HomeMy WebLinkAbout2008-11-05 Conservation Commission MinutesConservation Commission, November 5, 2008
Reading Conservation Commission Meeting R"- C E 1 V E D
Selectmen's Meeting Room 7:00 PM ! 0 C L E R
0I G, Pa s s,
Wednesday, November 5, 2008 E
2900 DEC 15 A 10 20
Present: Chairman Mark Wetzel, Vice Chairman Bill Hecht, Barbara Stewart, Doug Green and
Fran Fink, Conservation Administrator.
The meeting was called to order at 7:00 P.M.
22 Roma Lane -Violation Notice
Paul Foti, owner, was present. The Commission had inspected the Buffer Zone and wetlands area
where trees had been cut without a permit. The owner did not have any proposed solution, but said
he did not know what the Town regulations were. The Commission reviewed a draft Enforcement
Order with Mr. Foti, requiring replacement of the trees. The Commission told him he had to leave
the tree stumps from the trees that he cut down. He said he needed help with the type of trees and
shrubs that he should use. The owner will come back with a proposed planting plan by January 15,
2009 and will do necessary interim steps till then.
Motion made by Mr. Hecht to issue the Enforcement Order as drafted and amended. Ms. Stewart
seconded. The vote was 4-0-0.
287 Lowell Street, DEP 270-515, RGB 2007-30 - Status of work
Mr. Wetzel said the property looks the same as it did two weeks ago. Ms. Fink said the owner did
get the rebar and she helped him measure and they put five stakes in the ground. She reminded him
to plant the shrubs. The Commission will inspect again in two weeks.
320 Haverhill Street, DEP 270-527, RGB 2008-6 - Status of work
Mr. Wetzel said they did a site visit and will revisit the site in the spring. Mr. Hecht said it did look
nice.
Public Hearing, Notice of Intent, Randall and Susan Kneeland, 68 Longwood Road, DEP 270=
542, RGB 2008-36, addition to house
Ms. Fink witnessed the soils tests but the engineer was not yet able to submit a report due to
malfunctioning equipment. Mr. Kneeland and the Commission reviewed the draft.
Motion made by Mr. Hecht to close the public hearing. Ms. Stewart seconded. The vote was 4-0-0.
Motion made by Mr. Hecht to issue an Order of Conditions as amended. Ms. Stewart seconded. The
vote was 4-0-0.
Public Hearing, Notice of Intent, Massachusetts Highway Department, Causeway Road
Depot, landfill capping, drainage, grading
Ken Leach of the Mass. Highway Department described the work to be done. Bill Beyer from Fay
Spofford & Thorndike described the site conditions and said they are basically putting 2 feet of
topsoil over the present soil. The proposed work was already approved by DEP. Mr. Beyer
described the swales that would be used to direct runoff as well as other work that would be
performed. The Commission was concerned about spillage from the gas pumps but the amount of
gas being pumped is not excessive and only done by highway personnel and MHD employees. Ms.
Conservation Commission, November 5, 2008
Fink had done a site visit and had expressed concern about runoff going into the wetlands. MHD
wants to do additional work regarding runoff at the site because they have the funds available and
would like it all to be under the same Order of Conditions. Mr. Wetzel thought that there was no
proposed treatment for storm water management included in the proposal, and he thought what was
proposed was worse than what exists now at the site. Ms. Fink said she thought the Commission
should be allowed to inspect the site. The Commission scheduled a site visit for November 14, 2008
at 7:30 AM. Ms. Fink gave her assessment of the site. Cameron Arnott lives on Causeway Road
near this site. He said the Town DPW paved over a manhole that was being used to collect runoff,
causing flooding on the street and his driveway. Ms. Fink advised Mr. Arnott to speak to DPW
about the situation.
Motion made by Mr. Hecht to continue the hearing to the next meeting. Ms. Stewart seconded. The
vote was 4-0-0.
Public Hearing, Notice of Intent, Robert Zeraschi, 10 Torre Street, DEP 270-538, RGB 2008-
35, day care center, parking lot, drainage, and grading
Ms. Fink did not hear from the Mr. Zeraschi and he did not attend the hearing. Ms. Fink explained
where the case was at this point. There is also a zoning issue with this location and Mr. Zeraschi
will be appearing before the ZBA in December. There has been a DRT meeting to discuss
permitting issues. The DEP Commissioner has not sent Final Determination regarding riverfront
versus canal to date. Ms. Fink has done a site visit and explained the conditions that she observed
during her visit. The Applicant wants to build a Goddard School. Ms. Fink found the specifications
on the Goddard website that were required by the Goddard Schools in order to obtain a franchise.
The DRT also had many questions that have yet to be answered.
Motion made by Mr. Hecht to continue the hearing to December 10, 2008. Ms. Stewart seconded.
The vote was 4-0-0.
Old/New Business:
Causeway Road MHD Depot, DEP 270-313 RGB 1998-17 - Status of work
(The Commission reviewed this matter during the public hearing form the site earlier in the
evening. MHD has completed most of the work, but not the restoration planting. A Certificate of
Compliance has not been issued. )
Camp Curtis Guild, Haverhill Street, DEP 270-440 - Request for Certificate of Compliance
Ms. Fink did a site visit and said the slope at the back of the firing range is well vegetated.
Motion made by Mr. Hecht to. issue a Certificate of Compliance. Ms. Steward seconded. The vote
was 4-0-0.
48 Pasture Road, DEP 270-471, RGB 2006-4 - Request for Certificate of Compliance
Ms. Fink said she had received a planting plan from the Applicant. The shrubs in the zone of natural
vegetation were not all native plants. A patio has been added to the plan. It was not clear whether
bounds had been set. The Commission will inspect before the next meeting.
1 General Avenue, DEP 270-428, RGB 2004-22 - As-built plans, Request for Certificate of
Compliance
Mr. Hecht said a site visit showed good results but there was still a good amount of trash that
should be removed on a regular basis.
Conservation Commission, November 5, 2008
Motion made by Mr. Hecht to issue a Certificate of Compliance. Mr. Wetzel seconded. The vote
was 4-0-0.
445 Pearl Street, Enforcement Order - Status of work
Mr. Wetzel said they did a site visit and bounds had been set. $1,000 in fines has not been paid.
They will ask the Applicant to attend a meeting.
Motion made by Mr. Hecht to close the Enforcement Order. Mr. Wetzel seconded. The vote was 4-
0-0.
101 Longwood Road, DEP 270-416, RGB 2004-10 - Status of work
Mr. Hecht said they did a site visit and again asked the Applicant to do what they had requested.
Another site visit will be scheduled.
Trail Committee
Mr. Wetzel went to a meeting and more are scheduled. There is another workday scheduled for the
viewing deck at Bare Meadow. Ms. Fink recommended holding an organizational meeting for the
Adopt a Trail Program with new volunteers.
88-98 Walkers Brook Drive, Honda Gallery is behind schedule and they now want to open the
buildings in March. They have not done graded and planted the grass drainage swales
successfully yet. Ms. Fink asked them to concentrate on the grading issue. A site visit will be
scheduled in two weeks to determine whether the site is ready for paving.
Colburn Road has two new catch basins and two manholes. Mr. Hecht does not know where
they go. DPW has not responded to past requests for plans.
Kylie Drive has two new lots (#7 and #8) under construction. Sidewalks are not paved and
street trees are not planted yet.
7 Adams Way planted bushes and poured a patio. Patio and retaining wall are not as shown on site
plan, and may cause ponding at the foundation of the house. Ms. Fink will follow up and will send a
letter.
6 Summer Avenue (shed)
Motion made by Mr. Hecht to accept minor project. Ms. Stewart seconded. The vote was 4-0-0.
508 West Street wants to build staircase in buffer zone.
Motion made by Mr. Hecht to accept minor project. Ms. Stewart seconded. The vote was 4-0-0.
Revised site plan for 57 Longwood Road. Ms. Fink distributed plans for review. The Commission
will do a site visit.
The High School sent an engineering report to Ms. Fink. Ms. Fink will send a letter to them. The
Commission is concerned because work is not complete and the permits will expire this winter.
Mr. Hecht thinks there should be more interaction between Conservation, CPDC, and ZBA.
8 Walkers Brook Drive, Salem Five Bank submitted foundation as-built plans that conform with
the approved site plans.
Conservation Commission, November 5, 2008
Parker Middle School - Ms. Fink will inspect and work with DPW on stream bank stabilization.
Bare Meadow Conservation Area - The Commission would like the bare soils around the
viewing platform to be mulched with salt marsh hay for the winter.
306 Main Street - A final Chapter 21 E report has been issued for the hazardous waste cleanup.
4