HomeMy WebLinkAbout2026-05-21 Killam School Building Committee Packet (PDF)
Town of Reading
Meeting Posting with Agenda
This Agenda has been prepared in advance and represents a listing of topics that the chair reasonably anticipates will be dis cussed
at the meeting. However the agenda does not necessarily include all matters which may be taken up at this meeting.
Page | 1
2018-07-16 LAG Board - Committee - Commission - Council:
Killam School Building Committee
Date: 2026-05-21 Time: 7:00 PM
Building: Reading Town Hall Location: Select Board Meeting Room
Address: 16 Lowell Street Agenda:
Purpose: General Business
Meeting Called By: Joshua Delaune on behalf of Chair Carla Nazzaro
Notices and agendas are to be posted 48 hours in advance of the meetings excluding
Saturdays, Sundays and Legal Holidays. Please keep in mind the Town Clerk’s hours of
operation and make necessary arrangements to be sure your posting is made in an
adequate amount of time. A listing of top ics that the chair reasonably anticipates will be
discussed at the meeting must be on the agenda.
All Meeting Postings must be submitted in typed format; handwritten notices will not be accepted.
Topics of Discussion:
Join Zoom Meeting
https://us06web.zoom.us/j/86529208380?pwd=I5NmUErKtAC3zfODGk62PmJyb2b13B.1
Meeting ID: 865 2920 8380
Passcode: 041913
1. Call to Order
2. Public Comment
3. KSBC Liaison Reports
4. CPL Financial Review*
a. MSBA Budget Review Request (BRR)*
b. Invoices
i. LBA*
ii. CPL*
iii. Facilities Clerk*
iv. Daily Times Chronicle*
v. BidDocs*
vi. Other*
c. Commitments
i. Other*
5. CPL Schedule Review*
a. Updated Bid Timeline
6. Approval of Prior Meeting Minutes
a. 04/22/2026*
b. 05/11/2026*
Town of Reading
Meeting Posting with Agenda
This Agenda has been prepared in advance and represents a listing of topics that the chair reasonably anticipates will be dis cussed
at the meeting. However the agenda does not necessarily include all matters which may be taken up at this meeting.
Page | 2
7. Future Agenda Items and Next Meeting dates
KSBC XLT KSBC Meeting
06/08/26 – Review Subs 06/15/26 – Vote GC
07/13/26 07/20/26 – Meet GC
08/11/26 08/17/26
9/14/26 9/21/26
8. Adjourn*
*Noted Potential vote required
TO:
FROM:
DATE:
RE:
Table 1: Owner's Contingency Budget Revision
Note
if any
0801-0000 Owner's
Contingency 0003-0000 Environmental &
Site $5,886 $1,143,433
0801-0000 Owner's
Contingency 0603-0000 Swing
Space/Modulars $15,991 $1,127,442
0801-0000 Owner's
Contingency 0102-9900
Other
Administrative
Costs
$251,163 $876,279
Table 2: Construction Contingency Budget Revision
Note
if anyNew Scope Exclusion Transfer Scope Exclusion
Use Table 2 below for identification of expenditures against the Construction Contingency. The Total Construction Contingency in the Current Total Project Budget, Exhibit A of the PFA
dated XX-XX-XXXX is $XXXXX . (Please attach all supporting documentation, e.g., executed contracts, amendments and/or supporting invoices for reimbursable expenses)
MSBA USE ONLY
From
Classifi-
cation
Code
From
Classification
Name
To
Classifi-
cation
Code
To
Classification
Name
Budget
Revision
Amount
Reason for transfer
Amount Remaining
in Construction
Contingency
Ineligible/Cost/Scope Items excluded from the Total
Facilities Grant
Facilities Clerk Contract
Modular Relacation
Reason for transfer
Amount Remaining
in Owner's
Contingency
Ineligible/Cost/Scope Items excluded from the Total
Facilities Grant
New Scope Exclusion Transfer Scope Exclusion
LBA Amd 14
The District further acknowledges and agrees that the need for these revisions to the Total Project Budget [have not/have] been identified in the OPM monthly report as required pursuant to
the Contract for Owner’s Project Management Services between the District and the OPM.
The District further acknowledges and agrees that all of the information contained in this Total Project Budget Revision Request has been reviewed and approved by the TOWN of
Reading’s School Building Committee, and it further certifies and acknowledges that the funds to pay for the costs associated with these proposed revisions are available as indicated by the
signatures noted below.
Use Table 1 below for identification of expenditures against the Owner’s contingency. The Total Owner’s Contingency in the Current Total Project Budget, Exhibit A of the PFA dated 04-
23-2025 is $1,149,319 . (Please attach all supporting documentation, e.g., executed contracts, amendments and/or supporting invoices for reimbursable expenses)
MSBA USE ONLY
From
Classifi-
cation
Code
From
Classification
Name
To
Classifi-
cation
Code
To
Classification
Name
Budget
Revision
Amount
The District acknowledges and agrees that it will not seek reimbursement from the Authority for any costs that exceed the already approved line item limits set forth in Exhibit A until after
the Authority has accepted this Total Project Budget Revision Request, and the Authority’s ProPay system has been adjusted accordingly.
The District further acknowledges and agrees that in accordance with Sections 3.6 and 3.7 of the Project Funding Agreement, any revisions to the Total Project Budget will not result in an
increase to the Total Facilities Grant amount set forth in Section 2.1 of the Project Funding Agreement.
J. Warren Killam Elementary School
MSBA Project ID Number: 202102460017
1-May-26
Director of Capital Planning
Thomas Milaschewski
Town of Reading
Project Funding Agreement Budget Revision Request, NUMBER: 1
Pursuant to Section 3.6 of the Project Funding Agreement between the Town of Reading (the “District”) and the MASSACHUSETTS SCHOOL BUILDING AUTHORITY (the
“Authority”), the District hereby requests a revision to the Total Project Budget, Exhibit A, dated 06/09/2025, for the J. Warren Killam Elementary School Project. As required, the District
has provided the information outlined in the table below to indicate the Total Project Budget categories (line items) affected, the amounts needed and the reasons for the proposed revision.
Table 3: Budget Revisions not originally from Owner's or Construction Contingency
Note
if any
0003-0000 Environmental
& Site 0004-0000 Other $79,874 $426,012
0004-0000 Other 0001-0000
OPM Feasibility
Study $15,500 $594,374
0201-0400 A&E Design
Development 0102-0500
Construction
Contract
Documents
$142,500 $2,057,500
0201-0400 A&E Design
Development 0102-0700
Construction
Contract
Administration
$142,500 $1,915,000
0201-0400 A&E Design
Development 0204-0300 Geotechnical $18,708 $1,896,292
0201-0400 A&E Design
Development 0203-9900
Other
Reimbursable
Costs
$8,792 $1,887,500
0201-0600 A&E Bidding 0204-1200 Traffic Studies $59,450 $290,550
0201-0600 A&E Bidding 0203-9900
Other
Reimbursable
Costs
$4,050 $286,500
0201-0800 A&E
Closeout 0203-9900
Other
Reimbursable
Costs
$43,858 $231,142
0201-0800 A&E
Closeout 0204-0400 Site Survey $5,000 $226,142
0201-0800 A&E
Closeout 0204-0300 Geotechnical $5,500 $220,642
0201-9900
A&E Other
Basic/Extra
Services
0204-0300 Geotechnical $113,806 $111,194
Notes (applicable where marked in corresponding rows of tables above)
1.)
2.)
3.)
MASSACHUSETTS SCHOOL BUILDING AUTHORITY
_________________________________________________Date: _________________
By (Please Print):Title: Director of _________________________________________
Title: Chief Executive Officer Title: Superintendent of Schools Title: Chair of the School Committee
Date:Date:Date:
_____________________________________ _____________________________________ _____________________________________
By: Jayne Wellman By: Dr. Henry Turner By: Thomas Wise
This budget transfer has already been incorporated into the ProPay budget as accepted in PFA Bid Amendment. All items noted as N/A in excluion columns; no budget revision
request to be entered into ProPay.
The exclusions noted in this BRR are not new exclusions, but rather maintain the overall amount of excluded costs in the Total Project Budget without increase. An exclusion
amount equal to the amount of the buyout savings entered in GMP contingency will be reduced in the divisions of the construction budget, offsetting the buyout savings amount,
in order that the total excluded amount does not increase as a result of the transfer of buyout savings.
The exclusions noted in this BRR are not new exclusions, but rather maintain the overall amount of excluded costs in the Total Project Budget without increase. An exclusion
amount equal to the amount of the exclusions shown in this BRR will be reduced from the Constructon Contingency line item, offsetting the amount being added to the
Construction Change Order line item shown in this BRR, in order that the total excluded amount does not increase as a result of the budget transfers included in this BRR.
Therefore the 1% or 2% potentially eligible Construction Contingency amount, whichever is applicable to this project, will not be reduced by this BRR.
By signing this Total Project Budget Revision Request, I
hereby certify that I have read and understand the terms
of this Request and further certify that the information
supplied by the District in the tables is true, accurate and
complete.
By signing this Total Project Budget Revision Request, I hereby
certify that I have read and understand the terms of this Request
and further certify that the information supplied by the District in
the tables is true, accurate and complete.
By signing this Total Project Budget Revision Request,
I hereby certify that I have read and understand the
terms of this Request and further certify that the
information supplied by the District in the tables is
true, accurate and complete.
LBA Amd 21
LBA Amd 19
LBA Amd 17
LBA Amd 18
LBA Amd 17
LBA Amd 17
LBA Amd 16
LBA Amd 17
LBA Amd 15
LBA Amd 15
For OPM SD Cost
Estimate FS/SD Cost
New Scope Exclusion Transfer Scope Exclusion
LBA Amd 13
Use Table 3 below for identification of expenditures not originally from Owner's or Construction Contingency. The Current Total Project Budget, Exhibit A of the PFA dated 08-01-2025
is $130,011,783 . (Please attach all supporting documentation, e.g., executed contracts, amendments and/or supporting invoices for reimbursable expenses)
MSBA USE ONLY
From
Classifi-
cation
Code
From
Classification
Name
To
Classifi-
cation
Code
To
Classification
Name
Budget
Revision
Amount
Reason for transfer
Amount Remaining
in Revised Budget
Line
Ineligible/Cost/Scope Items excluded from the Total
Facilities Grant
Town of Reading
Killam Elementary School
May 19, 2026 Project Budget and Cost Summary
A C D E F G H I J K
(Bud. Adj. Tab)(C+D)(Com. Cost tab)(E-F)(Forecast. tab, >G)(F+G+H)(Invoice Tab)(I-J)
Description PFA
Approved
Budget
Authorized
Changes
Approved
Budget
Committed
Costs
Uncommitte
d Costs
Forecast
Costs
Total Project
Costs
Expenditur
es to Date
Balance To
Spend
20 Construction
Construction $101,521,394 $0 $101,521,394 $147,800 $101,373,594 $0 $101,521,394 $0 $101,521,394
Change Orders $0 $0 $0 $0 $50,000 $50,000 $0 $50,000
Subtotal $101,521,394 $0 $101,521,394 $147,800 $101,373,594 $50,000 $101,571,394 $0 $101,571,394
30 Architectural & Engineering
Design Development $2,200,000 -$312,500 $1,887,500 $1,887,500 $0 $0 $1,887,500 $1,887,500 $0
Construction Documents $3,200,000 $142,500 $3,342,500 $3,342,500 $0 $0 $3,342,500 $3,342,500 $0
Bidding / Negotiations $350,000 -$63,500 $286,500 $286,500 $0 $0 $286,500 $143,250 $143,250
Closeout $275,000 -$54,358 $220,642 $191,000 $29,642 $0 $220,642 $0 $220,642
Construction Administration $3,200,000 $142,500 $3,342,500 $3,342,500 $0 $0 $3,342,500 $0 $3,342,500
Other Basic Services $225,000 -$113,806 $111,194 $0 $111,194 $0 $111,194 $0 $111,194
Geotechnical & GeoEnv. Engineering $200,000 $138,014 $338,014 $328,840 $9,174 $0 $338,014 $138,407 $199,607
Site Survey $50,000 $5,000 $55,000 $55,000 $0 $0 $55,000 $43,065 $11,935
Survey of Existing Conditions / Wetlands $25,000 $0 $25,000 $0 $25,000 $0 $25,000 $0 $25,000
Hazardous Materials $200,000 $0 $200,000 $172,700 $27,300 $0 $200,000 $35,200 $164,800
Traffic Studies $50,000 $59,450 $109,450 $109,450 $0 $0 $109,450 $86,955 $22,495
Other Reimbursable Costs $50,000 $56,700 $106,700 $106,700 $0 $0 $106,700 $88,725 $17,975
Printing (Over the Minimum)$20,000 $0 $20,000 $0 $20,000 $0 $20,000 $0 $20,000
A&E Feasibility Study $850,000 $0 $850,000 $850,000 $0 $0 $850,000 $850,000 $0
Subtotal $10,895,000 $0 $10,895,000 $10,672,690 $222,310 $0 $10,895,000 $6,615,603 $4,279,397
40 Administrative Costs
OPM Feasibility Study $280,000 $55,500 $335,500 $335,500 $0 $0 $335,500 $335,500 $0
OPM Design Development $500,000 $0 $500,000 $250,000 $250,000 $0 $500,000 $250,000 $250,000
OPM Construction Contract Documents $500,000 $0 $500,000 $500,000 $0 $0 $500,000 $279,088 $220,912
OPM Bidding $150,000 $0 $150,000 $150,000 $0 $0 $150,000 $0 $150,000
OPM Construction Contract Admin $3,300,000 $0 $3,300,000 $3,175,000 $125,000 $0 $3,300,000 $0 $3,300,000
OPM Closeout $500,000 $0 $500,000 $216,569 $283,431 $0 $500,000 $0 $500,000
OPM: Cost Estimates $90,000 $0 $90,000 $54,000 $36,000 $0 $90,000 $34,000 $56,000
Advertising $5,000 $0 $5,000 $2,388 $2,612 $0 $5,000 $2,388 $2,612
Other Administrative Costs $200,000 $251,163 $451,163 $451,163 $0 $100,000 $551,163 $6,550 $544,613
Other Project Costs (Moving)$150,000 $0 $150,000 $0 $150,000 $0 $150,000 $0 $150,000
Utility Fees $200,000 $0 $200,000 $0 $200,000 $0 $200,000 $0 $200,000
Legal $100,000 $0 $100,000 $0 $100,000 $0 $100,000 $0 $100,000
Testing Services $400,000 $0 $400,000 $54,746 $345,254 $0 $400,000 $0 $400,000
Swing Space / Modular $750,000 $16,870 $766,870 $766,870 $0 $0 $766,870 $759,779 $7,091
Environmental & Site (FS/SD)$500,000 -$73,988 $426,012 $283,130 $142,882 $0 $426,012 $273,130 $152,882
Other Project Costs (FS/SD)$570,000 $24,374 $594,374 $594,374 $0 $0 $594,374 $593,174 $1,200
Subtotal $8,195,000 $273,919 $8,468,919 $6,833,740 $1,635,180 $100,000 $8,568,919 $2,533,608 $6,035,311
50 Furniture, Fixtures and Equipment
Furniture, Fixtures and Equipment $1,587,500 $0 $1,587,500 $0 $1,587,500 $0 $1,587,500 $0 $1,587,500
Equipment $1,587,500 $0 $1,587,500 $0 $1,587,500 $0 $1,587,500 $0 $1,587,500
Technology $0 $0 $0 $0 $0 $0 $0 $0
Subtotal $3,175,000 $0 $3,175,000 $0 $3,175,000 $0 $3,175,000 $0 $3,175,000
Project Sub-Total $123,786,394 $273,919 $124,060,313 $17,654,230 $106,406,084 $150,000 $124,210,313 $9,149,211 $115,061,102
Construction Contingency (Hard Cost)$5,076,070 $0 $5,076,070 $5,076,070 -$50,000 $5,026,070 $5,026,070
Owner's Contingency (Soft Cost)$1,149,319 -$273,919 $875,400 $875,400 -$100,000 $775,400 $775,400
Subtotal $6,225,389 -$273,919 $5,951,470 $5,951,470 -$150,000 $5,801,470 $5,801,470
Project Total $130,011,783 $0 $130,011,783 $17,654,230 $112,357,553 $0 $130,011,783 $9,149,211 $120,862,572
70 Project Contingency Potential
Contingency
BUDGET COST CASH FLOW
Potential
Risk
Current
Contingency
5/19/2026 Page 1 of 1
Town of Reading
Killam Elementary School
05/19/26
Project Budget Adjustments
Adjustment Item BRR Adjusted Amount Date
Approved CODE Comments
END OF FS-SD
Move to Other Project Cost (FS/SD) from A&E FS iPFA $50,000.00 06/02/25 40-810 Moved to correct for New PFA
From A&E FS to Other Project Cost (FS/SD)iPFA ($50,000.00)06/02/25 30-290 Moved to correct for New PFA
Move to Owner's SC Cont from OPM FS VOID 06/02/25 40-810 Moved to correct for New PFA (was $55,500.) Correction Not needed
From OPM FS to Owner's SC Cont VOID 06/02/25 40-010 Moved to correct for New PFA (was -$55,500.) Correction Not needed
Move to Other Project Costs from Eviron & Site VOID 06/02/25 40-810 Moved to correct for New PFA (was $105,500.) Correction Not needed
Move to Owner's SC Cont from Eviron & Site VOID 06/02/25 40-810 Moved to correct for New PFA (was $8,792.) Correction Not needed
From Eviron & Site to Owner's SC Cont / Other PC VOID 06/02/25 40-800 Moved to correct for New PFA (was -$114,292.) Correction Not needed
Start of New PFA
Move to Environ & Site from Owner's SC Const BRR 001 $5,886.00 06/02/25 40-800 Moved to cover Designer Amd 14
From Owner's SC Const to Eviron & Site BRR 001 ($5,886.00)06/02/25 70-500 Moved to cover Designer Amd 14
Move to A&E Const Doc from A&E Design Development BRR 001 $142,500.00 06/02/25 30-130 Internal Budget Adjustments - LBA Amd 15
From A&E Design Development to A&E Const Doc BRR 001 ($142,500.00)06/02/25 30-120 Internal Budget Adjustments - LBA Amd 15
Move to A&E Const Admin from A&E Design Development BRR 001 $142,500.00 06/02/25 30-160 Internal Budget Adjustments - LBA Amd 15
From A&E Design Development to A&E Const Admin BRR 001 ($142,500.00)06/02/25 30-120 Internal Budget Adjustments - LBA Amd 15
Move to Geotech from A&E Design Development BRR 001 $18,708.00 06/02/25 30-210 Internal Budget Adjustments - LBA Amd 16
From A&E Design Development to Geotech BRR 001 ($18,708.00)06/02/25 30-120 Internal Budget Adjustments - LBA Amd 16
Move to Traffic Studies from A&E Bidding / Negotiations BRR 001 $59,450.00 07/14/25 30-260 Internal Budget Adjustments - LBA Amd 17
From A&E Bidding / Negotiations to Traffic Studies BRR 001 ($59,450.00)07/14/25 30-140 Internal Budget Adjustments - LBA Amd 17
Move to Other Reimbable Costs from Various BRR 001 $56,700.00 07/14/25 30-270 Internal Budget Adjustments - LBA Amd 17
From A&E Design Development to Other Reimbable Costs BRR 001 ($8,792.00)07/14/25 30-120 Internal Budget Adjustments - LBA Amd 17
From A&E Bidding / Negotiations to Other Reimbable Costs BRR 001 ($4,050.00)07/14/25 30-140 Internal Budget Adjustments - LBA Amd 17
From A&E Closeout to Other Reimbable Costs BRR 001 ($43,858.00)07/14/25 30-150 Internal Budget Adjustments - LBA Amd 17
Move to Site Survey from A&E Closeout BRR 001 $5,000.00 08/14/25 30-230 Internal Budget Adjustments - LBA Amd 18
From A&E Closeout to Site Survey BRR 001 ($5,000.00)08/14/25 30-150 Internal Budget Adjustments - LBA Amd 18
Move to A&E Geotech from Other Basic Services BRR 001 $113,806.00 11/12/25 30-210 Internal Budget Adjustments - LBA Amd 19
from Other Basic Services to A&E Geotech BRR 001 ($113,806.00)11/12/25 30-200 Internal Budget Adjustments - LBA Amd 19
Move to A&E Geotech from A&E Closeout BRR 001 $5,500.00 11/12/25 30-210 Internal Budget Adjustments - LBA Amd 21
from A&E Closeout to A&E Geotech BRR 001 ($5,500.00)11/12/25 30-150 Internal Budget Adjustments - LBA Amd 21
Move to Modular from SC Contingency BRR 001 $1,624.19 11/12/25 40-751 Budget Adjustments - Modulease CO 01
From SC Contingency to Modular BRR 001 ($1,624.19)11/12/25 70-500 Budget Adjustments - Modulease CO 01
Move to Modular from SC Contingency BRR 001 $4,000.00 11/12/25 40-751 Budget Adjustments - Modulease CO 01
From SC Contingency to Modular BRR 001 ($4,000.00)11/12/25 70-500 Budget Adjustments - Modulease CO 01
Move to Modular from SC Contingency BRR 001 $8,273.74 12/15/25 40-751 Budget Adjustments - Modular Relocation
From SC Contingency to Modular BRR 001 ($8,273.74)12/15/25 70-500 Budget Adjustments - Modular Relocation
Move to Modular from SC Contingency BRR 001 $2,093.00 03/16/26 40-751 Budget Adjustments - Geinapp Amd 02
From SC Contingency to Modular BRR 001 ($2,093.00)03/16/26 70-500 Budget Adjustments - Geinapp Amd 02
Move to Other Admin. Cost from SC Contingency BRR 001 $251,163.00 03/16/26 40-300 Budget Adjustments - Reading Clerk Contract (Dave)
From SC Contingency to Other Admin. Cost BRR 001 ($251,163.00)03/16/26 70-500 Budget Adjustments - Reading Clerk Contract (Dave)
Move to Modular from SC Contingency $879.37 40-751 Budget Adjustments - Modular Relocation
From SC Contingency to Modular ($879.37)70-500 Budget Adjustments - Modular Relocation
Total Approved Adjustments to Date $0.00 -$
12:23 PM 5/19/2026 Budget Adjustments Page 1 of 1
Town of Reading
Killam Elementary School
05/19/26
Committed Cost (Contracts/Pos)
VENDOR AMOUNT ISSUE
DATE
SIGNED/ RETURN
DATE ENCUM (PO)CODE MSBA Notes
Lavallee Brensinger Architects -$28,590.00 6/17/2025 07/14/25 LBA Amd 17 40-800 0003-0000 Deduct from LBA Amd 02 - Traffic Study (GPI)
Lavallee Brensinger Architects $50,160.00 6/17/2025 07/14/25 LBA Amd 17 30-260 0204-1200 Traffic Engineer (On-Ste)
Lavallee Brensinger Architects $59,290.00 6/17/2025 07/14/25 LBA Amd 17 30-260 0204-1200 Traffic Engineering (off-site)
Lavallee Brensinger Architects $77,000.00 6/17/2025 07/14/25 LBA Amd 17 30-270 0203-9900 Compliance Energy Modeling - TEDI, LEED and Backstop
Lavallee Brensinger Architects $7,700.00 6/17/2025 07/14/25 LBA Amd 17 30-270 0203-9900 Tree Removal and Protection Plan
Lavallee Brensinger Architects $24,750.00 8/13/2025 08/18/25 LBA Amd 18 30-230 0204-0400 Supplemental Survey - Charles & Haverhill Streets
ADF Painting Co $3,000.00 8/6/2025 08/18/25 PO 26000411 40-751 0603-0000 Exterior Painting - Modular Relocation
Gienapp Architects $10,447.73 8/14/2025 08/18/25 GEINAPP Amd 01 40-751 0603-0000 Amendment 01 for Reimbursable Costs
Complete Cleaning Co $3,500.00 6/23/2025 08/18/25 MSA 40-751 0603-0000 Move contents from Classrooms to Gym
Knox Company $535.00 8/14/2025 08/18/25 PO 26000488-001 40-751 0603-0000 Knoxbox Surface Mount Hinged Door - Modular Relocation
Lavallee Brensinger Architects $113,806.00 9/26/2025 10/14/25 LBA Amd 19 30-210 0204-0300 Soil Pre-Characterization
Lavallee Brensinger Architects $0.00 9/18/2025 10/14/25 LBA Amd 20 Void Void Tree Survey (Voided - Submitted at $7,623.00)
Complete Cleaning Co $140.00 10/1/2025 10/14/25 MSA 40-751 0603-0000 Modular Deep Cleaning
Lavallee Brensinger Architects $5,500.00 10/30/2025 10/31/25 LBA Amd 21 30-210 0204-0300 Additional Soil Pre-Characterization
Comm-Tract Corp $14,129.48 8/28/2025 11/12/25 PO NA 40-751 0603-0000 Modular Relocation - Fiber optic network
Partners Technology $2,270.88 8/19/2025 11/12/25 PO 26000521 40-751 0603-0000 Modular Relocation - Audio
Modulease $2,499.00 8/18/2025 11/12/25 Modulease CO 01 40-751 0603-0000 Modulease CO 01
Gov Connection Inc $8,273.74 12/8/2025 12/15/25 26000243 40-751 0603-0000 Modular Relocation - Computer Power Supply
BidDocs Online Inc $7,650.00 12/9/2025 12/15/25 PO N/A 40-300 0199-0000 Bid Hosting
Daily Times Chronicle $1,372.00 1/29/2026 02/09/26 PO NA 40-200 0103-0000 Newspaper Ad - Peer Review, Tax Consultant, Materials Testing, Early Bid & Prequal
Peer Review Recommndation - 4LEAF $37,513.00 12/15/2025 02/09/26 4LEAF Contract 40-300 0199-0000 Peer Review Recommndation - Structural & Code
Early Package Recommendation - System Contracting$147,800.00 1/20/2026 02/09/26 Systems Contract 20-200 0502-0000 Early Package Recommendation
Materials Testing Recommendation - UTS $54,746.00 12/10/2025 02/09/26 UTS Contract 40-700 0602-0000 Materials Testing Recommendation
Gienapp Architects $2,093.00 12/18/2025 03/16/26 GEINAPP Amd 02 40-751 0603-0000 Gienapp Remb. Services December 2025 - Modular Relocation
Daily Times Chronicle $190.94 3/11/2026 03/16/26 PO NA 40-200 0103-0000 Newspaper Ad - Elevator Prequal
David Dallaire - Facilities Clerk $406,000.00 2/18/2026 03/16/26 David Dallarie Contract 40-300 0102-9900 Reading Clerk Salary
Daily Times Chronicle $313.14 3/11/2026 04/22/26 PO NA 40-200 0103-0000 Newspaper Ad - FSB and GC Bid posting
Lavallee Brensinger Architects -$9,174.00 4/9/2026 04/22/26 LBA Amd 22 30-210 0204-0300 LBA Amd 16 Geotech Fee Error Correction
Daily Times Chronicle $511.71 5/18/2026 05/21/26 PO NA 40-200 0103-0000 Newspaper Ad - FSB and GC Re-Bid posting
Amazon Business $879.37 9/30/2025 05/21/26 PO KG26000RISE 40-751 0603-0000 Modular Relocation - Playground Equipment
TOTAL $17,654,229.70 $17,654,229.70
12:21 PM 5/19/2026 Committed Costs Page 1 of 1
Town of Reading
Killam Elementary School
05/19/26
Expenditures - Invoices/Requisistions
Invoice
Amount Vendor Invoice Number Invoice
Date
Approval
Date CODE Propay Code Propay
Subm. #Description
$33,733.00 Colliers Project Leaders 1132845 01/07/26 01/20/26 40-030 0102-0500 CPL Services December 2025 - CD
$350.00 BidDocs Online 25-9KRD-1 01/26/26 02/09/26 40-300 0199-0000 30B Switchgear - Online Bid Hosting
$501,375.00 Lavallee Brensinger Architects 23076 01/13/26 02/09/26 30-130 0201-0500 LBA Services December 2025 - CD
$1,783.50 Lavallee Brensinger Architects 23076 01/13/26 02/09/26 30-260 0204-1200 LBA Add Services December 2025 - Traffic Engineer
$1,925.00 Lavallee Brensinger Architects 23076 01/13/26 02/09/26 30-270 0203-9900 LBA Add Services December 2025 - Tree Removal and Protection
$221.49 Daily Times Chronicle 260087 02/04/26 02/09/26 40-200 0103-0000 NewsPaper Ad - Prequal
$501,375.00 Lavallee Brensinger Architects 23289 02/10/26 03/16/26 30-130 0201-0500 13 LBA Services January 2026 - CD
$720.72 Lavallee Brensinger Architects 23289 02/10/26 03/16/26 30-210 0204-0300 13 LBA Add Services January 2026 - Geotech
$1,155.00 Lavallee Brensinger Architects 23289 02/10/26 03/16/26 30-230 0204-0400 13 LBA Add Services January 2026 - Acoustic Survey
$1,398.53 Lavallee Brensinger Architects 23289 02/10/26 03/16/26 30-270 0203-9900 13 LBA Add Services January 2026 - Other Reimbursables
$9,959.40 Lavallee Brensinger Architects 23289 02/10/26 03/16/26 30-260 0204-1200 13 LBA Add Services January 2026 - Traffic Engineer
$6,710.00 Lavallee Brensinger Architects 23289 02/10/26 03/16/26 30-270 0203-9900 13 LBA Add Services January 2026 - Compliance Energy Modeling
$108,024.40 Lavallee Brensinger Architects 23289 02/10/26 03/16/26 30-210 0204-0300 13 LBA Add Services January 2026 - Soil Pre-Characterization
$63,340.00 Colliers Project Leaders 1143662 02/05/26 03/16/26 40-030 0102-0500 13 CPL Services January 2026 - CD
$42,122.00 Colliers Project Leaders 1153042 03/05/26 03/16/26 40-030 0102-0500 13 CPL Services February 2026 - CD
$190.94 Daily Times Chronicle 260201 03/11/26 03/16/26 40-200 0103-0000 13 NewsPaper Ad - Elevator Prequal
$313.14 Daily Times Chronicle 260329 04/07/26 04/22/26 40-200 0103-0000 13 NewsPaper Ad - FSB and GC Bid posting
$1,200.00 David Dallaire DDCOW01 04/01/26 04/22/26 40-300 0102-9900 13 David Dallaire - January 2026 Services
$2,500.00 David Dallaire DDCOW02 04/01/26 04/22/26 40-300 0102-9900 13 David Dallaire - February 2026 Services
$2,500.00 David Dallaire DDCOW03 04/01/26 04/22/26 40-300 0102-9900 13 David Dallaire - March 2026 Services
$501,375.00 Lavallee Brensinger Architects 23495 03/20/26 04/22/26 30-130 0201-0500 13 LBA Services February 2026 - CD
$180.18 Lavallee Brensinger Architects 23495 03/20/26 04/22/26 30-210 0204-0300 13 LBA Add Services February 2026 - Geotech
$5,610.00 Lavallee Brensinger Architects 23495 03/20/26 04/22/26 30-270 0203-9900 13 LBA Add Services February 2026 - Compliance Energy Modeling
$2,890.80 Lavallee Brensinger Architects 23495 03/20/26 04/22/26 30-210 0204-0300 13 LBA Add Services February 2026 - Soil Pre-Characterization
$67,504.00 Colliers Project Leaders 1162442 04/07/26 04/22/26 40-030 0102-0500 13 CPL Services March 2026 - CD
$334,250.00 Lavallee Brensinger Architects 23579 04/15/26 05/21/26 30-130 0201-0500 LBA Services March 2026 - CD
$540.54 Lavallee Brensinger Architects 23579 04/15/26 05/21/26 30-210 0204-0300 LBA Add Services March 2026 - Geotech
$1,100.00 Lavallee Brensinger Architects 23579 04/15/26 05/21/26 30-270 0203-9900 LBA Add Services March 2026 - Compliance Energy Modeling
$65,656.00 Colliers Project Leaders 1173421 05/06/26 05/21/26 40-030 0102-0500 CPL Services April 2026 - CD
$16,500.00 Colliers Project Leaders 1173421 05/06/26 05/21/26 40-100 0102-1100 CPL Services April 2026 - Cost Estimation
$511.71 Daily Times Chronicle 260488 05/18/26 05/21/26 40-200 0103-0000 NewsPaper Ad - FSB and GC Re-Bid posting
$143,250.00 Lavallee Brensinger Architects 23727 05/18/26 05/21/26 30-140 0201-0600 LBA Services April 2026 - Bid
$15,400.00 Lavallee Brensinger Architects 23727 05/18/26 05/21/26 30-240 0204-0200 LBA Add Services April 2026 - Hazardous Materials
$469.70 Lavallee Brensinger Architects 23727 05/18/26 05/21/26 30-210 0204-0300 LBA Add Services April 2026 - Geotech
$2,640.00 Lavallee Brensinger Architects 23727 05/18/26 05/21/26 30-270 0203-9900 LBA Add Services April 2026 - Compliance Energy Modeling
$2,475.00 Lavallee Brensinger Architects 23727 05/18/26 05/21/26 30-230 0204-0400 LBA Add Services April 2026 - Survey
$9,149,210.81 Total Spent to Date $9,149,210.81
12:25 PM 5/19/2026 Invoice Listing Page 1 of 1
Killam Elementary School
Estimated Project Cash Flow Sheet
OPM Designer &
Consultants FF&E & Misc Construction Contingency Estimated Outlay Actual outlay Est Cum Act Cum
1 Aug-23 $8,203 $8,203 $620 $8,203 $620
2 Sep-23 $15,096 $15,096 $11,903 $23,299 $12,523
3 Oct-23 $15,096 $15,096 $8,303 $38,395 $20,825
4 Nov-23 $15,096 $15,096 $7,433 $53,491 $28,258
5 Dec-23 $14,025 $14,025 $0 $67,516 $28,258
6 Jan-24 $14,584 $20,000 $34,584 $32,431 $102,100 $60,689
7 Feb-24 $14,584 $50,000 $64,584 $60,074 $166,684 $120,763
8 Mar-24 $14,584 $75,000 $89,584 $0 $256,268 $120,763
9 Apr-24 $14,584 $75,000 $89,584 $91,282 $345,852 $212,045
10 May-24 $14,584 $75,000 $2,500 $92,084 $141,991 $437,936 $354,036
11 Jun-24 $14,584 $75,000 $2,500 $92,084 $74,197 $530,020 $428,233
12 Jul-24 $14,584 $75,000 $89,584 $0 $619,604 $428,233
13 Aug-24 $14,584 $75,000 $89,584 $156,873 $709,188 $585,106
14 Sep-24 $14,584 $75,000 $89,584 $219,660 $798,772 $804,766
15 Oct-24 $14,584 $75,000 $89,584 $88,483 $888,356 $893,249
16 Nov-24 $14,584 $75,000 $89,584 $23,026 $977,940 $916,275
17 Dec-24 $14,584 $75,000 $89,584 $139,799 $1,067,524 $1,056,073
18 Jan-25 $15,174 $75,000 $90,174 $181,969 $1,157,698 $1,238,043
19 Feb-25 $17,245 $75,000 $92,245 $0 $1,249,943 $1,238,043
20 Mar-25 $25,000 $75,000 $100,000 $0 $1,349,943 $1,238,043
21 Apr-25 $25,000 $300,000 $25,000 $350,000 $0 $1,699,943 $1,238,043
22 May-25 $50,557 $300,000 $25,000 $375,557 $0 $2,075,500 $1,238,043
23 Jun-25 $66,000 $750,000 $35,000 $851,000 $579,060 $2,926,500 $1,817,103
24 Jul-25 $66,000 $750,000 $450,000 $25,000 $1,291,000 $609,774 $4,217,500 $2,426,877
25 Aug-25 $102,000 $750,000 $350,000 $25,000 $1,227,000 $1,498,900 $5,444,500 $3,925,776
26 Sep-25 $65,000 $475,000 $10,000 $25,000 $575,000 $52,410 $6,019,500 $3,978,186
27 Oct-25 $95,000 $475,000 $10,000 $25,000 $605,000 $753,568 $6,624,500 $4,731,754
28 Nov-25 $65,000 $475,000 $10,000 $25,000 $575,000 $1,345,814 $7,199,500 $6,077,568
29 Dec-25 $122,000 $475,000 $10,000 $25,000 $632,000 $57,565 $7,831,500 $6,135,133
30 Jan-26 $86,000 $475,000 $10,000 $25,000 $596,000 $602,438 $8,427,500 $6,737,571
31 Feb-26 $104,000 $475,000 $10,000 $25,000 $614,000 $506,806 $9,041,500 $7,244,376
32 Mar-26 $128,000 $475,000 $10,000 $25,000 $638,000 $737,089 $9,679,500 $7,981,465
33 Apr-26 $128,000 $185,000 $10,000 $50,000 $373,000 $584,073 $10,052,500 $8,565,538
34 May-26 $128,000 $185,000 $10,000 $50,000 $373,000 $583,672 $10,425,500 $9,149,211
35 Jun-26 $128,000 $150,000 $10,000 $750,000 $50,000 $1,088,000 $0 $11,513,500
36 Jul-26 $128,000 $150,000 $10,000 $1,500,000 $50,000 $1,838,000 $0 $13,351,500
37 Aug-26 $128,000 $150,000 $10,000 $2,250,000 $75,000 $2,613,000 $0 $15,964,500
38 Sep-26 $121,000 $150,000 $10,000 $4,500,000 $150,000 $4,931,000 $0 $20,895,500
39 Oct-26 $121,000 $150,000 $10,000 $5,500,000 $200,000 $5,981,000 $0 $26,876,500
40 Nov-26 $121,000 $150,000 $10,000 $6,500,000 $200,000 $6,981,000 $0 $33,857,500
41 Dec-26 $121,000 $150,000 $10,000 $6,500,000 $300,000 $7,081,000 $0 $40,938,500
42 Jan-27 $126,000 $150,000 $10,000 $6,500,000 $300,000 $7,086,000 $0 $48,024,500
43 Feb-27 $126,000 $150,000 $10,000 $6,500,000 $300,000 $7,086,000 $0 $55,110,500
44 Mar-27 $126,000 $150,000 $10,000 $6,500,000 $300,000 $7,086,000 $0 $62,196,500
45 Apr-27 $126,000 $150,000 $10,000 $6,500,000 $200,000 $6,986,000 $0 $69,182,500
46 May-27 $126,000 $150,000 $10,000 $6,500,000 $200,000 $6,986,000 $0 $76,168,500
47 Jun-27 $126,000 $150,000 $10,000 $5,500,000 $200,000 $5,986,000 $0 $82,154,500
48 Jul-27 $126,000 $150,000 $10,000 $4,500,000 $300,000 $5,086,000 $0 $87,240,500
49 Aug-27 $126,000 $150,000 $50,000 $4,500,000 $300,000 $5,126,000 $0 $92,366,500
50 Sep-27 $126,000 $150,000 $50,000 $4,000,000 $300,000 $4,626,000 $0 $96,992,500
51 Oct-27 $133,000 $150,000 $100,000 $4,000,000 $300,000 $4,683,000 $0 $101,675,500
52 Nov-27 $154,000 $150,000 $1,750,000 $4,000,000 $300,000 $6,354,000 $0 $108,029,500
May 19, 2026
Month Feasibility Study PeriodSchematic DesignFun-dingDesign DevelopConstruction DocumentsBidConstruction Phase5/19/2026 Page 1 of 2
Killam Elementary School
Estimated Project Cash Flow Sheet
OPM Designer &
Consultants FF&E & Misc Construction Contingency Estimated Outlay Actual outlay Est Cum Act Cum
May 19, 2026
Month Feasibility Study Period53 Dec-27 $154,000 $100,000 $1,100,000 $3,500,000 $250,000 $5,104,000 $0 $113,133,500
54 Jan-28 $127,000 $100,000 $250,000 $250,000 $175,000 $902,000 $0 $114,035,500
55 Feb-28 $127,000 $100,000 $250,000 $250,000 $175,000 $902,000 $0 $114,937,500
56 Mar-28 $108,000 $100,000 $25,000 $2,500,000 $175,000 $2,908,000 $0 $117,845,500
57 Apr-28 $100,000 $100,000 $25,000 $1,500,000 $150,000 $1,875,000 $0 $119,720,500
58 May-28 $100,000 $100,000 $25,000 $1,000,000 $100,000 $1,325,000 $0 $121,045,500
59 Jun-28 $100,000 $100,000 $25,000 $1,500,000 $100,000 $1,825,000 $0 $122,870,500
60 Jul-28 $100,000 $100,000 $25,000 $1,500,000 $100,000 $1,825,000 $0 $124,695,500
61 Aug-28 $100,000 $100,000 $25,000 $1,250,000 $100,000 $1,575,000 $0 $126,270,500
62 Sep-28 $82,000 $100,000 $25,000 $1,000,000 $100,000 $1,307,000 $0 $127,577,500
63 Oct-28 $82,000 $100,000 $25,000 $700,000 $100,000 $1,007,000 $0 $128,584,500
64 Nov-28 $82,000 $100,000 $25,000 $71,394 $100,000 $378,394 $0 $128,962,894
65 Dec-28 $82,000 $50,000 $25,000 $100,000 $257,000 $0 $129,219,894
66 Jan-29 $58,000 $50,000 $25,000 $100,000 $233,000 $0 $129,452,894
67 Feb-29 $51,000 $40,000 $15,000 $50,000 $156,000 $0 $129,608,894
68 Mar-29 $51,000 $40,000 $10,000 $25,000 $126,000 $0 $129,734,894
69 Apr-29 $19,000 $40,000 $5,000 $25,000 $89,000 $0 $129,823,894
70 May-29 $15,000 $40,000 $2,500 $25,000 $82,500 $0 $129,906,394
71 Jun-29 $15,000 $40,000 $2,500 $25,000 $82,500 $0 $129,988,894
72 Jul-29 $3,000 $5,208 $14,681 $22,889 $0 $130,011,783
$130,011,783 $5,375,500 $11,795,208 $4,980,000 $101,521,394 $6,339,681 $130,011,783 $9,149,211Commissioning & Close outConstruction Phase5/19/2026 Page 2 of 2
Town of Reading
Killam Elementary School
Estimated Project Cash Flow Graph
May 19, 2026
$0
$20,000,000
$40,000,000
$60,000,000
$80,000,000
$100,000,000
$120,000,000
$140,000,000
Estimated Expenditure
Actual Expenditure
12:29 PM 5/19/2026 Page 1 of 1
100 Federal Street
Floor 13
Boston, MA 02110
Main: +1 617 330 8000
www.cplusa.com
May 19, 2026
Jayne Wellman
Town Manager
Town of Reading
16 Lowell St
Reading, MA 01867
Subject: J Warren Killam Elementary School Designer Services
Invoice # 23727
Dear Ms. Wellman:
Colliers Project Leaders has reviewed the attached invoice and finds that the invoice is in
compliance with the contract and the amount is appropriate for the scope of services delivered during
this time period.
The referenced invoice is #23727 for Lavallee Brensinger Architects, for the Month of April 2026.
The total recommended Payment is $164,234.70
We recommend payment of this amount, using the following ProPay Codes and Breakdowns.
Invoice
Number Task Request This
Period
ProPay
Code
23727 Bidding & Negotiation $143,250.00 0201-0600
23727 Hazardous Materials $15,400.00 0204-0200
23727 Geotechnical $469.70 0204-0300
23727 Compliance Energy Modeling $2,640.00 0203-9900
23727 Additional Survey Services $2,475.00 0204-0400
Please feel free to contact me at (508) 326 6078 if you have any questions concerning this invoice.
Sincerely,
Justin Ferdenzi,
Project Manager
Justin.ferdenzi@collierseng.com
Attachments: 2026 04 LBA Inv#23727
Invoice Total:$164,234.70
Customer PO #23004647-001
Jayne Wellman
Town of Reading MA
16 Lowell Street
Reading, MA 01867
May 18, 2026
Project No:23-106-00
Invoice No:23727
155 Dow Street, Suite 400
Manchester, NH 03101
603-622-5450
Project 23-106-00 Reading Killam Elementary School
Professional Services from April 1, 2026 to April 30, 2026
Task 025 Feasibility Study
Fee
Total Fee 400,000.00
Percent Complete 100.00 Total Earned 400,000.00
Previous Fee Billing 400,000.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Task
Task 026 Reimbursable Expenses
0.00Total this Task
Task 100 Basic Services
Phase 002 Schematic Design
Fee
Total Fee 450,000.00
Percent Complete 100.00 Total Earned 450,000.00
Previous Fee Billing 450,000.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 003 Design Development - 0201-0400
Fee
Total Fee 1,887,500.00
Percent Complete 100.00 Total Earned 1,887,500.00
Previous Fee Billing 1,887,500.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 004 Construction Documents - 0201-0500
Fee
Project 2372723-106-00 Reading Killam Elementary School Invoice
Total Fee 3,342,500.00
Percent Complete 100.00 Total Earned 3,342,500.00
Previous Fee Billing 3,342,500.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 005 Bidding & Negotiation - 0201-0600
Fee
Total Fee 286,500.00
Percent Complete 50.00 Total Earned 143,250.00
Previous Fee Billing 0.00
Current Fee Billing 143,250.00
Total Fee 143,250.00
$143,250.00Total this Phase
Phase 006 Construction Administration - 0201-0700
Fee
Total Fee 3,342,500.00
Percent Complete 0.00 Total Earned 0.00
Previous Fee Billing 0.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 007 Closeout - 0201-0800
Fee
Total Fee 191,000.00
Percent Complete 0.00 Total Earned 0.00
Previous Fee Billing 0.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
$143,250.00Total this Task
Task 101 Reimbursable Expenses - Basic
0.00Total this Task
Task 200 Add Services
Phase 001 Amendment #1 - Survey
Fee
Total Fee 26,400.00
Percent Complete 100.00 Total Earned 26,400.00
Previous Fee Billing 26,400.00
Current Fee Billing 0.00
Total Fee 0.00
Page 2
Project 2372723-106-00 Reading Killam Elementary School Invoice
0.00Total this Phase
Phase 002 Amendment #2 - Traffic
This phase will not be billed any further, remaining funds have been moved to phase 015.
Fee
Total Fee 120,450.00
Percent Complete 76.2639 Total Earned 91,859.90
Previous Fee Billing 91,859.90
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 003 Amendment #3 - HazMat
Fee
Total Fee 4,950.00
Percent Complete 100.00 Total Earned 4,950.00
Previous Fee Billing 4,950.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 004 Amendment #4 - Environmental
Fee
Total Fee 14,520.00
Percent Complete 100.00 Total Earned 14,520.00
Previous Fee Billing 14,520.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 005 Amendment #5 - GeoTech
Fee
Total Fee 41,800.00
Percent Complete 100.00 Total Earned 41,800.00
Previous Fee Billing 41,800.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 006 Amendment #6 - Soil Testing - 0003-0000
Fee
Total Fee 2,750.00
Percent Complete 100.00 Total Earned 2,750.00
Previous Fee Billing 2,750.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Page 3
Project 2372723-106-00 Reading Killam Elementary School Invoice
Phase 007 Amendment #7 - HVAC Cost Estimate - 0004-0000
Fee
Total Fee 2,750.00
Percent Complete 100.00 Total Earned 2,750.00
Previous Fee Billing 2,750.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 008 Amendment #8 - SD Energy Modeling - 0004-0000
Fee
Total Fee 16,500.00
Percent Complete 100.00 Total Earned 16,500.00
Previous Fee Billing 16,500.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 009 Amendment #9 - Presentation Boards - 0004-0000
Fee
Total Fee 2,753.94
Percent Complete 100.00 Total Earned 2,753.94
Previous Fee Billing 2,753.94
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 010 Amendment #13 - Continuation of Services - 0004-0000
Fee
Total Fee 500,000.00
Percent Complete 100.00 Total Earned 500,000.00
Previous Fee Billing 500,000.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 011 Amendment #11 - HVAC System Comparison Estimate - 0003-0000
Fee
Total Fee 1,540.00
Percent Complete 100.00 Total Earned 1,540.00
Previous Fee Billing 1,540.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 013 Amendment #14 - Geothermal Add Services - 0003-0000
Fee
Total Fee 72,810.00
Page 4
Project 2372723-106-00 Reading Killam Elementary School Invoice
Percent Complete 100.00 Total Earned 72,810.00
Previous Fee Billing 72,810.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 014 Amendment #16 - DD-CL Add Services
Fee
Billing Phase Phase Fee
Percent
Complete Fee Earned
Previous Fee
Billing
Current Fee
Billing
Hazardous Materials - 0204-
0200
172,700.00 20.3822 35,200.00 19,800.00 15,400.00
Geotechnical - 0204-0300 148,038.00 6.4143 9,495.64 9,025.94 469.70
Geoenvironmental - 0204-
0300
70,670.00 25.4648 17,996.00 17,996.00 0.00
Soil Testing - 0204-0400 3,300.00 0.00 0.00 0.00 0.00
Building Control Plan - 0204-
0400
3,850.00 10.00 385.00 385.00 0.00
Supplemental Survey - 0204-
0400
11,000.00 100.00 11,000.00 11,000.00 0.00
Certified Plot Plan - 0204-0400 4,400.00 0.00 0.00 0.00 0.00
Site Acoustic Survey - 0204-
0400
7,700.00 90.00 6,930.00 6,930.00 0.00
Reimbursables - 0203-9900 22,000.00 18.2967 4,025.28 4,025.28 0.00
Total Fee 443,658.00 85,031.92 69,162.22 15,869.70
Total Fee 15,869.70
$15,869.70Total this Phase
Phase 015 Amendment #17 - DD-CL Add Services #2
Remaining funds of $28,590 have been moved from phase 002 to this phase.
Fee
Billing Phase Phase Fee
Percent
Complete Fee Earned
Previous Fee
Billing
Current Fee
Billing
Traffic Engineering 0204-1200 109,450.00 79.4476 86,955.40 86,955.40 0.00
Compliance Energy Modeling
0203-9900
77,000.00 100.00 77,000.00 74,360.00 2,640.00
Tree Removal and Protection
0203-9900
7,700.00 100.00 7,700.00 7,700.00 0.00
Total Fee 194,150.00 171,655.40 169,015.40 2,640.00
Total Fee 2,640.00
$2,640.00Total this Phase
Phase 016 Amendment # 18 - Additional Survey Services - 0204-0400
Fee
Total Fee 24,750.00
Percent Complete 100.00 Total Earned 24,750.00
Previous Fee Billing 22,275.00
Current Fee Billing 2,475.00
Total Fee 2,475.00
Page 5
Project 2372723-106-00 Reading Killam Elementary School Invoice
$2,475.00Total this Phase
Phase 017 Amendment #19 - Soil Pre-characterization
Fee
Total Fee 113,806.00
Percent Complete 97.4599 Total Earned 110,915.20
Previous Fee Billing 110,915.20
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 019 Amendment # 21 - Add'l Soil Precharacterization
Fee
Total Fee 5,500.00
Percent Complete 0.00 Total Earned 0.00
Previous Fee Billing 0.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
$20,984.70Total this Task
$164,234.70Total this Invoice
Project Outstanding Invoices
Invoice Number Invoice Date Balance Due
23579 4/15/2026 335,890.54
Total 335,890.54
Current Prior Total
Billings to Date 164,234.70 7,230,001.66 7,394,236.36
Your mission inspires us. Our creativity and knowledge empower you. Together we achieve excellence.
Thank you for your business. Our standard payment terms are thirty (30) days from invoice date. Any amounts remaining unpaid beyond thirty (30) days are
subject to interest at a rate of 1.0% per month, 12% per annum or at the legal prevailing rate.
Page 6
Invoice
Date:4/17/2026
Invoice No.:2412-10
Bill To
Lavallee Brensinger Architects
155 Dow Street, Suite 400
Manchester, NH 03101
Terms
Due on receipt
Client No.
2090
Project Name
Prop. J Warren Killam Elem. Sc
Project Number
2412
Location
Reading, MA
Invoice for Period Ending:03/29/2026
Total due this invoice
Balance Due
100 Chelmsford Road
Suite 2
Billerica, MA 01862
Phone: (978) 330-5912
Fax: (978) 330-5056
E-mail: LGCI@LGCinc.net
Description Qty Rate Amount
Services Performed March 2, 2026 through March 29, 2026
LGCI Proposal No. 25057 $126,240.00
Amount Previously Billed $ 8,205.40
Current LGCI Invoice No. 2412-10 $ 427.00
Total Billed to Date $8,632.40
Balance Remaining from Budget $117,607.60
Task 8.3 Consultation
Senior Geotechnical Staff - Consultation 3.5 122.00 427.00
Make check payable to Lahlaf Geotechnical Consulting, Inc.
$427.00
$427.00
Contract Amendment No. 16
Contract Amendment No. 16
BOLD
(Include Project Number and Invoice Number)
contractcompletebillingbilling
Total this Invoice
2,400.00
Currency
2,400.00
0.00
Invoice subtotal
Bank:
Percent Previous Current Remaining
Invoice Date:
Payment Terms:
Project No:
Invoice No:
120,000.00 117,600.00
USD
100.00%
Phase
Progress detail
2,400.00
Subtotal 2,400.00 0.00
Subtotal
LEED Model 15,000.00 100.00%14,100.00 900.00 0.00
Backstop ASR 30,000.00 100.00%28,500.00 1,500.00 0.00
TEDI ASR 25,000.00 100.00%25,000.00 0.00 0.00
Design Assistance Energy Modeling ASR 25,000.00 100.00%25,000.00 0.00 0.00
Killam Elementary School - Schematic Design
LBA Project Number: 23-106-00
For professional services through April 24, 2026
Killam Elementary School - SD
9300 FS-SD 25,000.00 100.00%25,000.00 0.00 0.00
Fee
Jenni Katajamaki Net 30 Days
Attn: Accounts Payable
155 Dow Street, Suite 400
Manchester, NH 03101
P23264_00
ARIV0038272
WFBIUS6S
INVOICE
Lavallee Brensinger Architects April 21, 2026
SEND PAYMENT & REMITTANCE ADVICE TO
Thornton Tomasetti, Inc.P.O. Box 781187 Philadelphia, PA 19178-1187 USA
120 Broadway
New York, NY 10271
accountsreceivable@thorntontomasetti.com
Wells Fargo Routing Number:121000248
420 Montgomery
Street
San Francisco, CA
94104
Account #:2000039485775
Account Name:Thornton Tomasetti, Inc.
Federal Tax ID:13-1251070 Swift:
Office: 14 York Street, Suite 201 Portland, ME 04101
207.245.6060
Contract Amendment No. 17
Compliance Energy Modeling
Samiotes Consultants, Inc.
Civil Engineering + Land Surveying
20 A Street
Framingham, MA 01701
T 508.877.6688
www.samiotes.com
Lavallee Brensinger PLLC
Jenni Katajamaki, RA, LEED, AP, MCPPO April 21, 2026
One Washington Mall Project No: 53086.01
11th Floor, Suite 1101 Invoice No: 24683
Boston, MA 02108
Project 53086.01 J Warren Killam Elem School - Reading (survey)
Email invoice to: apcon@lbpa.com
LBA Project No. 23-106-00
Professional Services from March 01, 2026 to March 31, 2026
Fee
Contract Percent Billings to Previously Current Fee
Task Amount Complete Date Billed Billing
Right-of-Way Survey T24 22,500.00 100.00 22,500.00 20,250.00 2,250.00
Total Fee 2,250.00
Total this Invoice $2,250.00
Outstanding Invoices
Number Date Balance
23826 8/12/2025 2,000.00 (Addendum #1 services)
Total 2,000.00
Terms: DUE UPON RECEIPT. 1.5% Service charge on past due amounts over 30 Days
Invoice
Contract Amendment No. 18
100 Federal Street
Floor 13
Boston, MA 02110
Main: +1 617 330 8000
www.cplusa.com
May 19, 2026
Jayne Wellman
Town Manager
Town of Reading
16 Lowell St
Reading, MA 01867
Subject: J Warren Killam Elementary School Designer Services
Invoice # 23579
Dear Ms. Wellman:
Colliers Project Leaders has reviewed the attached invoice and finds that the invoice is in
compliance with the contract and the amount is appropriate for the scope of services delivered during
this time period.
The referenced invoice is #23579 for Lavallee Brensinger Architects, for the Month of March 2026.
The total recommended Payment is $335,890.54
We recommend payment of this amount, using the following ProPay Codes and Breakdowns.
Invoice
Number Task Request This
Period
ProPay
Code
23579 Construction Documents $334,250.00 0201-0500
23579 Geotechnical $540.54 0204-0300
23579 Compliance Energy Modeling $1,100.00 0203-9900
Please feel free to contact me at (508) 326 6078 if you have any questions concerning this invoice.
Sincerely,
Justin Ferdenzi,
Project Manager
Justin.ferdenzi@collierseng.com
Attachments: 2026 03 LBA Inv#23579
Invoice Total:$335,890.54
Customer PO #23004647-001
Matthew Kraunelis
Town of Reading MA
16 Lowell Street
Reading, MA 01867
April 15, 2026
Project No:23-106-00
Invoice No:23579
155 Dow Street, Suite 400
Manchester, NH 03101
603-622-5450
Project 23-106-00 Reading Killam Elementary School
Professional Services from March 1, 2026 to March 31, 2026
Task 025 Feasibility Study
Fee
Total Fee 400,000.00
Percent Complete 100.00 Total Earned 400,000.00
Previous Fee Billing 400,000.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Task
Task 026 Reimbursable Expenses
0.00Total this Task
Task 100 Basic Services
Phase 002 Schematic Design
Fee
Total Fee 450,000.00
Percent Complete 100.00 Total Earned 450,000.00
Previous Fee Billing 450,000.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 003 Design Development - 0201-0400
Fee
Total Fee 1,887,500.00
Percent Complete 100.00 Total Earned 1,887,500.00
Previous Fee Billing 1,887,500.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 004 Construction Documents - 0201-0500
Fee
Project 2357923-106-00 Reading Killam Elementary School Invoice
Total Fee 3,342,500.00
Percent Complete 100.00 Total Earned 3,342,500.00
Previous Fee Billing 3,008,250.00
Current Fee Billing 334,250.00
Total Fee 334,250.00
$334,250.00Total this Phase
Phase 005 Bidding & Negotiation - 0201-0600
Fee
Total Fee 286,500.00
Percent Complete 0.00 Total Earned 0.00
Previous Fee Billing 0.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 006 Construction Administration - 0201-0700
Fee
Total Fee 3,342,500.00
Percent Complete 0.00 Total Earned 0.00
Previous Fee Billing 0.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 007 Closeout - 0201-0800
Fee
Total Fee 191,000.00
Percent Complete 0.00 Total Earned 0.00
Previous Fee Billing 0.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
$334,250.00Total this Task
Task 101 Reimbursable Expenses - Basic
0.00Total this Task
Task 200 Add Services
Phase 001 Amendment #1 - Survey
Fee
Total Fee 26,400.00
Percent Complete 100.00 Total Earned 26,400.00
Previous Fee Billing 26,400.00
Current Fee Billing 0.00
Total Fee 0.00
Page 2
Project 2357923-106-00 Reading Killam Elementary School Invoice
0.00Total this Phase
Phase 002 Amendment #2 - Traffic
This phase will not be billed any further, remaining funds have been moved to phase 015.
Fee
Total Fee 120,450.00
Percent Complete 76.2639 Total Earned 91,859.90
Previous Fee Billing 91,859.90
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 003 Amendment #3 - HazMat
Fee
Total Fee 4,950.00
Percent Complete 100.00 Total Earned 4,950.00
Previous Fee Billing 4,950.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 004 Amendment #4 - Environmental
Fee
Total Fee 14,520.00
Percent Complete 100.00 Total Earned 14,520.00
Previous Fee Billing 14,520.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 005 Amendment #5 - GeoTech
Fee
Total Fee 41,800.00
Percent Complete 100.00 Total Earned 41,800.00
Previous Fee Billing 41,800.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 006 Amendment #6 - Soil Testing - 0003-0000
Fee
Total Fee 2,750.00
Percent Complete 100.00 Total Earned 2,750.00
Previous Fee Billing 2,750.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Page 3
Project 2357923-106-00 Reading Killam Elementary School Invoice
Phase 007 Amendment #7 - HVAC Cost Estimate - 0004-0000
Fee
Total Fee 2,750.00
Percent Complete 100.00 Total Earned 2,750.00
Previous Fee Billing 2,750.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 008 Amendment #8 - SD Energy Modeling - 0004-0000
Fee
Total Fee 16,500.00
Percent Complete 100.00 Total Earned 16,500.00
Previous Fee Billing 16,500.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 009 Amendment #9 - Presentation Boards - 0004-0000
Fee
Total Fee 2,753.94
Percent Complete 100.00 Total Earned 2,753.94
Previous Fee Billing 2,753.94
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 010 Amendment #13 - Continuation of Services - 0004-0000
Fee
Total Fee 500,000.00
Percent Complete 100.00 Total Earned 500,000.00
Previous Fee Billing 500,000.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 011 Amendment #11 - HVAC System Comparison Estimate - 0003-0000
Fee
Total Fee 1,540.00
Percent Complete 100.00 Total Earned 1,540.00
Previous Fee Billing 1,540.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 013 Amendment #14 - Geothermal Add Services - 0003-0000
Fee
Total Fee 72,810.00
Page 4
Project 2357923-106-00 Reading Killam Elementary School Invoice
Percent Complete 100.00 Total Earned 72,810.00
Previous Fee Billing 72,810.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 014 Amendment #16 - DD-CL Add Services
Fee
Billing Phase Phase Fee
Percent
Complete Fee Earned
Previous Fee
Billing
Current Fee
Billing
Hazardous Materials - 0204-
0200
172,700.00 11.465 19,800.00 19,800.00 0.00
Geotechnical - 0204-0300 148,038.00 6.097 9,025.94 8,485.40 540.54
Geoenvironmental - 0204-
0300
70,670.00 25.4648 17,996.00 17,996.00 0.00
Soil Testing - 0204-0400 3,300.00 0.00 0.00 0.00 0.00
Building Control Plan - 0204-
0400
3,850.00 10.00 385.00 385.00 0.00
Supplemental Survey - 0204-
0400
11,000.00 100.00 11,000.00 11,000.00 0.00
Certified Plot Plan - 0204-0400 4,400.00 0.00 0.00 0.00 0.00
Site Acoustic Survey - 0204-
0400
7,700.00 90.00 6,930.00 6,930.00 0.00
Reimbursables - 0203-9900 22,000.00 18.2967 4,025.28 4,025.28 0.00
Total Fee 443,658.00 69,162.22 68,621.68 540.54
Total Fee 540.54
$540.54Total this Phase
Phase 015 Amendment #17 - DD-CL Add Services #2
Remaining funds of $28,590 have been moved from phase 002 to this phase.
Fee
Billing Phase Phase Fee
Percent
Complete Fee Earned
Previous Fee
Billing
Current Fee
Billing
Traffic Engineering 0204-1200 109,450.00 79.4476 86,955.40 86,955.40 0.00
Compliance Energy Modeling
0203-9900
77,000.00 96.5714 74,360.00 73,260.00 1,100.00
Tree Removal and Protection
0203-9900
7,700.00 100.00 7,700.00 7,700.00 0.00
Total Fee 194,150.00 169,015.40 167,915.40 1,100.00
Total Fee 1,100.00
$1,100.00Total this Phase
Phase 016 Amendment # 18 - Additional Survey Services - 0204-0400
Fee
Total Fee 24,750.00
Percent Complete 90.00 Total Earned 22,275.00
Previous Fee Billing 22,275.00
Current Fee Billing 0.00
Total Fee 0.00
Page 5
Project 2357923-106-00 Reading Killam Elementary School Invoice
0.00Total this Phase
Phase 017 Amendment #19 - Soil Pre-characterization
Fee
Total Fee 113,806.00
Percent Complete 97.4599 Total Earned 110,915.20
Previous Fee Billing 110,915.20
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
Phase 019 Amendment # 21 - Add'l Soil Precharacterization
Fee
Total Fee 5,500.00
Percent Complete 0.00 Total Earned 0.00
Previous Fee Billing 0.00
Current Fee Billing 0.00
Total Fee 0.00
0.00Total this Phase
$1,640.54Total this Task
$335,890.54Total this Invoice
Project Outstanding Invoices
Invoice Number Invoice Date Balance Due
23495 3/20/2026 510,055.98
Total 510,055.98
Current Prior Total
Billings to Date 335,890.54 6,894,111.12 7,230,001.66
Your mission inspires us. Our creativity and knowledge empower you. Together we achieve excellence.
Thank you for your business. Our standard payment terms are thirty (30) days from invoice date. Any amounts remaining unpaid beyond thirty (30) days are
subject to interest at a rate of 1.0% per month, 12% per annum or at the legal prevailing rate.
Page 6
!"#$%&
!"#$ !"!#$#%
%&’()*#+,(-$#&’#($"
.)//+0(
)*+*,,--./0-12314-0.506738-682
’99.:;<.=80--8>.=?38-.&$$
@*167-28-0>.AB..$ ’$’
0#123
:?-.;1.0-6-3C8
4/)#&"+,(-
#$"$
51(6#*"+,!2#
D0;CE.F.G*00-1.H3,,*I.J,-IE.=6
51(6#*"+,728#1
#&’#
9(*!")(&
K-*L314>.@5
%&’()*#+:(1+5#1)(;+<&;)&=$$ !$’!#$#%
’#()*+,-&+(.$/+$!"#$%&
0)*)!%&+1-&
.’$$.M7-,I2N;0L.K;*L
.=?38-.#
./3,,-036*>.@5.$’O%#
.D7;1-P.Q"ROS. $(9"’#
.T*UP.Q"ROS. $(9$9%
.J(I*3,P.)VMWX)VM316E1-8
#3*1)>")(&?"@ A!"#B2(7&"
=-0+36-2.D-0N;0I-L.T-Y0?*0Z.#>.#$#%.870;?47.@*067.’>.#$#%
)VMW.D0;C;2*,.A;E.#9$9R..................[’#%>#&$E$$
5I;?18.D0-+3;?2,Z./3,,-L......................[.R>R’&E$$
M?00-18.)VMW.W1+;36-.A;E.#&’#($"........[...&"’E&$
\;8*,./3,,-L.8;.:*8-................................[O>#$9E&$
/*,*16-.K-I*31314.N0;I./?L4-8........[’’O>$ &E%$
\*2].OE .M;12?,8*83;1
=-13;0.V-;8-67136*,.J1431--0.(.M;12?,8*83;1 #E’ # &E$$ &"’E&$
@*]-.67-6].C*Z*Y,-.8;.)*7,*N.V-;8-67136*,.M;12?,8314>.W16E
[&"’E&$
[&"’E&$
Proj. #23-106-00
Task 200
Phase 014
BOLD
(Include Project Number and Invoice Number)
contractcompletebillingbilling
Total this Invoice
2,000.00
Currency
2,000.00
0.00
Invoice subtotal
Bank:
Percent Previous Current Remaining
Invoice Date:
Payment Terms:
Project No:
Invoice No:
120,000.00 115,600.00
USD
98.00%
Phase
Progress detail
2,000.00
Subtotal 2,000.00 2,400.00
Subtotal
LEED Model 15,000.00 94.00%14,100.00 0.00 900.00
Backstop ASR 30,000.00 95.00%28,500.00 0.00 1,500.00
TEDI ASR 25,000.00 100.00%24,000.00 1,000.00 0.00
Design Assistance Energy Modeling ASR 25,000.00 100.00%24,000.00 1,000.00 0.00
Killam Elementary School - Schematic Design
LBA Project Number: 23-106-00
For professional services through March 27, 2026
Killam Elementary School - SD
9300 FS-SD 25,000.00 100.00%25,000.00 0.00 0.00
Fee
Jenni Katajamaki Net 30 Days
Attn: Accounts Payable
155 Dow Street, Suite 400
Manchester, NH 03101
P23264_00
ARIV0035340
WFBIUS6S
INVOICE
Lavallee Brensinger Architects March 24, 2026
SEND PAYMENT & REMITTANCE ADVICE TO
Thornton Tomasetti, Inc.P.O. Box 781187 Philadelphia, PA 19178-1187 USA
120 Broadway
New York, NY 10271
accountsreceivable@thorntontomasetti.com
Wells Fargo Routing Number:121000248
420 Montgomery
Street
San Francisco, CA
94104
Account #:2000039485775
Account Name:Thornton Tomasetti, Inc.
Federal Tax ID:13-1251070 Swift:
Office: 14 York Street, Suite 201 Portland, ME 04101
207.245.6060
Compliance
Energy Modeling
Proj. #23-106-00
Task 200
Phase 015
100 Federal Street
Floor 13
Boston, MA 02110
www.cplusa.com
May 18, 2026
Jayne Wellman
Town Manager
Town of Reading
16 Lowell St
Reading, MA 01867
Subject: J Warren Killam Elementary School Project Management Services
Invoice #0001173421
Dear Ms. Wellman:
Attached please find Colliers Project Leaders (CPL) invoice #0001173421, in the amount of
$82,156.00 for Owner Project Manager services as authorized in Contract for the J Warren Killam
Elementary School Project, during the month of April 2026.
In the period of April 1 - April 30, 2026, the specific tasks undertaken and billed to this invoice include:
Prepare and attend in person School Building Committee meeting.
Attend and prepared agendas for XLT Meetings.
Attend Design meetings.
Review and process Architect invoice.
Coordinate with the Town on the updated prequalification list.
Coordinate with the design team on bid RFIs and addenda.
Modular relocation invoices and commitment review.
Coordinate with the Town on bidding preparation.
Managed GC and FSB prequalification in BidDocs.
Managed project bidding process.
Coordained with third-party consultant for structural and code review.
Please take note of our new remit to address;101 Crawfords Corner Road Suite 3400, Holmdel, New
Jersey 07733. Please feel free to contact me at (508) 215-6050 if you have any questions concerning this
invoice.
Sincerely,
Justin Ferdenzi,ProPay Code:
Project Manager $65,656.00: 0102-0500
Attachement : 2026 04 Colliers Invoice #1173421 $16,500.00: 0102-1100
For Professional Services Rendered Through 4/30/2026
Current Billings 82,156.00 8
Amount Due This Bill 82,156.00
Billings
Fee Remaining Fee % Complete To Date Previous Current
Feasibility Study / Schematic Design Phase 320,000.00 0.00 100.00 320,000.00 320,000.00 0.00
Cost Estimating 15,500.00 0.00 100.00 15,500.00 15,500.00 0.00
Design Development 250,000.00 0.00 100.00 250,000.00 250,000.00 0.00
Construction Documents 500,000.00 230,912.25 53.82 269,087.75 203,431.75 65,656.00
Bidding 150,000.00 150,000.00 0.00 0.00 0.00 0.00
Construction Administration 3,175,000.00 3,175,000.00 0.00 0.00 0.00 0.00
Completion / Closeout 216,569.00 216,569.00 0.00 0.00 0.00 0.00
Estimating 54,000.00 10,000.00 81.48 44,000.00 27,500.00 16,500.00
Subtotal:4,681,069.00 3,782,481.25 19.20 898,587.75 816,431.75 82,156.00
mike.carroll@collierseng.com;
justin.ferdenzi@collierseng.com
Town of Reading
Attn: Jayne Wellman
16 Lowell St
Reading, MA 01867
Invoice : 0001173421
Invoice Date : 5/6/2026
Project : 23010425A
Project Manager: Osterman, Derek
Project Name : Reading MA/ OPM - J. Warren
Killam Elementary School
REMIT TO: Colliers Project Leaders USA NE, LLC 101 Crawfords Corner Road, Suite 3400 | Holmdel, NJ 07733
Phone: 877-627-3772 | Fax: 732-383-1980
In accordance with our business terms and conditions, acceptance of this invoice is implied unless Colliers Project Leaders USA NE, LLC is notified by 14 days from the date of this invoice.
If timely payment cannot be made due to any discrepancy, please E-mail a brief explanation to Billing@colliersengineering.com and we will reply as soon as possible.
EFT/ACH PAYMENT INFO: Colliers Engineering & Design, Inc. | JP Morgan Chase | Routing 021000021 | Account# 836759092
Project: 23010425A - Reading MA/ OPM - J. Warren Killam Elementary School Invoice: 0001173421
PM05 - Construction Documents
Labor
Rate Labor
Class Hours Rate Amount
Assistant Project Manager 69.50 198.0000 13,761.00
Financial Specialists 3.00 177.0000 531.00
Project Director 36.50 354.0000 12,921.00
Project Manager 79.00 213.0000 16,827.00
Regional Director 2.00 458.0000 916.00
Senior Project Manager 75.00 276.0000 20,700.00
Total Rate Labor 65,656.00
Total Labor 65,656.00
Total Bill Task: PM05 - Construction Documents 65,656.00
PM09 - Estimating
Outside Services
Expenses
Account / Vendor Amount
Subcontractors - Other
A.M. Fogarty & Associates, Inc.16,500.00
Total Expenses 16,500.00
Total Outside Services 16,500.00
Total Project: 23010425A - Reading MA/ OPM - J. Warren Killam Elementary School 82,156.00
Page: 1
100 Federal Street,
Floor 33
Boston, MA 02110
Main: +1 617 330 8000
www.cplusa.com
May 19, 2026
Jayne Wellman
Town Manager
Town of Reading
16 Lowell St
Reading, MA 01867
Subject: J. Warren Killam Elementary School: Modular Relocation – Playground Equipment
PO# KG26000RISE Invoice# 1YNH-H979-6YWR
Dear Mr. Kraunelis:
Colliers Project Leaders, the Owner’s Project Manager, has reviewed the attached, invoice
#1YNH-H979-6YWR, and subject to approval of the corresponding Commitment recommend
payment of $879.37 for modular relocation playground equipment for the J. Warren Killam
Elementary School Project.
Subject to approval of the corresponding Commitment, we recommend payment of this
amount, using the following ProPay Codes and Breakdowns.
Invoice
Number
Task Request
This Period
ProPay
Code
1YNH-
H979-
6YWR
Modular Relocation - Playground
Equipment $879.37 0603-0000
Please feel free to contact me at (774) 294-6659 if you have any questions concerning this invoice.
Sincerely,
Justin Ferdenzi,
Project Manager
Justin.ferdenzi@collierseng.com
Credit Memo
For customer support, visit www.amazon.com/contact-us.
Page 1 of 1
Credit Memo Date
Credit Memo #
Invoice Date
Invoice #
Account #
Order #
Payment Terms
Registered Business Name
Town Of Reading
Bill To
Town Of Reading
16 Lowell Street
Reading, MA 01867
Ship To
Kevin Gerstner
62 OAKLAND RD
READING, MA 01867-1613
Net 30
111-2854049-0310629
A1ZYRRWOB9HS9H
1YNH-H979-6YWR
30-Sep-2025
1FPV-DJ1C-HX67
31-Oct-2025
Credit Memo Summary
Item Subtotal ($64.99)
Shipping & Handling $0.00
Promos & Discounts $0.00
Sales Tax $0.00
Amount Due ($64.99)USD
Order Information
Kevin GerstnerOrdered By
PO #
Department Facilities
KG26000RISE
Kevin Gerstner
Applying this credit note
Email the credit memo numbers you want to use and the Amazon-provided
invoice numbers you want to pay to ar-businessinvoicing@amazon.com
Credit Memo Details
Description Qty
Unit
Price
Subtotal
before
Tax
Tax
Rate Subtotal
Step2 Push Around Buggy Kids Push Car, Ride On Toy, Stroller
Substitute, Includes Seat Belt & Horn, Made of Durable Plastic, Max
Weight 50 lbs., For Toddlers 1.5-4 Years Old, Red
ASIN: B004MWI0GI Sold by: Amazon.com Services, Inc
1 $64.99 ($64.99)0.000%($64.99)
Invoice #1YNH-H979-6YWR |September 30, 2025
Invoice
For customer support, visit www.amazon.com/contact-us.
Page 1 of 3
Account #
Payment terms
Purchase date
Purchased by
PO #
Department
Registered business name
Town Of Reading
Bill to
Town Of Reading
16 Lowell Street
Reading, MA 01867
Ship to
Kevin Gerstner
62 OAKLAND RD
READING, MA 01867-1613
Facilities
KG26000RISE
Kevin Gerstner
23-Sep-2025
Net 30
A1ZYRRWOB9HS9HInvoice summary
Item subtotal before tax $944.36
Shipping & handling $0.00
Promos & discounts $0.00
Total before tax $944.36
Tax $0.00
Amount due $944.36 USD
Pay by
Electronic funds transfer (EFT/ACH/Wire)
Account name Amazon Capital Services, Inc
Bank name Wells Fargo Bank
ACH routing # (ABA)121000248
Bank account # (DDA)41630410331335557
SWIFT code (wire transfer)WFBIUS6S
Include Amazon invoice number(s) in the descriptive field of your electronic
funds transfer payment, or
Email ar-businessinvoicing@amazon.com to submit your remittance detail.
Check
Amazon Capital Services
PO Box 035184
Seattle, WA 98124-5184
Payment due by October 30, 2025
Invoice details
Description Qty Unit price
Item subtotal
before tax Tax
1 MountRhino Kids Parachute,6ft Play Parachute with 9 Handles -
Multicolored Parachute for Kids,Play Parachute for Indoor Outdoor
Games Exercise Toy
ASIN:
B07W1X7N6S
Sold by: Xiamenmufengxiuxianyongpinyouxiangongsi
Order # 111-6069764-3776211
1 $14.24 $14.24 0.000%
Invoice #1YNH-H979-6YWR
Invoice
Page 2 of 3
Description Qty Unit price
Item subtotal
before tax Tax
2 Climbing Tunnel for Kids,Multicolor Play Tunnel Tent Toy for Baby
or Pet, Outdoor Indoor Climb and Crawl Through, Play Equipment
for Toddler 3-10, for Daycare, Preschool, Playground (4 Sections)
ASIN:
B0DQPSHX8R
Sold by: Amazon.com Services, Inc
Order # 111-2832038-4086665
1 $214.36 $214.36 0.000%
3 Little Tikes Rocking Horse Blue, 33.00 L x 10.00 W x 17.50 H
Inches
ASIN:
B003ICWTME
Sold by: Amazon.com Services, Inc
Order # 111-5178259-9000255
3 $34.99 $104.97 0.000%
4 Sratte 12 Pcs Toy Hoop for Kid Detachable Adjustable Toy Hoop
Colored Hoop Exercise Ring Plastic Circle for Kid Teen Gymnastics
Dog Agility Equipment, Require Self Assembly(Simple Colors, 24
Inch)
ASIN: B0C58PFP2Z
Sold by: HEFEI SHUNHENG WANGLUOKEJI
YOUXIANGONGSI
Order # 111-6069764-3776211
1 $36.99 $36.99 0.000%
5 Little Tikes Push and Ride Racer - (Amazon Exclusive), 22"L x
10"W x 17"H with screws
ASIN: B00005850H Sold by: Amazon.com Services, Inc
Order # 111-6069764-3776211
3 $38.90 $116.70 0.000%
6 Little Tikes Cozy Coupe 30th Anniversary Car
ASIN:
B001NQHN7S
Sold by: Amazon.com Services, Inc
Order # 111-2854049-0310629
3 $58.89 $176.67 0.000%
7 Step2 Push Around Buggy Kids Push Car, Ride On Toy, Stroller
Substitute, Includes Seat Belt & Horn, Made of Durable Plastic,
Max Weight 50 lbs., For Toddlers 1.5-4 Years Old, Red
ASIN: B004MWI0GI Sold by: Amazon.com Services, Inc
Order # 111-2854049-0310629
3 $64.99 $194.97 0.000%
8 Amazon Basics Junior BPA-Free 4-to-Score Giant Premium Plastic
Games Set, 4 in A Row for Kids and Adults with Carrying Bag,
Great For Gifting, Variety of Colors, Blue, Yellow, Red, Green,
Large
ASIN: B08J8BQN82 Sold by: Amazon.com Services, Inc
Order # 111-6069764-3776211
1 $85.46 $85.46 0.000%
Invoice #1YNH-H979-6YWR
Invoice
Page 3 of 3
Total before tax $944.36
Tax $0.00
Amount due $944.36
FAQs
How is tax calculated?
Visit https://www.amazon.com/gp/help/customer/display.html/ref=hp_leftv4_sib?ie=UTF8&nodeId=202036190
How are digital products and services taxed?
Visit https://www.amazon.com/gp/help/customer/display.html/ref=hp_leftv4_sib?ie=UTF8&nodeId=202074670
100 Federal Street,
Floor 13
Boston, MA 02110
Main: +1 617 330 8000
www.cplusa.com
May 19, 2026
Jayne Wellman
Town Manager
Town of Reading
16 Lowell St
Reading, MA 01867
Subject: J Warren Killam Elementary School: Modular Relocation – Playground Equipment
Invoice #1YNH-H979-6YWR
Dear Mr. Kraunelis,
Colliers Project Leaders, the Owner’s Project Manager, has reviewed the attached, Amazon
Business, invoice #YNH-H979-6YWR, and recommend payment of $879.37 for modular relocation
playground equipment for the J. Warren Killam Elementary School Project.
We recommend payment of this amount, using the following ProPay Codes and Breakdowns.
Invoice
Number
Task Request This
Period
ProPay
Code
1YNH-
H979-
6YWR
Modular Relocation – Playground
Equipment $879.37 0603-0000
Please feel free to contact me at (617) 860-2267 if you have any questions concerning this invoice.
Sincerely,
Justin Ferdenzi,
Project Manager
Justin.ferdenzi@collierseng.com
Attachment: Daily Times Chronicle Invoice #1YNH-H979-6YWR $879.37- ProPay Code: 0603-0000
Credit Memo
For customer support, visit www.amazon.com/contact-us.
Page 1 of 1
Credit Memo Date
Credit Memo #
Invoice Date
Invoice #
Account #
Order #
Payment Terms
Registered Business Name
Town Of Reading
Bill To
Town Of Reading
16 Lowell Street
Reading, MA 01867
Ship To
Kevin Gerstner
62 OAKLAND RD
READING, MA 01867-1613
Net 30
111-2854049-0310629
A1ZYRRWOB9HS9H
1YNH-H979-6YWR
30-Sep-2025
1FPV-DJ1C-HX67
31-Oct-2025
Credit Memo Summary
Item Subtotal ($64.99)
Shipping & Handling $0.00
Promos & Discounts $0.00
Sales Tax $0.00
Amount Due ($64.99)USD
Order Information
Kevin GerstnerOrdered By
PO #
Department Facilities
KG26000RISE
Kevin Gerstner
Applying this credit note
Email the credit memo numbers you want to use and the Amazon-provided
invoice numbers you want to pay to ar-businessinvoicing@amazon.com
Credit Memo Details
Description Qty
Unit
Price
Subtotal
before
Tax
Tax
Rate Subtotal
Step2 Push Around Buggy Kids Push Car, Ride On Toy, Stroller
Substitute, Includes Seat Belt & Horn, Made of Durable Plastic, Max
Weight 50 lbs., For Toddlers 1.5-4 Years Old, Red
ASIN: B004MWI0GI Sold by: Amazon.com Services, Inc
1 $64.99 ($64.99)0.000%($64.99)
Invoice #1YNH-H979-6YWR |September 30, 2025
Invoice
For customer support, visit www.amazon.com/contact-us.
Page 1 of 3
Account #
Payment terms
Purchase date
Purchased by
PO #
Department
Registered business name
Town Of Reading
Bill to
Town Of Reading
16 Lowell Street
Reading, MA 01867
Ship to
Kevin Gerstner
62 OAKLAND RD
READING, MA 01867-1613
Facilities
KG26000RISE
Kevin Gerstner
23-Sep-2025
Net 30
A1ZYRRWOB9HS9HInvoice summary
Item subtotal before tax $944.36
Shipping & handling $0.00
Promos & discounts $0.00
Total before tax $944.36
Tax $0.00
Amount due $944.36 USD
Pay by
Electronic funds transfer (EFT/ACH/Wire)
Account name Amazon Capital Services, Inc
Bank name Wells Fargo Bank
ACH routing # (ABA)121000248
Bank account # (DDA)41630410331335557
SWIFT code (wire transfer)WFBIUS6S
Include Amazon invoice number(s) in the descriptive field of your electronic
funds transfer payment, or
Email ar-businessinvoicing@amazon.com to submit your remittance detail.
Check
Amazon Capital Services
PO Box 035184
Seattle, WA 98124-5184
Payment due by October 30, 2025
Invoice details
Description Qty Unit price
Item subtotal
before tax Tax
1 MountRhino Kids Parachute,6ft Play Parachute with 9 Handles -
Multicolored Parachute for Kids,Play Parachute for Indoor Outdoor
Games Exercise Toy
ASIN:
B07W1X7N6S
Sold by: Xiamenmufengxiuxianyongpinyouxiangongsi
Order # 111-6069764-3776211
1 $14.24 $14.24 0.000%
Invoice #1YNH-H979-6YWR
Invoice
Page 2 of 3
Description Qty Unit price
Item subtotal
before tax Tax
2 Climbing Tunnel for Kids,Multicolor Play Tunnel Tent Toy for Baby
or Pet, Outdoor Indoor Climb and Crawl Through, Play Equipment
for Toddler 3-10, for Daycare, Preschool, Playground (4 Sections)
ASIN:
B0DQPSHX8R
Sold by: Amazon.com Services, Inc
Order # 111-2832038-4086665
1 $214.36 $214.36 0.000%
3 Little Tikes Rocking Horse Blue, 33.00 L x 10.00 W x 17.50 H
Inches
ASIN:
B003ICWTME
Sold by: Amazon.com Services, Inc
Order # 111-5178259-9000255
3 $34.99 $104.97 0.000%
4 Sratte 12 Pcs Toy Hoop for Kid Detachable Adjustable Toy Hoop
Colored Hoop Exercise Ring Plastic Circle for Kid Teen Gymnastics
Dog Agility Equipment, Require Self Assembly(Simple Colors, 24
Inch)
ASIN: B0C58PFP2Z
Sold by: HEFEI SHUNHENG WANGLUOKEJI
YOUXIANGONGSI
Order # 111-6069764-3776211
1 $36.99 $36.99 0.000%
5 Little Tikes Push and Ride Racer - (Amazon Exclusive), 22"L x
10"W x 17"H with screws
ASIN: B00005850H Sold by: Amazon.com Services, Inc
Order # 111-6069764-3776211
3 $38.90 $116.70 0.000%
6 Little Tikes Cozy Coupe 30th Anniversary Car
ASIN:
B001NQHN7S
Sold by: Amazon.com Services, Inc
Order # 111-2854049-0310629
3 $58.89 $176.67 0.000%
7 Step2 Push Around Buggy Kids Push Car, Ride On Toy, Stroller
Substitute, Includes Seat Belt & Horn, Made of Durable Plastic,
Max Weight 50 lbs., For Toddlers 1.5-4 Years Old, Red
ASIN: B004MWI0GI Sold by: Amazon.com Services, Inc
Order # 111-2854049-0310629
3 $64.99 $194.97 0.000%
8 Amazon Basics Junior BPA-Free 4-to-Score Giant Premium Plastic
Games Set, 4 in A Row for Kids and Adults with Carrying Bag,
Great For Gifting, Variety of Colors, Blue, Yellow, Red, Green,
Large
ASIN: B08J8BQN82 Sold by: Amazon.com Services, Inc
Order # 111-6069764-3776211
1 $85.46 $85.46 0.000%
Invoice #1YNH-H979-6YWR
Invoice
Page 3 of 3
Total before tax $944.36
Tax $0.00
Amount due $944.36
FAQs
How is tax calculated?
Visit https://www.amazon.com/gp/help/customer/display.html/ref=hp_leftv4_sib?ie=UTF8&nodeId=202036190
How are digital products and services taxed?
Visit https://www.amazon.com/gp/help/customer/display.html/ref=hp_leftv4_sib?ie=UTF8&nodeId=202074670
100 Federal Street,
Floor 13
Boston, MA 02110
Main: +1 617 330 8000
www.cplusa.com
May 18, 2026
Jayne Wellman
Town Manager
Town of Reading
16 Lowell St
Reading, MA 01867
Subject: J Warren Killam Elementary School - Publishing Services
Invoice #260488
Dear Mr. Kraunelis,
Colliers Project Leaders, the Owner’s Project Manager, has reviewed the attached, Daily Times
Chronicle, invoice #260488, and recommend payment of $511.71 for publishing services for the J.
Warren Killam Elementary School Project.
We recommend payment of this amount, using the following ProPay Codes and Breakdowns.
Invoice
Number
Task Request This
Period
ProPay
Code
260488 Publishing Services – Town of Reading:
FSB and GC Re-Bid Notice $511.71 0103-0000
Please feel free to contact me at (617) 860-2267 if you have any questions concerning this invoice.
Sincerely,
Justin Ferdenzi,
Project Manager
Justin.ferdenzi@collierseng.com
Attachment: Daily Times Chronicle Invoice #260488 $511.71 - ProPay Code: 0103-0000
Daily Times Chronicle
Reading -- Wakefield
Woburn Daily Times, Inc., PO Box 2433, Woburn MA 01888
781-933-3700
INVOICE
Town of ReadingBill To
Joshua Delaune, MPAAttn:
16 Lowell StreetAddress 1
Address 2
ReadingCity MAState 01867ZIP
PO#
260488Legal Ad#
260488 Reading IFB KS-26-08 Killam School ConstructionBilling Key
16.8# of Inches 1# of Runs
5/20/2026Run 1 Run 2 Run 3
$511.71Cost Notary Fee $511.71Total Cost
Payment Date Payment $511.71Balance Due
100 Federal Street,
Floor 33
Boston, MA 02110
Main: +1 617 330 8000
www.cplusa.com
May 18, 2026
Jayne Wellman
Town Manager
Town of Reading
16 Lowell St
Reading, MA 01867
Subject: J. Warren Killam Elementary School – Daily Times Chronicle: Advertising Services
Dear Ms. Wellman:
Colliers Project Leaders, the Owner’s Project Manager, has reviewed the attached, invoice
#260488 is subject to approval of the corresponding Commitment recommend payment of $511.71
for GC and FSB re-bid ad posting service for the J. Warren Killam Elementary School Project.
Subject to approval of the corresponding Commitment, we recommend payment of this
amount, using the following ProPay Codes and Breakdowns.
Task Request
This Period
ProPay
Code
Advertising Services – GC and FSB Re-Bid Posting $511.71 0103-0000
Please feel free to contact me at (774) 294-6659 if you have any questions concerning this invoice.
Sincerely,
Justin Ferdenzi,
Project Manager
Justin.ferdenzi@collierseng.com
Daily Times Chronicle
Reading -- Wakefield
Woburn Daily Times, Inc., PO Box 2433, Woburn MA 01888
781-933-3700
INVOICE
Town of ReadingBill To
Joshua Delaune, MPAAttn:
16 Lowell StreetAddress 1
Address 2
ReadingCity MAState 01867ZIP
PO#
260488Legal Ad#
260488 Reading IFB KS-26-08 Killam School ConstructionBilling Key
16.8# of Inches 1# of Runs
5/20/2026Run 1 Run 2 Run 3
$511.71Cost Notary Fee $511.71Total Cost
Payment Date Payment $511.71Balance Due
IDTask ModeTask NameDuration Start Finish Predecessors1Forming the Team (MSBA MOD 02)187 daysThu 4/13/23Tue 12/12/232OPM Selection86.5 daysThu 4/13/23Thu 8/3/2310Design Team Selection99.25 daysMon 8/7/23Tue 12/12/2328Feasibility (MSBA MOD 03)244 daysMon 12/18/23Wed 10/30/2429Preliminary Design Program Initiative (PDP)179 daysMon 12/18/23Wed 8/7/2430Existing Conditions Assessment42 daysTue 1/2/24Mon 2/26/2427FS+15 days31Design Process117 daysTue 1/2/24Fri 5/31/2427FS+15 days32Meetings - Community, SBC, User Groups110 daysMon 12/18/23Thu 5/9/2442Cost Estimating - Preliminary Alternatives15 daysThu 4/11/24Wed 5/1/2439FS+3 days,3043Preliminary Design Program Submission (PDP)0 daysMon 5/20/24Mon 5/20/2441FS+8 days,3044MSBA PDP Review30 daysTue 5/21/24Mon 7/1/2443FS+1 day45District Response to MSBA PDP Review Comments20 daysMon 7/1/24Thu 7/25/244446MSBA Acceptance of PDP10 daysFri 7/26/24Wed 8/7/2445,3147Preferred Schematic Report (PSR)125 daysTue 5/21/24Wed 10/30/2448Design Process (PSR)57.88 daysTue 5/21/24Mon 8/5/2443FS+1 day49Meetings - Community, SBC, User Groups43 daysMon 6/17/24Mon 8/12/2455Preferred Schematic Report Submission (PSR)0 daysWed 8/21/24Wed 8/21/2454FS+8 days,4656MSBA Facilities Assessment Subcommittee (FAS)0 daysWed 9/11/24Wed 9/11/2455FS+15 days57MSBA Facilities Assessment Subcommittee (FAS)0 daysWed 9/25/24Wed 9/25/2455FS+27 days58District Response to FAS Comments10 daysWed 9/25/24Tue 10/8/245759MSBA PSR Review32 daysThu 8/22/24Wed 10/2/2455FS+1 day60District Response to MSBA PSR Review Comments9 daysThu 10/3/24Tue 10/15/245961MSBA Conference Call to Review PSR0 daysWed 10/16/24Wed 10/16/2460FS+1 day62MSBA Board Approval of Preferred Solution0 daysWed 10/30/24Wed 10/30/2457,58,59,60,61FS+11 days63Schematic Design (MSBA MOD 04)219 daysWed 10/16/24Wed 7/30/2564Schematic Design28 daysWed 10/30/24Fri 12/6/246265Meetings - SBC73 daysWed 10/16/24Wed 1/22/2571SD Cost Estimates20 daysMon 12/9/24Mon 1/6/2564FS+1 day72Establish Project Scope & Budget10 daysWed 1/15/25Wed 1/29/2571,69,70FF73Establish CM@R or ch1490.88 daysMon 12/16/24Mon 12/16/2471,69,70FF74OPM Informational email to MSBA0.88 daysFri 1/31/25Fri 1/31/2572FS+5 days,7075DESE Submittal152 daysWed 10/30/24Fri 5/16/2576Prepare DESE Submittal77 daysWed 10/30/24Tue 2/11/256277MSBA Review of DESE Submittal36 daysTue 2/11/25Fri 3/28/257678DESE Review & Approve39 daysFri 3/28/25Fri 5/16/257779Schematic Design Report Submission0 daysMon 2/10/25Mon 2/10/2574FS+6 days,7380MSBA SD Review36.88 daysTue 2/11/25Fri 3/28/2579FS+1 day81District Response to MSBA SD Review Comments11 daysMon 3/31/25Fri 4/11/258082Project Scope and Budget Conference0 daysWed 3/26/25Wed 3/26/258183MSBA Board Approval Schematic Design13 daysFri 4/11/25Wed 4/30/2581,828450% DCAMM Designer Evaluation Submission10 daysThu 7/17/25Wed 7/30/2511585Extended Design Prior to the Start of DD46 daysMon 3/10/25Tue 5/13/2586Extendend Design46 daysMon 3/10/25Tue 5/13/257987Owner release into DD0 daysTue 5/13/25Tue 5/13/258688Funding the Project (MSBA MOD 05)96.75 daysWed 1/8/25Tue 5/13/2589Reading Funding Process96.75 daysWed 1/8/25Tue 5/13/2590Develop Meeting & Vote Language26.88 daysWed 1/8/25Thu 2/13/2591Secure MSBA Vote & Specical Town Meeting Language18 daysWed 1/8/25Fri 1/31/257192Finalize Language with Town Council & MSBA0 daysFri 1/31/25Fri 1/31/259193Submit Language to Matt to Write Article11 daysFri 1/31/25Thu 2/13/259294Submit Language to Laura (Min 35 days before election)0 daysFri 1/31/25Fri 1/31/25925/208/219/119/2510/1610/302/103/265/131/311/31AMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJHalf 1, 2023Half 2, 2023Half 1, 2024Half 2, 2024Half 1, 2025Half 2, 2025Half 1, 2026Half 2, 2026Half 1, 2027Half 2, 2027Half 1, 2028Half 2, 2028Half 1, 2029TaskMilestoneSummaryKilliam Elementary School Page 1Project: 2023 09-18 Reading KiDate: Tue 5/19/26
IDTask ModeTask NameDuration Start Finish Predecessors95Special Town Meeting61.25 daysThu 2/13/25Mon 5/12/2596Information to Select Board for Special Town Meeting0 daysThu 2/13/25Thu 2/13/2594,9397Select Board Meeting - Vote to Close Warrant for Special Town Meeting2 daysFri 2/14/25Tue 2/18/259698Select Board Meeting - Vote for Special Town Meeting (14 days before Town Meeting and no meeting on 04/08/25 or 04/15/25)0 daysTue 4/1/25Tue 4/1/259799Special Town Meeting Warrant Published14 daysTue 4/1/25Thu 4/17/2598,97100Special Town Meeting Warrant Report Published0 daysThu 4/17/25Thu 4/17/2599101Special Town Meeting (05/01-05/05)2 daysThu 5/1/25Mon 5/5/2598FS+10 days,99FS+10 days,100102Post Warrant for Election 1 dayMon 5/5/25Tue 5/6/25101103Waiting Period after Special Town Meeting 5 daysMon 5/5/25Mon 5/12/25101104Town Meeting32.13 daysTue 3/25/25Thu 5/8/25105Town Meeting Warrant Published0 daysTue 3/25/25Tue 3/25/25106Town Meeting Warrant Report Published0 daysFri 4/4/25Fri 4/4/25105FS+9 days107Town Meeting (04/28, 05/01, 05/05 & 05/08)10 daysMon 4/28/25Thu 5/8/25105FS+25 days,106FS+16 days108Popular Election34.5 daysTue 3/25/25Tue 5/13/25109Information to Select Board for Elections0 daysTue 3/25/25Tue 3/25/2593FS+30 days110Select Board Meeting - Vote for Election to happen (35 days before election andno meeting on 04/08 or 04/15)0 daysTue 4/1/25Tue 4/1/25109FS+6 days111Select Board must notify the Town Clerk of Election1 dayWed 4/2/25Wed 4/2/25110112Vote (Special Elecation - Has to be 7 days after closing and Historically on a Tuesday)0 daysTue 5/13/25Tue 5/13/25103,110FS+25 days,111113Design Development (MODULE 6)262.25 daysFri 5/23/25Fri 5/1/26114Design Development (DD)89.38 daysFri 5/23/25Wed 9/17/25115Design Development Drawings41 daysFri 5/23/25Thu 7/17/25112,87116MHC - Project Notification Form Filing0 daysTue 7/22/25Tue 7/22/25115FS+3 days117Register Project with USBGC0 daysThu 6/12/25Thu 6/12/25115SS+15 days118DD Cost Estimating15 daysThu 7/17/25Tue 8/5/25115119DD Estimate Reconciliation Meeting2 daysWed 8/6/25Thu 8/7/25118120Finalize VE log and Reconciled Budget2 daysThu 8/7/25Mon 8/11/25119121Review Budget with XLT0 daysMon 8/11/25Mon 8/11/25120122Issue SBC Documents4 daysMon 8/11/25Fri 8/15/25121123SBC Meeting1 dayFri 8/15/25Mon 8/18/25119FS+6 days,122124SBC Meeting - Approve DD Submission0 daysMon 8/18/25Mon 8/18/25123125Submit DD Pacakge to MSBA0 daysTue 8/19/25Tue 8/19/25124FS+1 day,117126Site Plan Review and Stormwater Permit Special Hearing0 daysMon 8/25/25Mon 8/25/25124FS+5 days127Site Plan Review and Stormwater Permit Approval8 daysMon 8/25/25Wed 9/3/25126128MSBA Review and Comments (Business Days)13 daysTue 8/19/25Thu 9/4/25125129Respond to MSBA DD comments (Business Days)10 daysThu 9/4/25Wed 9/17/2512813060% Construction Documents Phase (60% CD)93 daysTue 8/19/25Thu 12/18/2513160% Construction Drawings40 daysTue 8/19/25Thu 10/9/25125132SBC Meeting0 daysThu 10/9/25Thu 10/9/2513113360% CDs for Pricing0 daysThu 10/9/25Thu 10/9/2513213460% CD Cost Estimating15 daysThu 10/9/25Wed 10/29/2513313560% CD Reconciliation Meeting0 daysMon 11/3/25Mon 11/3/25134FS+3 days136Finalize VE log and Reconciled Budget2 daysMon 11/3/25Tue 11/4/25135137Review Budget with XLT0 daysWed 11/5/25Wed 11/5/25136FS+1 day138Issue SBC Documents1 dayThu 11/6/25Thu 11/6/25137139SBC Meeting - Approve 60% Submission0 daysWed 11/12/25Wed 11/12/25135FS+7 days,138FS+2 days140Submit 60% CD Package to MSBA0 daysThu 11/13/25Thu 11/13/25139FS+1 day,129141MSBA Review and Comments (Business Days)16 daysThu 11/13/25Thu 12/4/25140142Respond to MSBA 60% comments (Business Days)11 daysThu 12/4/25Thu 12/18/2514114390% Construction Documents Phase (90% CD)130.5 daysWed 11/12/25Fri 5/1/262/134/14/173/254/43/254/15/137/226/128/118/188/198/2510/910/911/311/511/1211/13AMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJHalf 1, 2023Half 2, 2023Half 1, 2024Half 2, 2024Half 1, 2025Half 2, 2025Half 1, 2026Half 2, 2026Half 1, 2027Half 2, 2027Half 1, 2028Half 2, 2028Half 1, 2029TaskMilestoneSummaryKilliam Elementary School Page 2Project: 2023 09-18 Reading KiDate: Tue 5/19/26
IDTask ModeTask NameDuration Start Finish Predecessors14490% Construction Documents49 daysWed 11/12/25Thu 1/15/2613914590% CDs Issued for Cost Estimating0 daysThu 1/15/26Thu 1/15/26142,14414690% CDs Issued for Code Review0 daysThu 1/15/26Thu 1/15/2614414790% CD Cost Estimating10 daysThu 1/15/26Thu 1/29/2614514890% CD Reconciliation Meeting0 daysMon 2/2/26Mon 2/2/26147FS+2 days149Finalize VE log and Reconciled Budget2 daysMon 2/2/26Wed 2/4/26148150Review Budget with XLT0 daysWed 2/4/26Wed 2/4/26149151Issue SBC Documents1 dayWed 2/4/26Thu 2/5/26150152SBC Meeting - Approve 90% CD Submission0 daysMon 2/9/26Mon 2/9/26151FS+2 days153Submit 90% CD Package to MSBA0 daysTue 2/10/26Tue 2/10/26152FS+1 day154MSBA review of 90% Package (Business Days)16 daysTue 2/10/26Tue 3/3/26153155District Team's Response to MSBA Review of 90% package (Business Days)11 daysTue 3/3/26Tue 3/17/26154156Completion of the Bid Documents10 daysWed 3/18/26Mon 3/30/26155157Issue SBC Documents0 daysThu 3/26/26Thu 3/26/26156FS-3 days158SBC Meeting - Approve Bid Document Submission0 daysMon 3/30/26Mon 3/30/26156159100% CD Package MSBA Submission1 dayTue 3/31/26Tue 3/31/26158160100% CD Package to MSBA review14 daysWed 4/1/26Fri 4/17/26159161100% CD DCAMM Designer Evaluation10 daysFri 4/17/26Fri 5/1/26160162Construction Phase (MODULE 7)860.88 daysWed 11/12/25Thu 11/30/28163Early Package #01 Switchgear384.38 daysWed 11/12/25Tue 5/4/27164Bid Package for Switchgear & Generator56 daysWed 11/12/25Tue 1/27/26165Completion of the Early Bid documents21 daysWed 11/12/25Tue 12/9/25144SS166Submit Advertisement for Early Bids1 dayWed 12/10/25Wed 12/10/25165167SBC Meeting - Approve Early Package-Invitation For Bid0 daysMon 12/15/25Mon 12/15/25166FS+3 days168Advertise for Early bid package1 dayMon 12/15/25Tue 12/16/25167169Early Bid Package Submission Period21 daysTue 12/16/25Wed 1/14/26168170Early Package Bids Due0 daysWed 1/14/26Wed 1/14/26169171SBC Meeting - Review results/ Vote to Award0 daysTue 1/20/26Tue 1/20/26170FS+4 days172Issue Notice of Award5 daysTue 1/20/26Tue 1/27/26171173Construction for Switchgear330.63 daysTue 1/27/26Tue 5/4/27174Execute Contract45 daysTue 1/27/26Mon 3/30/26172175Shop Drawings7 daysTue 3/31/26Wed 4/8/26174176Fabriation and Delivery300 daysThu 4/9/26Tue 5/4/27175177GC To take Delivery of Switchgear0 daysTue 5/4/27Tue 5/4/27176178Base Contract136.38 daysMon 12/15/25Tue 6/23/26179Prequalification Base Contract81.25 daysMon 12/15/25Tue 3/31/26180SBC Meeting - Approve Prequal Sub Committee (PQC)0 daysMon 12/15/25Mon 12/15/25144SS+25 days181PQC - Kick-Off7 daysMon 1/26/26Tue 2/3/26180182PQC - Approve RFQ0 daysTue 2/3/26Tue 2/3/26181183PQC - Submit Ad for Qualifications6 daysWed 1/28/26Wed 2/4/26182184PQC - Advertise for Qualifications (GCs/FSB) online0 daysWed 2/4/26Wed 2/4/26183185PQC - Qualifications Submission Period18 daysWed 2/4/26Fri 2/27/26184186Qualifications Due0 daysFri 2/27/26Fri 2/27/26185187PQC - Distribute & Review SOQs2 daysFri 2/27/26Tue 3/3/26186188PQC - Review PreQuals21 daysTue 3/3/26Fri 3/27/26187189PQC - Complete SOQ Review and Approve List of Contractors2 daysMon 3/30/26Tue 3/31/26188190Bidding Base Contract65 daysTue 3/31/26Tue 6/23/26191Advertise for bids (Central Reg, New Paper, City Hall)5 daysTue 3/31/26Tue 4/7/26189,158192Issue Bid Docs to Project Dog for Clerical Review 0 daysTue 3/31/26Tue 3/31/26159SS193Bid Documents Published Online6 daysTue 3/31/26Tue 4/7/26192194 Contractor Pre-Bid Briefing Session/Conference0 daysTue 4/7/26Tue 4/7/261931/151/152/22/42/92/103/263/3012/151/141/205/412/152/32/42/273/314/7AMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJHalf 1, 2023Half 2, 2023Half 1, 2024Half 2, 2024Half 1, 2025Half 2, 2025Half 1, 2026Half 2, 2026Half 1, 2027Half 2, 2027Half 1, 2028Half 2, 2028Half 1, 2029TaskMilestoneSummaryKilliam Elementary School Page 3Project: 2023 09-18 Reading KiDate: Tue 5/19/26
IDTask ModeTask NameDuration Start Finish Predecessors195Advertise for Re-bids (Central Reg, New Paper, City Hall)5 daysThu 5/14/26Wed 5/20/26194FS+29 days196Bid Documents Published Online for Re-bid6 daysTue 5/12/26Wed 5/20/26195FF197Filed Sub-Bid time11 daysWed 5/20/26Thu 6/4/26196198 Filed Sub-Bids Due0 daysThu 6/4/26Thu 6/4/26197,194199GC Bid Time17 daysWed 5/20/26Thu 6/11/26196200 General Contractor Bids Due0 daysThu 6/11/26Thu 6/11/26199,194,198201Review Results of GC Bids with SBC2 daysThu 6/11/26Mon 6/15/26200202Vote to Approve GC Bid0 daysMon 6/15/26Mon 6/15/26201203Issue Notice of Award1 dayMon 6/15/26Tue 6/16/26202204Execute Contract5 daysTue 6/16/26Tue 6/23/26203,161205Phase 1 - New Building Construction475.38 daysTue 6/23/26Mon 2/28/28206Notice to Proceed1 dayTue 6/23/26Wed 6/24/26203,204207Construction438 daysTue 6/23/26Mon 1/10/28204208EPA - NPDES Notice of Intent and Approval65 daysWed 6/24/26Tue 9/15/26206209Substantial Completion of New School Building0 daysMon 1/10/28Mon 1/10/28207210Receive Temporary Certificate of Occupancy (TCO)0 daysMon 1/10/28Mon 1/10/28209211Student/Staff Tours of New Building10 daysMon 1/10/28Mon 1/24/28210212Move from Existing Building to New36 daysMon 1/10/28Fri 2/25/28209213Occupy5 daysSun 2/20/28Mon 2/28/28207,21221450% DCAMM Rating (Contractor)10 daysMon 1/10/28Mon 1/24/28207215Phase 2 - Demo and Site210 daysFri 3/3/28Thu 11/30/28213FS+5 days216Construction200 daysFri 3/3/28Thu 11/16/28213,210,209217Substantial conpletion0 daysThu 11/16/28Thu 11/16/28216218100% DCAMM Rating (Contractor)10 daysThu 11/16/28Thu 11/30/28226219Project Closeout (MODULE 8)384.38 daysMon 1/10/28Tue 5/15/29207220Punchlist262.38 daysMon 1/10/28Wed 12/13/28221Contractor Punch List for Designer14 daysMon 1/10/28Thu 1/27/28207FF222Design Team Punch List1.5 monsMon 1/10/28Wed 2/16/28207FF223Punch List - Phase 1 Contractor to Perform Punch33 daysThu 1/27/28Thu 3/9/28221224FF&E Punchlist15 daysMon 1/10/28Fri 1/28/28211FF225FF&E Closeout20 daysThu 11/16/28Wed 12/13/28216226Punch List - Phase 233 daysThu 10/5/28Thu 11/16/28216FF227Cx257.38 daysMon 1/10/28Wed 12/6/28228Commissioning New Building4 monsMon 1/10/28Fri 4/21/28208FF229Commissioning + 10 month 11 monsMon 1/10/28Thu 10/19/28210230Final Commissioning Report to MSBA10 daysThu 11/16/28Thu 11/30/28226,229231Commissioning Certificate of Completion to MSBA5 daysThu 11/30/28Wed 12/6/28229,230232USGBC76 daysFri 2/9/29Tue 5/15/29233Final Construction Package to USGBC66 daysFri 2/9/29Wed 5/2/29225,226,236234LEED-S Construction Application & Final Review10 daysThu 5/3/29Tue 5/15/29233235USGBC issue Green School Program Certification letter0 daysTue 5/15/29Tue 5/15/29234236Closeout GC - Final Change Order66 daysThu 11/16/28Fri 2/9/29226,217237GC Request for Final Payment15 daysFri 2/9/29Wed 2/28/29236238Submission of As-Builts and O&M44 daysThu 11/16/28Fri 1/12/29226,216239DCAMM Evaluation Form following GC Final Payment10 daysWed 2/28/29Tue 3/13/29237240Final Reimbursement Request Submittal to MSBA3.4 monsTue 5/15/29Wed 8/8/29235,229,238241Corrective actions by GC22 daysTue 3/13/29Tue 4/10/29239242MSBA Closeout33 daysTue 5/15/29Tue 6/26/29234,229,231243Project Complete0 daysWed 8/8/29Wed 8/8/29240,2426/46/116/151/101/1011/165/15AMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJHalf 1, 2023Half 2, 2023Half 1, 2024Half 2, 2024Half 1, 2025Half 2, 2025Half 1, 2026Half 2, 2026Half 1, 2027Half 2, 2027Half 1, 2028Half 2, 2028Half 1, 2029TaskMilestoneSummaryKilliam Elementary School Page 4Project: 2023 09-18 Reading KiDate: Tue 5/19/26
Town of Reading
Meeting Minutes
Page | 1
2016-09-22 LAG Board - Committee - Commission - Council:
Permanent Building Committee Killam School Building Committee
Date: 2026-04-22 Time: 7:00 PM
Building: Reading Town Hall Location: Conference Room
Address: 16 Lowell Street Session: Open Session
Purpose: General Business Version: Draft
Attendees: Members - Present:
Pat Tompkins, John Coote, Chris Haley, Ed Ross, Greg Stepler, Nancy
Twomey, and Carla Nazzaro.
Members - Not Present:
Shawn Brandt and Kirk McCormick.
Others Present:
Reading Town Manager Jayne Wellman, Reading Fecilities Clerk David
Dallaire, Colliers Project Director Mike Carroll, Colliers Project Manager Justin
Ferdenzi, LBA Project Manager Jenni Katajamaki, LBA Architect David Harris
Minutes Respectfully Submitted By: Harani Kumaresh
Topics of Discussion:
This meeting was held in-person in the Town Hall Conference Meeting Room and remotely
via Zoom.
Call to order:
Chair Carla Nazzaro called the meeting to order at 7:00 pm.
Roll call attendance: Pat Tompkins, John Coote, Chris Haley, Ed Ross, Greg Stepler, Nancy
Twomey, and Carla Nazzaro
Public Comment:
No reports.
Liaison Reports:
Sawtelle House / Noise Mitigation:
Jayne Wellman provided an update on the Sawtelle tell House noise mitigation plan. Mike
Carroll reported that the project team and the Sawtelle House have reached agreement on
noise mitigation measures. The plan includes a temporary wood fence on the property line,
a public walkway between the construction zone and the Sawtelle House, and a construction
fence with scrim to provide visual screening and dust mitigation. The wood fence is over and
above what would typically be required of the contractor. Additionally, all construction
equipment will be required to have mufflers and comply with sound requirements. Standard
work hours are 7:00 AM to 3:30 PM on weekdays and reduced hours on Saturdays,
consistent with town ordinances. Any work outside of standard hours, including nights,
weekends, or Sundays, requires prior written authorization from the Town Manager and
coordination with the Police Department. The project team ant icipates two or three nights of
Page | 2
extended work, primarily for concrete slab finishing operations. The Sawtelle House was
invited to the abutters meeting but did not attend or respond.
Abutters Meeting:
Mike Carroll reported that the project team held an abutters meeting the previous Thursday.
Approximately 20 to 25 people were invited, including immediate abutters and abutters of
abutters. Approximately half attended, and the meeting was well received with no
significant pushback. The project team had one-on-one conversations with abutters to
provide updated information. LBA brought drawings showing property lines and project
boundaries for attendees to take home. Mike Carroll will send a follow -up email to attendees
with contact information for the owner’s project manager as the first point of contact for
construction-related concerns. The abutters meeting presentation will be posted to the
project website, and Justin Ferdenzi’s contact information will be added to the website
contact page by Friday. During construction, the site representative’s contact information
will replace Justin’s.
Committee members raised several additional items during liaison reports:
• Plante Moran Tax Consultant: Carla Nazzaro reported attending a Plante Moran
seminar regarding potential reimbursements under the Inflation Reduction Act. A
contract has been sent to Plante Moran, who responded with two proposed changes
currently under review by legal counsel.
• RMLD Letter: The committee received a letter from Reading Municipal Lig ht
Department (RMLD) regarding an increase in their reimbursement with requirements
related to Renewable Energy Certificates (RECs). A meeting will be scheduled to
review the requirements.
• New Superintendent: Dr. Henry Turner will begin as the new superin tendent on July
1st. A meeting has been scheduled at Killam School to provide him with a project
update.
• Federal Road Safety Grants: Mike Carroll noted a potential federal grant opportunity
for road safety improvements. The project team will coordinate wi th the town
engineer to evaluate eligibility, as the project already includes road safety
improvements along the school corridor based on a prior traffic study.
Builder’s Risk Policy*
Jayne Wellman presented a recommendation for the Town of Reading to ow n the builder’s
risk insurance policy for the project. Connor Powers of Maya Insurance joined the meeting
to answer questions. The premium quote is $140,000 to $145,000 for the entire project
period, which is comparable to the cost if carried by the general contractor.
The policy includes $25,000 deductibles for all perils, including water, lightning, theft, hail,
windstorm, and named windstorm, with coverage up to the full construction hard cost limit
of approximately $100 million. Flood and earthquake coverage carries a $25,000 deductible
with a $25 million coverage limit for each, which is consistent with industry standards.
Several other Massachusetts municipalities carry owner-controlled builder’s risk policies,
including Hopkinton, Woburn, Boxford, Tewksbury, Billerica, Maynard, Stoughton, Medway,
and Lexington
Jayne outlined the benefits of owner-controlled builder’s risk coverage: the Town controls
the cost, claims, and timing of the policy; coverage extends through the entire project until
the building comes onto the Town’s schedule of locations, eliminating potential gaps
between substantial completion and certificate of occupancy; the policy includes protection
for delays and soft costs; and the Town avoids hidden markups with direct pricing
negotiated with Maya Insurance.
John Coote asked about the difference between the flood and earthquake coverage limit
($25 million) and the full project limit. Connor Powers explained that this is standard
industry practice, with flood and earthquake coverag e typically set at approximately one
Page | 3
quarter of the construction cost. He noted that catastrophic flood or earthquake events
typically also trigger FEMA or MEMA assistance.
On a motion by Nancy Twomey, seconded by Ed Ross, the Killam School Building
Committee voted 7-0-0 to approve the Town of Reading owning the builder’s risk
policy for the J. Warren Killam Elementary School Project.
Roll call vote: Pat Tompkins – Yes; John Coote – Yes; Chris Haley – Yes; Ed Ross – Yes;
Greg Stepler – Yes; Nancy Twomey – Yes; Carla Nazzaro – Yes.
Updated Pre-Qualified Vendors List*
Justin Ferdenzi reported that a bid protest was received after the original pre -qualified
contractor and subcontractor list was approved. The protesting party claimed they were
unfairly disqualified. Town counsel reviewed the matter and determined that disqualification
for administrative paperwork issues, specifically failure to acknowledge addenda issued
during the pre-qualification process, was not sufficient grounds for disqualification.
The pre-qualification committee’s original decision to disqualify was consistent and applied
fairly across all applicants. However, town counsel advised that the addenda in question
were administrative in nature and did not materially affect the scoring criteria. All affected
vendors had scored above the 70-point minimum threshold, with some scoring in the 90s.
Legal counsel recommended adding approximately 15 additional subcontractors and
contractors to the pre-qualified list.
Mike Carroll noted that the OPM had already issued an addendum including the revised list
to maintain the bid schedule, subject to committee approval. Justin Ferdenzi and David
concurred that the additional contractors are well -qualified and would benefit the project by
expanding the competitive pool.
On a motion by Nancy Twomey, seconded by Ed Ross, the Killam School Building
Committee voted 7-0-0 to accept the revised pre-qualified contractor and
subcontractor bid list for the J. Warren Killam Elementary School Project.
Roll call vote: Pat Tompkins – Yes; John Coote – Yes; Chris Haley – Yes; Ed Ross – Yes;
Greg Stepler – Yes; Nancy Twomey – Yes; Carla Nazzaro – Yes.
Property Perimeter Fence Discussion
Carla Nazzaro raised the topic of the permanent perimeter fence planned f or the project
site. The fence, as currently specified, is an all -wood fence composed of northern white
cedar with oil-based stain (two coats).
Mike Carroll noted that the wood fence is specified on the two sides of the site facing
neighboring properties, not the street-facing sides. The Haverhill Street side has a cable
guardrail and decorative fence, and the Charles Street side is mostly open with a seat wall,
trees, and shrubbery. He recommended keeping the current fence specification for bidding
purposes, with the option to adjust later if needed. The first permanent fencing would not
be installed for approximately 18 months.
David from LBA reported that northern white cedar has a typical lifespan of 15 to 20 years
untreated and 20 to 40 years with oil or stain treatment. The fence is designed as a high -
quality commercial-grade installation. The design team had also evaluated composite wood
as an alternative but noted it carries a significant cost premium. The posts are set into
concrete footings with stainless steel sleeves to prevent ground contact and rot.
John Coote raised a question about graffiti resistance of the treated wood surface. The
committee discussed that the oil-based stain provides good protection, and composite
Page | 4
material could be considered if graffiti resistance becomes a priority. No vote was required
on this item.
CPL Financial Review*
Justin Ferdenzi presented the financial status of the project. The construction budget
remains at $101,521,394, which will be updated once trade bi ds and general contractor bids
are received and approved. Administrative costs expended to date total $2,450,061, with a
remaining balance of $6,117,979. The total project budget, including technology, furniture,
fixtures, and equipment, stands at approximately $130,011,783.
Justin Ferdenzi and Mike Carroll explained corrections to the budget revision request (BRR)
process with the MSBA. During the transition from feasibility to the Project Funding
Agreement (PFA), a second BRR submitted during feasibility was never processed by the
MSBA. The project team has corrected the initial budget values to align with the MSBA’s
records. The current budget figures remain unchanged; only the initial budget baseline
values were adjusted. The project team is preparing BRR #1 for the main project phase,
which will be submitted for formal committee approval at the next meeting.
Mike Carroll explained the MSBA’s BRR process for the benefit of the committee. Soft cost
BRRs can be submitted as needed, but the MSBA now requires a single hard cost BRR at the
end of construction. Change orders are submitted to the MSBA monthly and reviewed
quarterly, but are not formally entered into the MSBA’s accounting system until construction
closeout. The Town pays the contractor for approved change orders as work is completed,
and the MSBA reimburses the Town’s eligible portion at the end of the project.
On a motion by Nancy Twomey, seconded by Ed Ross, the Killam School Building
Committee voted 7-0-0 to approve a commitment to Daily Times Chronicle in the
amount of $313.14 for advertisement for the J. Warren Killam Elementary School
Project.
Roll call vote: Pat Tompkins – Yes; John Coote – Yes; Chris Haley – Yes; Ed Ross – Yes;
Greg Stepler – Yes; Nancy Twomey – Yes; Carla Nazzaro – Yes.
On a motion by Nancy Twomey, seconded by Ed Ross, the Killam School Building
Committee voted 7-0-0 to accept LBA Amendment 22, a credit of $9,174.00,
correcting a geotech scope double-count from Amendment 16 for the J. Warren
Killam Elementary School Project.
Roll call vote: Pat Tompkins – Yes; John Coote – Yes; Chris Haley – Yes; Ed Ross – Yes;
Greg Stepler – Yes; Nancy Twomey – Yes; Carla Nazzaro – Yes.
On a motion by Nancy Twomey, seconded by Ed Ross, the Killam School Building
Committee voted 7-0-0 to accept Daily Times Chronicle Invoice No. 260329 in the
amount of $313.14 for the J. Warren Killam Elementary School Project.
Roll call vote: Pat Tompkins – Yes; John Coote – Yes; Chris Haley – Yes; Ed Ross – Yes;
Greg Stepler – Yes; Nancy Twomey – Yes; Carla Nazzaro – Yes.
On a motion by Nancy Twomey, seconded by Ed Ross, the Killam School Building
Committee voted 7-0-0 to approve David Delair, Clerk of the Works, Invoices DDC
OW01, DDCOW02, and DDCOW03 in the total amount of $6,200.00 for the J.
Warren Killam Elementary School Project.
Roll call vote: Pat Tompkins – Yes; John Coote – Yes; Chris Haley – Yes; Ed Ross – Yes;
Greg Stepler – Yes; Nancy Twomey – Yes; Carla Nazzaro – Yes.
Page | 5
On a motion by Nancy Twomey, seconded by Ed Ross, the Killam School Building
Committee voted 7-0-0 to accept LBA Invoice No. 23495 in the amount of
$510,555.98 for the J. Warren Killam Elementary School Project.
Roll call vote: Pat Tompkins – Yes; John Coote – Yes; Chris Haley – Yes; Ed Ross – Yes;
Greg Stepler – Yes; Nancy Twomey – Yes; Carla Nazzaro – Yes.
On a motion by Nancy Twomey, seconded by Ed Ross, the Killam School Building
Committee voted 7-0-0 to accept Colliers Invoice No. 001162442 in the amount of
$67,504.00 for the J. Warren Killam Elementary School Project.
Roll call vote: Pat Tompkins – Yes; John Coote – Yes; Chris Haley – Yes; Ed Ross – Yes;
Greg Stepler – Yes; Nancy Twomey – Yes; Carla Nazzaro – Yes.
Project cash flow is trending in line with projections, approximately $1 to $2 million under
the estimated cash flow, which is favorable. The cash flow projection will be updated once
the contractor is on board and provides their estimated billing schedule.
CPL Schedule Update
Justin Ferdenzi provided an update on the project schedule. The bid is currently li ve on
BidDocs with significant interest, including numerous downloads and RFI submissions. Filed
Sub Bids are due May 6, 2026, and General Contractor bids are due May 19, 2026. The
committee will review bid results on May 22, 2026.
Following contractor selection and committee approval, the project team anticipates issuing
a Notice to Award and Notice to Proceed around the end of May or beginning of June 2026.
A kickoff meeting with the selected contractor will be held to coordinate mobilization after
the school year concludes.
Mike Carroll noted that the RFI deadline is April 23, 2026, at 3:00 PM. The project team has
received reasonable RFI requests indicating strong bidder engagement with the documents.
The design team is working through responses, inclu ding updates to the site logistics plan.
One vendor requested a deadline extension, which is not anticipated to be granted.
Approval of Prior Meeting Minutes (02/09/26) *
On a motion by Nancy Twomey, seconded by Ed Ross, the Killam School Building
Committee voted 6-0-1 to approve the meeting minutes of March 16, 2026. Chair
Carla Nazzaro abstained as she was not present at the March 16th meeting.
Roll call vote: Pat Tompkins – Yes; John Coote – Yes; Chris Haley – Yes; Ed Ross – Yes;
Greg Stepler – Yes; Nancy Twomey – Yes; Carla Nazzaro – Abstain.
On a motion by Nancy Twomey, seconded by Ed Ross, the Killam School Building
Committee voted 7-0-0 to approve the meeting minutes of March 30, 2026.
Roll call vote: Pat Tompkins – Yes; John Coote – Yes; Chris Haley – Yes; Ed Ross – Yes;
Greg Stepler – Yes; Nancy Twomey – Yes; Carla Nazzaro – Yes.
Church Parking Lot Update
Mike Carroll reported that the church parking lot license agreement has not yet been
finalized, as the church is not ready to proceed at this time. The project team has developed
a backup plan that includes temporary parking on site in the area of the future driveway,
which will be cleared this summer. Other parking options for future construction phases
have also been identified. The church parking lot remains the preferred option (Plan A), with
the on-site temporary parking service as Plan B. The parking arrangement also affects the
Page | 6
sequence of add alternate roadway work and safe student access during construction
phases.
Future Agenda Items & Next Meeting Dates
The next XLT meetings will be held on May 11th, May 18th, and June 8th. The next KSBC
meeting will be held on Thursday, May 21st (note the day change from the regular Monday
schedule), specifically to review and approve the general con tractor selection. The following
KSBC meeting will be on Monday, June 15th, which is expected to include an introduction of
the selected general contractor and a playground area design update. The parent
playground committee members will be invited to the June 15th meeting to review the
playground design.
Adjourn*
On a motion by Nancy Twomey, seconded by Ed Ross, the Killam School Building
Committee voted 7-0-0 to adjourn the meeting.
Roll call vote: Pat Tompkins – Yes; John Coote – Yes; Chris Haley – Yes; Ed Ross – Yes;
Greg Stepler – Yes; Nancy Twomey – Yes; Carla Nazzaro – Yes.
Town of Reading
Meeting Minutes
Page | 1
2016-09-22 LAG Board - Committee - Commission - Council:
Permanent Building Committee Killam School Building Committee
Date: 2026-05-11 Time: 7:00 PM
Building: Reading Town Hall Location: Conference Room
Address: 16 Lowell Street Session: Open Session
Purpose: General Business Version: Draft
Attendees: Members - Present:
John Coote, Chris Haley, Kirk McCormick, Ed Ross, Greg Stepler, Nancy
Twomey, and Carla Nazzaro.
Members - Not Present:
Shawn Brandt and Pat Tompkins.
Others Present:
Reading Town Manager Jayne Wellman, Reading Fecilities Clerk David
Dallaire, Colliers Project Director Mike Carroll, Colliers Project Manager Justin
Ferdenzi, LBA Project Manager Jenni Katajamaki, LBA Architect David Harris
Minutes Respectfully Submitted By: Harani Kumaresh
Topics of Discussion:
This meeting was held in-person in the Town Hall Conference Meeting Room and remotely
via Zoom.
Call to order:
Chair Carla Nazzaro called the meeting to order at 7:00 pm.
Roll call attendance: John Coote, Chris Haley, Kirk McCormick, Ed Ross, Greg Stepler, Nancy
Twomey, and Carla Nazzaro.
Public Comment:
No reports.
Liaison Reports:
No reports.
Review of Current Bid Status and Issues
Mike Carroll and Jayne Wellman provided an update on the current bid status. The original
timeline anticipated filed sub bids this week with general contractor bids due approximately
one week later. However, several weeks prior, a second-tier bidder (paragraph E sub-
bidder) raised a concern regarding what they believed was a proprietary specification
related to HVAC controls.
The project team met with town counsel to review the concern and informed the
complainant that the specification was intentionally proprietary, as the Killam Sch ool
Building Committee had reviewed and voted to approve six proprietary specification items at
its March meeting. The project team believed the matter was resolved.
Page | 2
However, the day before filed sub bids were due, the Attorney General’s (AG) Office Bid Unit
contacted the Town and directed that the HVAC work must be rebid. The specific objection
was to language in the specifications that stated, “substitutions not accepted.” The AG’s
Office determined that this language created a “chilling effect” on potential bidders, even
though a substitution request procedure existed within the bid documents (Division 0,
Section 1300).
Jayne noted that the paragraph E sub-bidder had not filed a formal bid protest, but the AG’s
Bid Unit issued direction to rebid the HVAC portion. Town counsel reviewed the matter and
confirmed that the committee’s proprietary vote process was proper; the issue was limited
to the specific “substitutions not accepted” language.
The project team initially proposed correcting the language through an addendum, which is
standard practice. However, the AG’s Office rejected this approach, stating that an
addendum was not acceptable, and also declined a meeting request from the project team.
Mike Carroll noted that while the AG’s specific direction addressed only HVAC, the same “no
substitutions” language existed for electrical and potentially other items among the six
proprietary specifications. The OPM and Jayne recommended rebidding the entire project
rather than just HVAC to avoid potential bid protests on the other proprietary items
afterward. This approach would minimize overall schedule impact.
Review Re-bid Timeline:
Mike Carroll presented the proposed rebid timeline:
• Cancel current bid by addendum (completed)
• Submit advertisement to Central Register by May 14, 2026
• Issue letter to all pre-qualified bidders explaining the cancellation and rebid
• Advertisements published and bid documents available through BidDocs on May 20,
2026
• RFIs due by May 28, 2026
• Addenda issued by June 1, 2026
• Filed Sub Bids due June 4, 2026 (two weeks plus one day, accounting for Memorial
Day)
• General Contractor Bids due June 11, 2026
• KSBC meeting on June 15, 2026 for recommendation and approval
• Notice to Proceed issued June 16, 2026
The rebid documents will consist of a conformed set incorporating the original bid
documents and five previously issued addenda, with clarifications on the six proprietary
specification items. The two-week bid period for filed sub bids was deemed sufficient, as the
documents have already been on the street and all pre-qualified bidders are familiar with
the project.
Mike Carroll noted that the school department’s request that the contractor not mobilize to
the site until students are out of school remains achievable under this timeline. Physical site
mobilization timing is not expected to change. The rebid results in approximately three
weeks of lost time for contractor pre-construction activities (paperwork, shop drawings,
submittals, and equipment orders).
Discussion on Proprietary Specifications and Substitutions:
The revised specification language will indicate that items such as Honeywell controls are
“intended to be proprietary specifications” while referencing the substitution request
procedure in Section 1300. Under Massachusetts General Law, even proprietary
specifications must allow for substitution requests. Bidders submitti ng substitution requests
must demonstrate that their proposed product is equal to the specified product.
John Coote raised concerns about potential disputes regarding substitution determinations,
noting that the process involves judgment calls that could be challenged. Mike Carroll
Page | 3
confirmed that the architect serves as the ultimate interpreter of the documents and would
review substitution requests in consultation with the district’s facilities team. Substitution
requests could potentially be brought to the committee for review.
Greg Stepler, noting his familiarity with control systems, cautioned the design team to
ensure the specification language is very specific about the functionality and requirements
of the control system rather than using boilerpl ate language. This specificity would better
support the proprietary designation if substitution requests were received. David Harris
confirmed that this communication had already been sent to the design team.
The committee discussed whether to hold a special KSBC meeting on Friday, June 12 or the
regularly scheduled Monday, June 15 meeting. Greg Stepler recommended the Monday
meeting to allow the OPM and design team additional time for bid review and leveling. The
committee agreed to maintain the June 15 meeting date.
Cancel Current Bid*
On a motion by Nancy Twomey, seconded by Ed Ross, the Killam School Building
Committee voted 7-0-0 to cancel the current bid for the J. Warren Killam
Elementary School Project.
Roll call vote: John Coote – Yes; Chris Haley – Yes; Kirk McCormick – Yes; Ed Ross – Yes;
Greg Stepler – Yes; Nancy Twomey – Yes; Carla Nazzaro – Yes.
Approve Proposed Re-bid Timeline*
On a motion by Nancy Twomey, seconded by Ed Ross, the Killam School Building
Committee voted 7-0-0 to approve the proposed rebid timeline as specified in the
agenda for the J. Warren Killam Elementary School Project.
Roll call vote: John Coote – Yes; Chris Haley – Yes; Kirk McCormick – Yes; Ed Ross – Yes;
Greg Stepler – Yes; Nancy Twomey – Yes; Carla Nazzaro – Yes.
Future Agenda Items & Next Meeting Dates
The next XLT meetings will be held on Monday, May 18th and June 8th. The next KSBC
meetings will be held on Thursday, May 21st and Monday, June 15th.
Adjourn*
On a motion by Ed Ross, seconded by Nancy Twomey, the Killam School Building
Committee voted 7-0-0 to adjourn the meeting.
Roll call vote: John Coote – Yes; Chris Haley – Yes; Kirk McCormick – Yes; Ed Ross – Yes;
Greg Stepler – Yes; Nancy Twomey – Yes; Carla Nazzaro – Yes.