HomeMy WebLinkAbout1983-07-11 Board of Survey Minutes Board of Survey Meeting of July 11, 1983 Page 1
R meeting of the Board of Survey convened in Room Sb, Municipal
Building at 8:01 P.M. Present were Chairman Wood, Secretary Barker, Board
Member Griffin and Superintendent. E. Roger Louanis.
The Board reviewed the letter from Parkwood Construction Company
requesting an extension of the completion date for Bak Knoll Subdivision
until September 30, 1983 on the advice of the Tree Warden for the planting
of the trees, and requesting that the bond be reduced to the value of the
work remaining.
It was moved, seconded and voted 3:0 to extend the completion
date on Bak Knoll Subdivision to September 30, 1983.
It was moved, seconded and voted 3:0 to reduce the Three Party
Agreement Bond to $20,000.00, releasing $100,000.00 of the present bond to
cover any work remaining.
The Board reviewed plans of a proposed new Subdivision off of
Franklin Street to be called "Batchelder Estates".
Superintendent Louanis stated that these plans were submitted to
us on June 20. There will be a Public Hearing held on July 25.
Asst. Superintendent Bergeron compiled a list of approximately 24
problems associated with the proposal, including the names of the proposed
streets that would have to be resolved by the Contractor before approval
would be given.
There is a proposed sewer ejector system to be built on Lot S.
The Department finds no major problems with this proposed
development but many insignificant problems seem to be cropping up.
Superintendent Louanis stated the Board will receive a copy of
the list of concerns before the Public Hearing.
The meeting adjourned at 8:35 P.M.
Respectfully submitted,