
would not meet the water conservation requirements of the present Plumbing
Code. Water closets are estimated to use 3.5 gpf.
2. The 1969 Work "reused" most of the toilet fixtures that existing in the 1952 por-
tions f the building; removing some water closets, and resetting a couple of uri-
nals offer (minimal) accessibility. These fixtures are antiquated and have an
even igher water usage (possibly up to 5.6 gpf for water closets) than the 1969
1-1 _ 08/02/02
3. Exi
a.
b.
1.
g fixtures are as follows:
1952 areas
1) Water Closets - Floor-mounted, floor-outlet, elongated, flush
valve, white, open-front seat w/o cover.
2) Urinals - Wall-hung, extended side shields (w/o vanity shields),
top spud, flush valve,
3) Lavatories - Wall-hung (on wall hanger?), 20 X 18 with high
back, vitreous china, faucet on 4" centers (not metering or tem-
perature limiting).
4) Drinking Fountains - China, recessed.
1969 areas
1) Water Closets - Wall hung, elongated, flush valve, white, open-
front seat w/o cover.
2) Urinals - wall-hung, top spud, flush valve.
3) Lavatories - Wall-hung (on wall hanger?), 20 X 18, vitreous
china, (not metering or temperature limiting).
4) Showers
Boys - Column style, tempered water and mixing types.
Girls - Cubicle style, mixing style.
5) There are no accessible sinks in the Science areas.
1. In the crawl space of Unit "A2" (Auditorium), near Stair #2, there is a concrete
(steel ined?) structure that used to have a sump pump. The 1952 drawings indi-
cate t at this received the drainage from the, 1952 Elevator Pit as well as a floor
drain low Stair tit, with discharge to the sanitary system. The discharge piping
was n it evident and appears that there is no longer an operable pump.
2. The rater Department does water lead level testing, once or twice a year. There
was time, 7-8 years ago, when the school was told to open a faucet every
momi g and let it run for a while. This issue seems to have been resolved, as
they are not asked to do this any longer.
3. The wn has a "once-a-year" backflow preventer testing program.
4. There are two toilets on the lowest level of Unit "A3" that have been closed off
forabout 10 years. There are reported to be cracked fixtures, sinks not working,
12 08/02/02
etc. fixtures remain and traps are (manually) primed with a non-evaporating
solution.
51 There a problems in the Boiler Room with old valves that do not operate prop-
erly or provide for positive shut-off.
6. There 's a sump receiver in the original Boiler Room, which is indicated on the
1952 plans to take the drainage from the floor drains in the room, and discharge
to the buried sanitary system.
7. The 1952 drawings indicate a boiler "blow-off" tank in the Boiler Room, with a
cold Ater connection for cooling the boiler blow-down condensate prior to dis-
chargi g to the sanitary system. It is not known if this is still utilized.
8. Domestic water piping for the 1969 additions was run through the crawl spaces
for Units "B I"& "C" and underground to the Field House.
1. Conclusions d Recommendations:
1, The roof drains and storm water piping from the 1952 portions of the facility are
50 yc rs old, and will be nearing the end of their useful life. In a renovation
mode, we would recommend replacing all piping and accessories above grade.
Belo% grade/horizontal crawl space piping may be able to be reused, pending
size, l ation, conditions and invert. Test samples may help with a decision.
2. The b ilding sanitary/waste systems are reported to be in a deteriorated condi-
tion, ch that making new connections to the existing piping is difficult. Some
sectio is have been replaced. We understand that this is mainly horizontal, extra-
heavy cast iron piping in crawl-space type areas. Since this piping has been here
for 5 years, it is possible that the deterioration was mainly due to the "hard-
ncss/ gressive" nature of the Town's well water over the years. This is believed
not to be the case now, with the improvements to the water treatment plant over
the 1 t 15 years or so. A complete replacement should be anticipated for any
major renovation scheme.
3. The Kitchen does not have a dedicated "Grease Waste" piping system. If up-
grad to the Food Handling areas were more than modest, we would recommend
a dedicated piping system.
4. The 1 ations and number, of "Master Gas Valves" (for shut-off in the Science
Roo s) arc not adequate and do not meet code. Revisions to these devices
would be required, even in a minor renovation scheme.
5. Sine there are some old gas-fired devices, which remain in place but are no
long used (stoves, incinerators, etc.), there may be abandoned gas lines which
are " ~vc"! All abandoned/live gas lines would be removed and capped back at
"acti e" mains.
6. The xisting domestic water service entry, meter and valving, is old original
equi ent with minimal accessibility. This should be replaced, along with the
servi a entry piping.
13 08/02/02
7. Valve from the 1952 systems are near the end of their useful life. In addition,
many re located in crawl spaces that offer difficult access for usage. As a
minim m, all valves should be replaced. IIowevcr, complete new distribution
L.. f water iptng should be provided for all 1952 areas of the facility,
8. Piping to the 1952 toilet areas contains only "air chambers" as a means of con-
trollin water hammer. Access to shock absorbers for the 1969 toilet areas was
not ev dent. Shock absorbers would need to be incorporated in any toilet reno-
vation work.
9. There are many threaded type outlets in the domestic water systems that are not
protected with vacuum brcakcrs, as well as the dishwasher, which also does not
have ackflow protection. These devices are required for safety and public
health reasons, and should be done regardless of any particular renovation
10. The domestic hot water heaters, pumps, and mixing valves are near the end of
their u ful life, and are recommended for replacement.
11. The domestic hot water recirculation system is basically inoperable (for the Main
Buildi g). This results in inadequate hot water, elevating domestic water tem-
pcrat es, dangerous high temperature "cross-flow" conditions at sinks, etc. As a
temp rarysolution, until the renovations are incorporated, the Owner may
want consider installing a dedicated water heater at the Kitchen, exclusively
for the Kitchen.
12. Them: is a reported shortage of domestic hot water in the Field House also. This
is believed to have been caused by (electrical) problems in the circulator, as op-
posed to system under sizing.
13. Emer ency showers and eyewash units are not provided with tempered water.
Mix- valves would be required under any renovation scheme involving the
Scien a areas,
14. Plumbing fixtures are 33 and 50 years old, offer minimal accessibility, and do not
meet he water conservation requirements of the current plumbing code. All toi-
lets d fixtures in the 1952 areas are recommended for a complete upgrade and
repla meat. Toilets in the 1969 portions could probably be renovated, if sup-
plem ted with proper ADA accessible fixtures.
V. ELECTRICAL
A. Summary:
The existing electrical systems in the 1952 original building and the 1969 additions are
generally on final building materials, which visually appeared to be installed in confor-
mance with a applicable code requirements and electrical practices at the time of in-
stallation.
Massachusetts Electric Code, NFPA Standards, Massachusetts State Building Code, and
Life Safety r quiremcnts relating to educational facilities, including ADA regulations,
14 08/02/02
necessitate replacement or upgrading of affected normal. and emergency power distribu-
tion systems, re alarm and emergency lighting, and exit sign systems. Lighting energy
savings, comrr unication systems, and building security system demands of today's edu-
cational facilit es warrant the rep lacement/renovation or installation of these systems as
well.
Therefore, it i TMP's recommendation that, in order for this School to provide enhanced
educational 0 ortunities in a safe, well lighted, and pleasant environment, replacement
or upgrading ost of the existing electrical systems will be a fundamental requirement.
B. General:
1. This e isting Electrical Conditions Report is based on an examination of the ex-
isting wilding electrical contract drawings, dated May 20, 1952 and dated Sep-
tembe 9, 1969, and several site visits to visually observe existing conditions.
Existing Electrical Specifications and Shop Drawings were not available. The
exist' g main building was constructed in 1952 and additions/renovations were
added 'n 1969.
2. Site i speetion efforts included visual observations of all existing electrical sys-
tems erein noted and follow-up meetings with the Director of Facilities and
maint Hance staff. Conclusions drawn arc based on opinion, the experience of
personnel consulted and good engineering practice.
3. In adillition, TMP met with the Director of Facilities on 07/18/02 regarding
buildi g issues.
C. Exterior Building Power Distribution:
I. The igh School is presently served by 4 #2/0, SkV primary electric service ca-
bles ii k an underground ductbank from Oakland Road to existing Unit Substation
No. 1 in Building 'AY Basement Level (1952 Building), and then distributed out
to Unit Substations No. 2 (Existing Boiler Room 1952 Building 'A5'), No. 3
(Buil ing 511969 Addition), No. 4 (Building 'A1' Basement), and No. 5 (Ncw
Boil Room Addition 1969) Building'A5%
2. Seco ary service electrical characteristics are 120/208 volts, 3 phase, 4 wire, 60
hertz.
3. It w visually noted that two additional overhead electrical services from Oak-
land Road appear to serve the existing Snack Shack and Grandstand Press Box.
The Bond ovenccad service appears to serve pole mounted floodlights, which
may tave been installed by Reading Municipal Light Department.
4. The site appears to be primary metered.
D, Electric Servi a Equipment:
I. Exist ng main electrical service distribution equipment consists of five (5) unit
subst tions located in various buildings. Existing unit substations are as follows:
15 08/02/02
a.
b.
C.
2.
- d.
No. 1; 1000 amp, 120/208 volts, 3 phase (1952)
No. 2: 2500 amp, 120/208 volts, 3 phase (1952)
No. 3: 800 amp, 120/208 volts, 3 phase (1969)
No. 4; 1600 amp, 120/208 volts, 3 phase (1969)
e. I No. 5: 1600 amp, 120/208 volts, 3 phase (1969)
Condi ion and capacity of the 1952 unit substations is highly questionable and
probably not reusable in a major renovation project. The condition and capacity
of the 1969 unit substations is also questionable and will need to be tested by an
inde ndent and certified electrical testing company to establish condition and
reuse a major renovation.
3. Replacement parts for the 1952 unit substations arc difficult or near impossible to
fund, In addition, replacement parts for the 1969 unit substations are also diffi-
cult t find.
4. Int pting ratings for the unit substations may not meet present Reading Mu-
nicip Light DNparunent Standards for Network Distribution.
E. Building No al Power Distribution Equipment:
1. Existi g building distribution systems consist of distribution panelboards, light-
ing p nelboards, power panelboards, and motor control centers. This equipment
vane in age from original 1952 and 1969 installed equipment to present day
added patteiboards to feed specific areas or functions.
2. Cond ion and capacity of the 1952 and 1969 Power Distribution Equipment is
very uestionable. Original equipment replacement parts are difficult or near
imoo sible to find.
3. It wa indicated that many of the existing panelboards have no remaining capac-
ity an that some individual branch circuits are overloaded.
F. Building Erne gency Power Distribution Equipment:
1. The ampus is presently served emergency power from a 200kW/25OkVA,
120/ 8 volt, 3 phase, 4 wire Kohler diesel fueled interior generator located in
the n w 1969 Boiler Room Addition Building 'A5'. The generator has 664 run-
ning ours indicated on its instrumentation and visually appears operational at
hest.
2. The condition and capacity of the 1969 installed Kohler 200kW emergency gen-
erato is questionable and will be needed to be tested by an independent and cer-
tified electrical testing company to establish condition, capacity, repair requirc-
ment and estimated remaining life expectancy.
16 08/02/02
3. The a fisting 1952 installed emergency generator is abandoned in place and of no
practi l use.
4. It was noted that the 1969 emergency generator is installed in a separate room as
required by present day electrical code. However, a review may be required to
addres whether the emergency generator room is two-hour rated, as required by
State Building Code.
5. The 1069 emergency generator is fueled by an interior (500 gallon estimated)
diesel fuel storage tank located within the 1969 boiler room. It is the opinion of
TMP at this tank will need to he relocated or enclosed by at least a two-hour
rated nclosure. This item will need to be reviewed with the Authorities in Juris-
6. Theemergency power distribution system consists of one central automatic trans-
far switch wired from the 1969 emergency generator, which in turn feeds emer-
gcney power distribution panel MOP-E (300 amps, 120/208 volts, 3 phase),
which sub-feeds emergency loads throughout the complex.
7. The sub-emerge ncy distribution system consists of local emergency panelboards
locate within the campus buildings to serve emergency lighting loads as well as
select d heating, refrigeration and building elevators.
G. Present Day Code Deficiencies:
1. Life s ety pane Iboard feeders are not presently 2-hour rated.
2. Sub-d suibution life safety panelboards are not located in 2-hour rated enclosures
or roo s.
3. Life safety and non-life safety emergency loads are not properly separated per
Code. This requirement necessitates separate equipment rooms for Life Safety
system automatic transfer switch, distribution panclboard, and local building
bran circuit emergency lighting panelboards.
H. Branch Circui and Feeder Wiring:
I. Existi g branch circuit and feeder wiring is copper, generally concealed in race-
ways in walls and above ceilings. Wiremold (surface metal raceway) was noted
in may classrooms for receptacle, sound, tel/data system expansions, and corri-
dors f r building fire alarm system.
2. Materials are generally 33 and 50 years old, except for new device wiring and
emer nay lighting battery unit wiring. Some branch circuit wiring and possibly
feed wiring is original building material (1952).
3. All 1952 branch circuit wiring and feeder wiring is well beyond its normal life
expec aney.
4. All 169 branch circuit wiring and feeder wiring has reached its normal life ex-
17 08/02/02
I. Lighting Sys
1. Intel
a.
b.
C.
d.
e.
9.
h.
i.
2. E:
a.
Generally, existing lighting consists of ceiling surface black sided metal
box or wrap-around, or suspended fluorescent type 8" x 4', 1' x 41, 1' x
8', 2' x 4' and 2' x 2' recessed prismatic lensed fixtures and 4 x 4 fluores-
cent light fixtures in Library,
Gymnasium and Field House lighting is suspended H.I.D. high-bay type
fixtures with wire guards-
Auditorium lighting consists of ceiling recessed 300 and 500 watt incan-
descent down light fixtures and performance stage lighting including
stage front and side floodlighting, and ceiling suspended connector
strip/border lights on stage. Performance lighting is controlled from
stage dimmer cabinet and console. It was reported that performance
lighting and equipment are functional, but aged and in need of upgrad-
ing.
Cafeteria lighting consists of ceiling surface mounted linear fluorescent
fixtures mounted in a sort of recessed soffit.
The Library was originally equipped with 4 x 4 fluorescent light fixtures
but these where abandoned and Gymnasium type H.I.D. light fixtures
were added to improve the deficient light level.
Majority of lighting fixtures appear to be in marginal to poor condition.
Broken and missing lenses, and lens color deterioration is apparent on
many fixtures. It was reported and noticed that some classrooms, corri-
dors, and staWWls are insufficiently lighted.
All existing classrooms have multiple switches at entrance doors, pro-
viding two or three levels of illumination.
The Superintendent's Office suite has undergone major renovation and
new 2 x 4 parabolic style fluorescent light fixtures have been installed.
Exit signs "illuminated type" are generally located at all points of egress
from the building.
Existing exterior lighting consists of the following types:
1) Utility pole mounted H.I.D. type floodlighting in parking area,
which appears to be leased from the Town of Reading Municipal
Light Department.
2) Wall mounted lensed H.I.D. type light fixtures at various loca-
tions around building.
18 08/02/02
b,
c
J. Fire Alarm Sys
3) Pole mounted 100 and 400 watt H.I.D. light fixtures mounted on
painted poles. The paint finish has long since flaked off leaving
discolored base metal. The 100 watt pole mounted light fixtures
are mounted to close to finished grade to provide overall illumi-
nation of walking paths.
Exterior lighting is automatically controlled by photoelectric sensors
and/or time clocks.
It was noted that quantity and multiple different types of exterior lighting
fixtures appear to adequately illuminate most exterior areas. However,
maintaining supply of various lamp and ballast types has been an ongo-
ing maintenance problem.
1. Existi g multi-plex, zoned fire alarm system is 23 years old. Control panel and
stand batteries are located in ground floor main electric room of 1952 Building
'A3'. System is connected to Reading Fire Department via a pedestal mounted
street a master box located on Oakland Street. System consists of heat detec-
tors i all classrooms; smoke detectors in all corridors at smoke doors, stairhalls;
and large group areas; hom/light (AN) signals in corridors and large group areas;
pull s ations in corridors and near most egress doors, and magnetic holders on
some moke doors.
2. It wasireported that the system is functional.
3. It wai noted that AN signals are non-ADA generation type and that classrooms,
and toilets, are not provided with AN signals.
4. Majoity of system wiring to devices is installed in the 1952 Building in surface
wall d ceiling mounted wiremold. Wiring in the 1969 building addition is con-
K Receptacles a4d Switches:
1. Existing receptacles and switches visually appear in serviceable condition. Re-
ceptacles arc grounded type and switches are toggle type throughout facility, ex-
cept r key switching in some corridors.
2. Quark, ity of academic classroom receptacles is inadequate by today's standards
for educational technology. Most academic classrooms have only two or three
recep acles requiring many multi-outlet extension cords.
L. Telephone
1. Existing Verizon Contrex telephone system is fed underground from pole on
Oakland Road to an equipment mounting board on ground floor Main Electric
Roo of 1952 Building 'A3'. Telephone system wiring appeared concealed in
cond it throughout building, except for new outlet locations that utilize wire-
mold Number of service lines is unknown but seems to be minimal.
19 08/02/02
2. It was reported that system seems to be functional.
M. Clock and Program System:
1. Existing master clock and program system appears reasonably new and consists
of master clock in Administration Office Building 'A3', and secondary clocks in
classr Moms, large group areas and administration areas. The master
clock/~ontroller was replaced. Existing program system consists of program
bells in corridors, large group areas and on exterior walls.
2. It was reported that most system clocks are not working correctly, but that pro-
gram ells are working adequately. Many system clocks have been replaced with
batte operated or 120 volt plug-in type clocks.
N. Sound Paging od Intercom System:
1. Existing sound paging and intercom system consists of a Dukane style individual
classy om type control console in Administration Office Building 'A3', flush or
surface wail or ceiling recessed (1952) mounted speakers and privacy type inter-
com s itches in most classrooms, and combination clock speaker units with pri-
vacy switches (1969), and large group areas. Trumpet style speakers are located
in fo er shop type rooms. All-call paging from Administration console by mi-
cronh ne and eornanunication with each classroom are basic features of system.
2. Syste+ was reported to be barely functional with only general paging in the Cor-
ridors available to the Front Office Staff.
3. Cafet na, Gymnasium, and Auditorium have independent systems, it was re-
porte that each system is functional, and paging can be heard in each space.
0. Cable Televisi n System:
1. Existi g cable television system consists of a Media One Cable TV service from
Oakl d Road to the 1952 Building'A3'.
2. It was reported that system is functional.
3. Outle are located in classrooms and labs but a full survey is required to verify
full w .tent of this system.
P. Computer Dath Technology System:
1. A system of data outlets, head end equipment and data wiring have' been pro-
videdlin the recent past in classrooms, some laboratories and other spaces. Sys-
tem cabling is installed in surface wall and ceiling mounted wiremold. Outlets
are lol;ated in administrative offices, library, computer room, and classrooms.
2. System outlets have required additional receptacles and circuiting to be installed
in most areas. Some of these circuits are problematic with tripping and over-
loade circuits.
20 08/02/02
• v ~ .I.y ✓ V till i.vV v v II - r V' ~ _ - ..V v v _ _ .
3. It was ePorted that system is functional.
Q. Door Signal System:
1. Existi g doorbell systems consist of pushbutton at entrance to Boiler (1952),
Main ntrance (1952) and Receiving Dock (1952), and interior bells.
2. It coul~ not be verified if these systems are in working order. Further site inves-
tigatio' will be necessary.
R. Security
1. Existi ~g security system consists of control panel, door alarm contact switches
and m tion detectors located in high value rooms and selected entrances. System
is contlected to Police Department via communications transmitter.
2. Contr '1 panel is located in 1952 Building'A3%
3. It was reported by the Director of Facilities that the buildings have been broken
into d minor vandalism has occurred.
4. The sCcurity system was reported as operational but in need of repair and up-
grade.
S. Conclusions d Recommendations:
1. Electric Service and Service Equipment
a. Existing underground primary service and unit substations are approxi-
mately 30 and 50 years old. Distribution panels fed from unit substations
are approximatciy 30 and 50 years old. Ownership and maintenance of
primary service is responsibility of Reading Municipal Light Depart-
ment. Unit substations and distribution panels are owned and maintained
by the School,
b. Original equipment replacement parts are no longer available for unit
substations and distribution panels due to manufacturers being out of
stock. Replacement parts by alternate manufacturers are available but
costly. Capacity and condition of this equipment is inadequate to serve
present day educational and environmental technology needs.
C. Interrupting rating of the unit substations and panclboards may not meet
present interrupting rating of the Town of Reading's municipal power
network distribution system.
d. Service and service equipment should be replaced.
2. Interir Distribution System and Branch Circuit and Feeder Wiring
a Existing panelboards, motor controls and majority of wiring system arc
30 to 50 years old, and therefore, have exceeded their useful life.
21 08/02/02
4
3.
4.
Panelboards, motor controls and all wiring should be replaced. Existing
conduits may be reusable.
System
Existing 200kW 120/208V, 3~, 4W interior diesel fueled generator and
indoor 600 amp automatic transfer switch, 30 years old, appear to be in
functional condition and are exercised regularly. However, based on age
and visual appearance, it is recommended that the emergency generator
be replaced.
New Life Safety system automatic transfer switch, distribution equip-
ment and branch panelboards must be provided in new 2-hour fire rated
rooms in order to comply with Massachusetts Electric Code.
Existing automatic transfer switch may be able to be reused as non-
proprietary (standby) equipment and remain in main electric room with
new distribution and isolation control equipment added.
It was also reported that the Town of Reading does use a portion of the
High School as a Storm Shelter. This issue generally requires a much
larger generator to fully provide the proper features for an emergency
storm shelter.
b.
E~
a.
b.
C.
d.
System
Existing lighting system is generally 30 to 50 years old with some newer
types in specific areas. However, ballasts have been failing and present a
persistent maintenance problem. Majority of fixtures appear in marginal
to poor condition and lens discoloration and ballast failures will con-
tinue. Additional lighting should be provided in classrooms, corridors
and stairhalls where existing lighting is insufficient. Exterior lighting is
only adequate at best, and variety of lamp/ballast types result in high
maintenance costs.
a.
Interior and exterior lighting systems should be replaced.
System
Existing fire alarm system is approximately 30 years old and does not
comply with present day ADA, NFPA, and State Building Code re-
quirements due to insufficient coverage in classrooms, improper type
visual alarm signals, and device mounting heights on walls.
System should be replaced with Code compliant system. Existing con-
duit and outlet system may be reusable.
b.
5. fire
a.
b.
22
08/02/02
6
7.
8.
9.
10.
11.
Recep I cles and Switches
a. Existing receptacles and switches are a variety of 30 to 50 year old mate-
rials, except for newer devices in specific renovated areas. Quantity of
classroom receptacles and associated branch circuiting is inadequate.
b. Older devices should be replaced. Quantities of classroom recepta-
cles/branch circuiting should be substantially upgraded to provide for the
educational technology standards of today.
Telephone System
a. Existing telephone system appears very limited. New educational tech-
nology systems may require service upgrading,
b. System should be replaced.
Clock d Program System
a. Existing master clock and program system is only partly operating and
has exceeded its useful life.
b. System should be replaced.
Sound Paging and Intercom System
a. Existing sound paging and intercom system is barely functional and most
equipment is antiquated. Most classroom speakers are 30 to 50 years old
and should be replaced. Gymnasium systems appear in functional con-
dition.
b. Sound paging and intercom system central equipment should be replaced
with a new integrated telephone, intercom, paging systems. Speakers in
classrooms and large group areas should be replaced. Auditorium and
Gymnasium systems should he tested and upgraded as needed.
Cable 't'elevision System
a. Existing system is reportedly funcdonal.
b. System should be able to be maintained and expanded to satisfy aca-
demic needs.
Computer Data System
a.
b.
Existing system appears and is reported to be operational and may be ca-
pable of expansion.
Review of program needs and evaluation by school information technol-
ogy personnel should determine future of system in present state.
23 08/02/02
. _...r , rv u,_. v. . , ,
12. Door Signal System
a. Existing doorbell system probably needs replacement or integrated into
new telephone, intercom and paging system.
b. System may be maintained.
13. Securi ty System
a. Existing security system is, functional but in need of evaluation by
School and possible replacement. Exact age of system is unknown and
generally wiring is installed in surface wall mounted wiremold or cabling
above hung ceilings.
b. Noting that vandalism is present, a new state-of-the-art security systcm
should be provided throughout facility with all wiring concealed and
motion detection added to ground floor perimeter rooms with windows.
C. Installation of an additional CCTV (closed circuit television system)
should be evaluated by the Town of Reading, budget permitting.
FLANSBURGH ASSOCIATES
August 7, 2002
Reading Memorial High School Study
FAI No. 2204.00
List of Testing Procedures for Discussion with Committee
The following is a list of tests for your consideration. A number of these tests (italicized)
are necessary only in the event that a renovation project does not proceed, in order to
provide the town with an accurate assessment of the existing systems. The systems
involved would likely be replaced in a comprehensive renovation.
Costs do not include abatement of any hazardous material.
1) Infrared Scan of Existing Roofing
To determine extent of moisture penetration below roofs.
Estimated Cost: $2,500 to $4,000
Selective Demolition for examination of Roof Deck
Based on the results of the infrared scan, and field observation, core and analyze
selected areas of gyp. Crete and fibrous wood deck.
Estimated Cost: $4,000 to $6,000
2) Water Flow Test
To assess the ability of the water supply to support a fire suppression system
Estimated Cost: $1400 (Inclusive of fees)
3) Domestic Water Piping /Joints
To determine the quality of 50 year old piping and joints.
4) Roof Storm Water Piping
To determine the quality of 50 year old piping subject to acid rain and other
effects.
S) Sanitary Piping
To determine the quality of 50 year old piping. These lines are reported to be
deteriorated.
6) Domestic Water Service Entry
To assess the reliability of the service entry, the meter, and the main shut off
valves.
Estimated Cost for Items 2 thru 5: $6,000 to $8,000
7) Indoor Air Quality Tests ,
In locations to be determined, to take place in the fall. Fresh air intakes should be
cleaned and dampers proven operable priorto testing.
Estimated Cost: $5,000 to $10,000
8) Zone Control Valves
So that the hot water system and circulating pumps can be proven operable.
Estimated Cost: None (Can be done through existing Invensys Contract)
9) Low Pressure Steam Piping
To determine the quality of 50 year old piping.
Estimated Cost: $1,000
10) Emergency Generator
Verify proper operation and sequencing.
Estimated Cost: $5,500
11) Building Nonnal Electrical Distribution
Test existing unit substations, circuit breakers, primary switches, instruments etc.
including infrared scanning.
Estimated Cost: $14, 000 to $17, 000
12) Panel Testing
Test (2) main distribution panel boards and f ave randomly selected panel boards
for physical condition, operation, and life expectancy.
Estimated Cost: $6000
N z -
y
S ~
.J 1.
41
J ,
3
a 1
Z
CL Is 4u
S M .
. ,9
s °y
.
N ~ V ` w
o
cn
10 4, Cw
x.°°~~ 1wu, nS i 1
N
3,~;wi.~%..{~y .J._..~f ~.~e vC~~S►,~._~v1~1~ iii _ a
_._...,.._...._.._..m_..__._..._..........._....._......._.
0
U y rt ~
ig -1j,
i/ W„Z 0 F
M Z......................
IR,
W NS _
7-
..............._.............._J...
V
0
> r.
~ n?;~_d .............~.a.,...b....~ 0
c..
0
. i
o.......,.......:...~....y....................... ? o
$ 2 v..._..........o o
......................._,........_........-..................._....._._._.......:...._~~~.Z........~. _ _..._..........o..:....................................:.......:
N `
V C+