HomeMy WebLinkAbout2018-09-20 RMLD Board of Commissioners Minutes i rR
° Town of Reading RECEIVED
ToIA'rl �t F ,v
= Meeting Minutes I('Sy M¢ A♦ .
1�[_l1.�:I'm J, ly9 A.
.E ; j'1r25
Board - Committee - Commission - Council:
RMLD Board of Commissioners
Date: 2018-09-20 Time: 07:30 PM
Building: Reading Municipal Light Building Location: Winfred Spurr Audio Visual Room
Address: 230 Ash Street Session: Open Session
Purpose: General Business Version: Final
Attendees: Members - Present:
David Talbot, Vice Chair
John Stempeck, Commissioner
Tom O'Rourke, Commissioner
Philip B. Pacino, Commissioner
Members - Not Present:
David Hennessy, Chair
Others Present:
RMLD Staff:
Coleen O'Brien, General Manager
Hamid Jaffari, Director of Engineering and Operations
Jane Parenteau, Director of Integrated Resources
Wendy Markiewicz, Director of Business, Finance, and Technology
Tracy Schultz, Executive Assistant
Citizens' Advisory Board:
Dennis Kelley, Chair
Select Board Liasion:
Vanessa Alvarado
Minutes Respectfully Submitted By: John Stempeck, Secretary Pro Tem
Topics of Discussion:
Call Meeting to Order
Vice Chair Talbot called the meeting to order and announced that the meeting is being
videotaped at the RMLD office at 230 Ash Street, for distribution to the community television
stations in North Reading, Lynnfield, and Wilmington. Vice Chair Talbot read RMLD's Code of
Conduct.
Public Comment
Vice Chair Talbot welcomed Ms. Alvarado, who had no comments. Vice Chair Talbot
welcomed Mr. Kelley, who reported that at the CAB meeting the previous evening, there was a
reorganization and the upcoming budget meeting was discussed. There was no public
comment.
Approval of Board Minutes(Attachment 1)
Mr. Pocino mode a motion, seconded by Mr. Stempeck, to approve the June 21, 2018 minutes,
on the recommendation of the General Manager.
Motion Carried:4:0:0.
Report of the Chair-Vice Chair Talbot
Page 1 1
Meeting of the Sub-Committee on the Payment to the Town of Reading
Vice Chair Talbot deferred to Mr. Pacino, who stated that the Sub-Committee needs to
schedule another meeting. Mr. Pacho stated that he himself has been considering freezing the
payment for the next two or three years and then base the payment amount to reflect kWh
sales.
Ms. Alvarado asked if the report on RMLD's financial long-term outlook has been released.
Ms. O'Brien explained to save money on an outside study, Ms. O'Brien prepared a report on
RMLD's projected sales and distributed it to the Board.
Releasing the study to the Select Board was discussed. Ms. O'Brien expressed concern because
the Board Members have yet to provide feedback on the study.
Mr. O'Rourke stated that releasing the study before the Board discussed its contents may cause
more confusion if the board were to ultimately make a different recommendation.
Vice Chair Talbot suggested putting the study on next month's Agenda.
Ms. O'Brien also wanted to make it clear that the study includes recommendations but is not a
proposal to the Town.
Mr.Stempeck suggested stamping the study"Draft."
Vice Chair Talbot commented that RMLD pays the largest Town payment of any Massachusetts
municipal and that the money for the payment is coming from ratepayers. Vice Chair Talbot
stated he would like to find ways for the Town and RMLD to save money by collaborating. Ms.
Alvarado was receptive to that idea.
Mr. Pocinc stated that he wants to make it clear that freezing the payment is his idea and not a
proposal.
It was agreed that Ms. Schultz would contact the sub-committee members to schedule a
meeting as soon as possible.
General Manager's Report-Ms.O'Brien
Review of the General Manager
Mr. Stempeck made a motion, seconded by Mr. Pacino, that the Board approve the General
Manager Committee's recommendation that effective July 1, 2018, Ms. O'Brien receive a salary
increase of four-and-o-holf percent, in addition to a $6,000 bonus, paid out as Ms. O'Brien
chooses as ICMA, cash, or a combination of the two.
Motion Carried:4:0:0.
Review of Board Policies
Vice Chair Talbot stated his wish to hold off voting on the change to Policy No. 30, stating he
wants the policy to perhaps have more information on the topic of sustainable and renewable.
Integrated Resources Division-Ms. Parenteau
Community Engagement
Ms. Parenteau announced that RMLD's Ride and Drive event, held in collaboration with
Wakefield and Danvers, was a success. On Sunday, September 16 an estimated 75 to 100
customers attended and there were over 35 test drives. There will be a Tech Talk on Smart
Homes at the Reading Public Library on September 27 at 7 p.m. RMLD's Public Power Week
Open House will be on October 11 from 3 to 6 p.m.Wilmington is holding an open house for new
and existing residents on October 15 at 6 p.m. at the Wilmington Library. Elementary School Art
Contest materials are being distributed. The award ceremonies will take place in February. The
historical calendar is in the works.
Page 1 2
Integrated Resources Division-Ms. Parenteau
Community Engagement
Mr. Pacino asked about the EV rebate program. Ms. Parenteau replied that 31 rebates have
been issued. 30 was the forget. Update next month. Starting to analyze residential load off-peak
charging.
Power Supply Report-May 2018(Attachment 2)
Ms. Parenteau reported on June and July Purchased Power. Three years of energy costs and
costs per kWh from 2016 to 2018. Energy costs went from$32.4 million in FY 16 to$31.5 million in FY
17. The estimated cost for FY 18 is $30.1 million. Liquid natural gas prices are at an all-time low
and sales are going down. The average cost has gone from over 4.5 cents per kWh to 4.45
cents, which is a pass-through to customers. Transmission costs are going up an average of five
percent each year. FY 16 $12.3 million 5.6 percent increase in FY 1710 $13 million and in FY 2018
5.1 percent increase to $13.7 million. Those costs are primarily for regional network service and
are socialized throughout New England. Capacity costs for FY 2016 were $18.7 million and then
increased by 6.9 percent in 2017 to just under $20 million. FY 2018 capacity costs were $25.4
million, which is a 27 percent increase. This is seen on customer bills as PPCT. RMLD makes no
return from that charge. Ms. Parenteau then discussed kWh sales by class. declining trend, going
down an average of one percent per year.
Mr. Kelley asked if the CAB could get a breakdown of use by town. Ms. Parenteau answered in
the affirmative.
Engineering and Operations Report-June 2018-Mr. Jaffarl (Attachment 4)
Mr. Joffari stated that the total spending on routine capital construction for the month of June
was $68,523 bringing the year-to-date total to $1,360,110. Total capital spending in the month of
June was $687,683, bringing the year-to-date total to$6,513,565, leaving $1,171,956 remaining in
the budget. Mr. Joffari announced that progress is being made on routine maintenance. The
rate of pole failure is decreasing. Infrared scanning showed no hot spots at the substations.
Porcelain cutout replacement is 91 percent completed. Three underground subdivision
upgrades were completed, and many more are in progress. Lynnfield has 19 pending pole
transfers. North Reading has 9 pending pole transfers and 44 pending pole removals. Reading
has 27 pending pole transfers and 18 pending pole removals. Wilmington has 28 pending Pole
transfers and four pending pole removals. Reliability is improving. The larger-than-usual squirrel
population is leading to more animal-caused outages. RMLD has squirrel guards but they don't
always deter animals from making contact.
Due to recent gas explosions in the Boston area, Mr. Pacino asked about RMLD's readiness in the
event of an emergency. Mr. Jaffari explained that RMLD has an emergency management plan
and has contractors to assist if needed.
RMLD Procurement Requests Requiring Board Approval-Mr. Jaffari(Attachment 5)
IFB 2019-01: 1151 Pole Replacement Project
Mr. Jaffari explained that there are two lines feeding Station 4. Some of the poles on both lines
were determined to be at the end of their life. Lost year one line was taken care of. This is
preventive maintenance.The bid invitation was sent to 17 companies;five responded.
Mr. Pacino made a motion, seconded by Mr. Stempeck, that bid 2019-01 for: 1151 Pole
Replacement Project be awarded to:Mass Bay Electrical Corporation for$120,585.00, pursuant to
M.G.L. c. 30, Section 39M, as the lowest responsible and eligible bidder on the recommendation
of the General Manager.
Motion Carried:4:0:0.
General Discussion
Ms. O'Brien announced that RMLD had a self-audit in preparation for the need to be OSHA-
compliant by February 2019. M5. O'Brien explained that she asked the auditor to be extremely
thorough and shot the RMLD fared well. In a verbal assessment by the auditor.The auditor has to
prepare a final report and then a presentation on the results will be forthcoming.
Page 1 3
General Discussion
Meeting dates were discussed,and Ms. O'Brien stated that the CAB agreed to change the
Budget presentation form two nights to one night.The Board agreed to some.
Adjournment
At 9:05 p.m., Mr. Pacino made a motion,seconded by Mr.O'Rourke,that the Board adjourn.
A true copy of the RMLD Board of Commissioners minutes
as approved by a majority of the Commission.
John Stempeck,Secretary Pro Tem
RMLD Board of Commissioners
Page 1 4
READING MUNICIPAL
LIGHT DEPARTMENT
BOARD OF COMMISSIONERS
REGULAR SESSION
THURSDAY, SEPTEMBER 20, 2018
APPROVAL OF BOARD MINUTES
JUNE 21 , 2018 AND JULY 19, 2018
ATTACHMENT 1
READING MUNICIPAL LIGHT DEPARTMENT
BOARD OF COMMISSIONERS MEETING
230 Ash Street
Reading,MA 01867
June 21,2018
Start Time of Regular Session: 7:30 p.m.
End Time of Regular Session: 9:20 p.m.
Commissioners:
Dave Hennessy,Chair John Stempeck,Commissioner
Dave Talbot,Vice Chair Philip B. Pacino, Commissioner
Tom O'Rourke, Commissioner-Secretary Pro Tem
Staff:
Call O'Brien, General Manager Joyce Mulvaney,Communications Manager
Hamid Jaffari, Director of Engineering and Operations Ben Thivlerge,Resource Specialist
Jane Parenteau, Director of Integrated Resources Tracy Schultz, Executive Assistant
Wendy Markiewicz, Director of Business, Finance and
Technology
Citizens Advisory Board: Select Board Liaison:
Neil Cohen,Member Vanessa Alvarado
Call Meeting to Order
Chair Hennessy called the meeting to order and announced that the meeting is being videotaped at the RMLD
office at 230 Ash Street, for distribution to the community television stations in North Reading, Lynnfleld, and
Wilmington. Chair Hennessy then read the RMLD's Code of Conduct.
Public Comment
Chair Hennessy welcomed Mr. Cohen and Ms. Alvarado, neither of whom had comments.There was no public
comment.
Chair Hennessy explained that Vice Chair Talbot was participating remotely due to travel, and that all votes
would need to be roll call.Vice Chair Talbot greeted the Commission and apologized for his physical absence.
Approval of Board Minutes(Attachment 1)
Mr. Pacino made a motion, seconded by Mr.Stempeck, to approve the April 5, 2018 and April 17, 2018 minutes,
per the recommendation of the General Manager.
Chair Hennessy called for a poll of the vote: Mr. O'Rourke: Aye; Mr. Pacino: Aye; Chair Hennessy: Aye; Mr.
Stempeck: Aye; Mr.Talbot:Aye.
Motion Carded.
5:0:0.
RMLD Board Member Attendance at Citizens' Advisory Board Meetings Report-Mr. Pacino
Mr. Pacino stated that he attended the CAB meeting on May 16th. The financial report, reliability and
organizational study updates, and NEPPA conference were discussed. Mr. Pacino stated that he attended the
Town of Reading Audit Committee meeting on June 13th. The Committee recommended that the audit be
accepted as presented. There was no management letter. On June 20th Mr. Pacino attended the Citizens'
Advisory Board meeting in Mr.Stempeck's place. The CAB reviewed minutes and discussed OSHA compliance
and the new RMLD website.
General Manager's Report-Ms.O'Brien
Review of Board Policies
Ms. O'Brien explained that RMLD is in the process of reviewing and updating its policies.To date, 12 have been
completed, and five are being presented to the Board for review tonight. Ms. O'Brien stated that she would
provide an overview of the changes for each policy.Policy No.7 Sick Time gives more responsibility to the General
Manager,the Department Managers,and Human Resources for ensuring that there is no abuse of sick time. It
General Manager's Report-Ms. O'Brien
Review of Board Policies
provides for monitoring for abuse of sick time and time off according to legislation and RMLD's collective
bargaining agreements.
Ms. O'Brien explained that Policy No. 9 Section 2 Procurement policy has updated threshold values due to
changes in M.G.L. Chapter 164§56D.
Policy No. 17 Tuition Reimbursement now outlines approved areas of study and clarifies eligible expenses. Ms.
O'Brien explained that some schools are now allowing students to defer tuition payment until after the course is
completed if the employer has a tuition reimbursement program. Policy changes now allow for that. Mr.
Stempeck asked if professional education courses were included. Ms. O'Brien explained continuing education
credits are considered training and are processed as expenses. Mr. O'Rourke suggested adding a line for
supervisor signature on the reimbursement form. All agreed this should be done.
Ms. O'Brien stated that NERC cybersecurity requirements for compliance were added to Policy No. 27 Use of
RMLD Information Systems. Mr.Stempeck suggested adding language to Section D. Board of Commissioners to
allow the Board to send pertinent data and articles to each other. Mr. Pacino suggested using the word
.,educational" Mr.O'Rourke suggested changing "When in doubt:don't" to"When in doubt:ask" Mr.O'Rourke
mentioned that policy provisions for data protection may be something to consider in the future.
Mr. Pacino made a motion, seconded by Mr.Stempeck,that the Board approve the changes to RMLD Policy
No. 27 Use of RMLD Information Systems,with the changes in Section II Item D that the word 'educational,' be
added before 'procedural or housekeeping matters' and in Section III the last item in Section B replace the
word 'don't' with 'ask.'
Chair Hennessy called for a poll of the vote: Mr. O'Rourke: Aye; Chair Hennessy: Aye; Mr. Pacino: Aye; Mr.
Stempeck; Aye; Mr.Talbot:Aye.
Motion Carried.
5:0:0.
Mr. Pacino made a motion, seconded by Mr. O'Rourke, that the Board approve the changes to Policy No. 17
Tuition Reimbursement,with the change to Attachment A: adding a line for Supervisor signature.
Chair Hennessy called for a poll of the vote: Mr. O'Rourke: Aye; Chair Hennessy: Aye; Mr. Pacino: Aye; Mr.
Stempeck;Aye; Mr.Talbot: Aye.
Motion Carried.
5:0:0.
Ms. O'Brien stated that the last policy for review is Policy No. 31 RMLD Vehicle Use. An insurance company
accident form is in every RMLD vehicle. Instructions were added to the policy on immediately notifying a
supervisor after certain types of accidents occur. Hands free device use was clarified. Touching a phone or
electronic device is prohibited when driving.
Mr. Pacino made a motion, seconded by Mr. Stempeck, that the Board approve the changes to Policy No. 7
Sick Leave Benefits, No. 9 Procurement, and No. 31Vehicle Use, on the recommendation of the General
Manager.
Chair Hennessy called for a poll of the vote: Mr. O'Rourke: Aye; Chair Hennessy: Aye; Mr. Pacino: Aye; Mr.
Stempeck; Aye; Mr.Talbot:Aye,
Motion Carried.
5:0:0.
Ms.O'Brien announced that state entities must be OSHA compliant by February 13,2019.A trainer will be coming
in to RMLD for a meeting with the entire company. RMLD will be conducting a two-day self-audit at the end of
the summer. RMLD already follows the APPA Safety Manual which is OSHA based.
2
Integrated Resources Division-Ms. Porenteau
Power Supply Repot-April 2018(Attachment 3)
Ms. Parenteau announced that she would be reporting on April 2018 purchase power and began with capacity
requirements and imbedded costs from 2014 to 2018.In 2014 RMLD's April capacity requirement was 215,566 kW
and the average cost per kW was$10.25. In 2018 RMLD's April capacity requirement was 222,431 kW and there
was a significant increase to cost: $13.56 per kW. This was due to an increase in NEMA's capacity zone, which
resulted in a 16 percent increase for the capacity year (which runs from June 1 to May 31). This is a $3 million
annual cost increase. Capacity is based on the summer peak from the previous year.Ms. Parenteau announced
that Ms.Mulvaney has started the Shred the Peak campaign. RMLD has a list of 2,000 customers who have opted
in for Shred the Peak notifications.RMLD issues tweets and e-mailswhen anticipating peak usage.Chair Hennessy
asked how people can participate. Ms. Parenteau explained that customers can sign up on RMLD's website.
Ms. Parenteau then discussed purchased power and imbedded costs for fuel. April 2018 purchases, which are
somewhat reflective of sales,were down significantly. Despite that, RMLD's average cost of power is still under
five cents.Ms. Parenteau then discussed transmission costs over the last five-years, from 201410 2018.90 percent
of transmission costs are through ISO New England which provides regional network service. Costs are socialized
throughout New England and are based on monthly peak. RMLD's transmission providers are National Grid and
Eversource. Costs are based on monthly peak and regional network charges and are forecasted to increase
annually.
Electric Vehicle Pilot Program-Mr.Thivierge(Attachment 2)
Mr. Thlvierge explained that RMLD has started an electric vehicle (EVA pilot program for the summer called
'Electrify Your Ride'. Mr.Thlvierge highlighted the environmental and savings benefits of EVs and explained that
there are three types of electric vehicles: plug-in electric hybrid (gas and electric, with a battery capacity less
than 10 kWh , plug-in electric hybrid plus (gas and electric, with a battery capacity greater than 10 kWh), and
battery electric vehicles (completely electric). Mr. Thivierge explained that RMLD is offering a $1,000 rebate for
the purchase or lease of new plug-in electric hybrid plus vehicles and a$1,500 rebate for the purchase or lease
of new or used battery electric vehicles. RMLD also has a residential EV charging station rebate for 100 percent
of equipment costs (up to$500) for the home installation of level 2 networked ('smart') charging stations.
Vice Chair Talbot asked how many other light departments have similar programs? Mr. Thivierge replied that
RMLD is the only municipal in Massachusetts offering a rebate for the purchase or lease of a car.
Ms. O'Brien explained that less people are coming in for solar. Ms. Parenteau stated that the rebate budget is
$235,000 and $40,000 has been allocated to the EV program.
Vice Chair Talbot stated that a collaboration with the Town of Reading could benefit both sides. The Town and
RMLD should think creatively about future technologies.Mr.Encino added that he will soon be purchasing a new
car and stated that zoning by-laws need to be tweaked.
Ms. Alvarado stated that is a timely idea since Select Board is beginning to discuss Master Plan and the Zoning
Board is updating their guidelines. Chair Hennessy asked if there's anything RMLD can do. Ms. O'Brien told Ms.
Alvarado that RMLD can provide the Select board with specs, guidelines, and language regarding charging
stations.
Ms. O'Brien stated that RMLD is developing a program to approach refailors in strategically selected locations
about installing EV chargers. Chair Hennessy asked if the EV chargers will be RMLD owned. Ms. O'Brien replied
that only RMLD can sell electricity within its service territory. Unless a company installs a meter and provides
charging to its employees for free the electricity must be sold by RMLD.
Mr.Thivierge continued his presentation. RMLD's goal is to have 30 approved vehicle applications in five months
and is therefore aiming for six per month.Six applications have been approved in June so for.Educational articles
will be running in local newspapers and online on The Patch and the RMLD website.Information will be provided
on billing envelopes and through e-mails to customers. RMLD will be of the Wilmington Farmer's Market on
Sunday, July 15 to showcase and allow customers to test drive electric vehicles.
3
Community Engagement-Ms.Mulvaney
Ms. Mulvaney announced that RMLD's new website launched on June 10. Content has been reorganized and
the design has been cleaned up.The website is now mobile friendly. It's a responsive design so it adjusts to any
screen. There will be an outage map. There are separate sections for residential and commercial customers.
RMLD looked at analytics from its previous website and the most selected are now quick links. The News and
Announcements section highlights current events and campaigns. Ms. O'Brien added that there is a calendar
showing upcoming Board and CAB meetings.
Mr.Talbot disconnected from the meeting.
Financial Report-April 2018- Ms. Markiewicz- (Attachment 4)
Ms.Markiewicz announced that she would be reporting on the first ten months of the fiscal year,ending on April
30,2018.Ms. Markiewicz stated that a FERC accounting trainer stated that the industry standard is to have three
to four months of operating cash available. RMLD targeting two months understanding that there is reserve
available if needed. Ms. Markiewicz then presented o summary of plant. As of April, total capital assets were
$77.5 million. Of that$77.5 million, $52.5 million is infrastructure,which makes up the bulk of plant.Structures and
improvements total$10.8 million,equipment and furnishings total$12.9 million (computer hardware and software,
office furniture,fleet,tools, GIS,SCADA,fiber), and land totals$1.3 million.Ms. Markiewicz then presented a plant
comparison over the last five-years. In 2014 structures and improvements started of$6.4 million and has gone up
to $10.8 million. Equipment and furnishings has stayed flat because RMLD hasn't put a lot of money into office
equipment or fleet. Infrastructure started at$49.5 million and has increased to$52.5 million.
Ms. Markiewicz stated that year-to-date operating and maintenance expenses are on target for the budget.
May looks like it will go over budget but the impact from the March storms does not seem to be as dramatic as
anticipated.
Engineering and Operations Report-April 2018- Mr.Jail (Attachment 5)
Mr.Jaffari stated that year-to-date capital spending totals$5,007,896.$7,685,521 was budgeted for Fiscal Year
2018 so$2,677,625 remains.Mr.Jaffari stated that routine maintenance is going well and that RMLD is
monitoring the tree-trimming program to ensure that if doesn't go over the amount budgeted.843 spans have
been cut through April.There were no substation hof spots.Three underground subdivisions were completed in
April and eight more are in progress. Lynnfield has 20 pending transfers and one pending pull pole. North
Reading has 10 transfers and 49 pull poles. Reading has 27 transfers and 54 pull poles.Wilmington has 35
transfers and four pull poles. These numbers will be substantially higher in May and June because a lot of
upgrades have been completed. Reliability indices are well below the national and regional averages for
outages. Mr.Jaffari announced that all Fiscal Year 2018 projects are completed except for the parking lot.
There was a round of applause.Mr. Jaffari stated that Fiscal Year 2019 projects are being started ahead of
schedule.
General Discussion
Mr. Pacino suggested that the Sub-Committee Payment to the Town of Reading be listed as an agenda item
for the next Board meeting and future meeting dates were discussed.
Adjournment
Mr.Stempeck made a motion,seconded by Mr. O'Rourke,that the Board go into Executive Session to consider
the purchase of real property and return to Regular Session for the sole purpose of adjournment.
Motion Carried.
4:0:0.
A true copy of the RMLD Board of Commissioners minutes
as approved by a majority of the Commission.
Tom O'Rourke,Secretary Pro Tem
RMLD Board of Commissioners
4
POWER SUPPLY REPORT
JUNE AND JULY 2018
ATTACHMENT 2
^ , M V
W W D
O
O O
in N o
Ln
C N v
4-+
O o �
0
O N
023
Qu rc)
m c �
v �
r c
d
v o
c
CD-
Q)
0 0 0 0 0 0Lr)
v v v a
0 0 0 0 0 0
0 0 0 0 0 0
V). 41� 40 11). in in
00
■ N
0
Y N
}
LL
L r
Q G 3
}r !'I a
V }
LL I
� � o
r N
,A }
W LL
Y
O V
to
p L
V LL
C
W
Atko �
W 0
N
N
}
W LL
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0m0000000Ln
m N N � cZ o 0 (3 a o0
m m m m m m m N N N
Vw Vw in to to in Ln +n +n in
00
O
N
}
LL
N oo
O Jw
U O
C N
O L.L
�E
Ln O
c N
co
L {.L
O
N
T
u
00
01
0
N
}
LL
W
N 0
O N
U }
L
4-J , o
�U l0
Q 0
co N
U >-
LL
0
N
N
}
LL
OD
_ o
}
0
N
LL
N
7�C
V 10 N
cn OO o D
� o
FD Q)
N H
N LL.
F:)
r
0 0 0 0 0 0 0 0
0 o 0 0 0 0 o 0
0 6 6 6 6 6 0 C
0 0 0 0 0 0 0 0
16 V N O os V N
NNNN N N N N
SGI OS u M�
00
_ o
C'4
o
}
N 'O
00 E;
V) p
N
LL U')
i o
O
N N
L o "
N
O O O O O O
O O O O O O
O O O O O O
O O O O O O
L6 O ui O vi O
O O a, a, 00 00
SCIDS qmA
0
0
N
N LL
Q
L
U
V)
U
00
IL04
7C) O r
N O
0o
N LL
/� LL
SL
C�
L
V
O
N
r
O o 0 0 0 0 0 0
0 0 0 00 o 0 0
0 0 0 0 0 0 0 0
00 0 0 0 0 0 0
0 00 O 00 0 00 0 00
✓J VJ V V (") Cl N N
N N N N N N N N
salr)S qml
co
o
� N
N LL
U
L
Q)
00C N
C � C
r
4' O }
N
U LL D
@ � 0
r L N
O N
LL LL u
L LL
J
Y
� V
4+ Q
N
}
LL
O O O O O O O O O O
O O O O O O O O O O
O O O O O O O O O O
OOOOOO OO O O
U� O 6 O h O u� O Ui O
D, a OJ OJ N Io 10 4
10 10 10 10 10 10 10 10 10 10
S91 IDS uMj
To: Coleen O'Brien
Fr nr
1 �aureen McHugh, Jane Parenteau
Dale August 31, 2018
Subject: Purchase Power Summary—June, 2018
Energy Services Division(ESD)has completed the Purchase Power Summary for the
month of June,2018.
ENERGY
The RMLD's total metered load for the month was 57,931,718, which is a 5.97%
decrease from the June, 2017 figures.
Table 1 is a breakdown by source of the energy purchases.
Table 7
Amount of Cost of %of Total Total$ $as e
Resource Emmy Energy Energy Coats %
(kWh) (Val
Millstone 03 3,567,431 $838 6.07% $22,]54 115%
Seabrook 5,]18,587 $592 973% $33,854 171%
Stanbrook lMeooediate 101 $3524 171% $35,383 176%
Shell Energy 9,90'allo $5752 16.86% 5569,980 2873%
1 1,771,368 $5.36 3.01% $9.530 048%
Neste. 6,11000 $3345 11.27% $221,541 1117%
ISO Interchange 13,260,435 $29% 22.559% $391,123 20.02%
Nem.Cangeation $0.00 000% 496,015 434%
Coop Resales 15,71a $14880 003% $2,339 012%
ECF 3,360,000 $26M 5.71% $69.133 449%
Flydm Projects• 1,401,396 $6619 2.38% $92.760 468%
Sharma Watson Unit 262.846 $9033 045% $23,742 1.209h
Saddleback/Jericho Wind 1,434,026 $7892 244% $113,171 570%
Community Solar 845,862 $7316 1 44% 161,872 312%
Eaelon 9,475,20) $3888 1612% $368.357 18.57%
Stonybrooh Peskin, 143,250 $199.00 0.24% $28,507 1.44%
Monthly Total 58,792,691 $3375 10000% $1984,037 100.W%
'PepFeNl, Woronoco,MOfm MYw,Turoer FaUs,Co/lin$Wones,,HaYery Ai AVinki Hydro
Table 2 breaks down the ISO interchange between the DA LMP Settlement and the RT
Net Energy for the month of June,2018.
Table 2
Amount Cost %of Total
Resource of Energy of Energy Energy
(kWh) ($/MM)
ISO DA LMP19,337,251 $29.41 32.89%
Settlement
RT Net Energy " (6,076,816) $35.82 -10.34%
Seelement
ISO Interchange 13,260,435 $33.40 22.55%
(sublotaq
Independent system Operalm Day-A4eW rmalional MaMmal Pnca
JUNE 2018 ENERGY BY RESOURCE
%mvv,aakPk
U
5eob�nok
14.13%
p
For
Shell riiergy 1
t4.54Y
Hydro Projects
2.35%
LSD mWchpnye
12.55'%
NYPA
CAPACITY
The RMLD hit a demand of 135,950 kW, which occurred on June 18, at 5 pm. The
RMLD's monthly UCAP requirement for June,2018 was 233,627 Ms.
Table 3 shows the sources of capacity that the RMLD utilized to meet its requirements.
Table 3
Source Amount(kWs) Cost($IkW-month) Total Cost$ %of Total Cost
Millstone#3 4,950 24.76 $122,550 571%
Seabrook 7,914 18.89 $149,495 6.97%
Stonybrook Peaking 24,980 2.33 $58,233 271%
Stonybrook CC 42,925 8.20 $351,959 18.41%
NYPA 0 0.00 -$41,063 -1.91%
Hydro Quebec 0 0 -$39,856 -1.88%
Braintree Watson Unit 0 0.00 $12,343 0.58%
150-NE Supply Auction 152,858 10.02 $1,531,588 71.39%
Total 233,627 $9.18 $2,145,249 100.00%
Table 4 shows the dollar amounts for energy and capacity per source.
Table 4 Cost of
%of Arm of Energy Power
Resource Energy Capacity Total cast Total Cwt (kWh) skWh)
Millstone#3 $22,]54 $122,550 $145357 3.52% 3,557,431 0N07
Seabrook $33,854 $149495 $183.349 444% 5,718,567 0.W21
Stonybrwklntermediale $35,383 $351,959 $387,342 9.38% 1,004,192 03857
Hydro puabac $0 -$39,856 -tolerate 497% 00000
Shall Energy $569980 $0 $559,980 13.80% 9,909,800 0M75
N.AEVEOF $221541 $0 $221,541 5.37% 5693,000 00335
NYPA $9538 $41083 -$31,525 -076% 1,771,368 -0.0178
ISO Interchange $397,123 $1,531,588 $1,928,711 46.71% 13,268435 01454
Name Congestion $86,015 $0 -$86,015 -208% - 00000
EOE $89,133 $0 $89,133 2.16% 3.350.000 00265
* hydro Projects $92,760 $0 $92,760 2254 1,401,396 0Deal
elect.Watson Unit $23.742 $12,343 species 0.87% 262,846 01373
" SaCdlebeck/,kncM10 $113,171 $a $113.91 274% 1434,026 00769
* Burlington 8 Community Solar $61,872 So $81,872 1 50% 845,682 00732
Coop Resales $2339 $0 $2,339 0.06% 15,718 014611
Exelon Energy $388,39 $0 E368,357 892% 9475,200 0.0389
Stonybrook Peaking $28,507 $58,233 $86,740 2.10% 143,250 06055
Monthly Total $1,984,037 $2,145,249 $4,129,286 10000% 58,792691 00702
*Renewable Resources;per RMLD Board Policy,any RECa are said to offset energy is for all ewtomers.
RENEWABLE ENERGY CERTIFICATES (RECs)
Table 5 shows the amount of banked and projected RECs for the Swift River Hydro
Projects through June, as well as their estimated market value.
Table 5
RECs Sutmary
2018
REC RECs RECs BIO Revenue Revenue
Classiiandon Projected Sold $ Potential Received
Cr] 8.936 1,726 1250 $111,694 $21,575
NWl 2,398 459 1260 $30210 $5,783
MR/Cr/RVR61 15,909 2,988 12.70 =2044 $37,948
eln/RV,iR1 8,588 1,624 1270 $109,060 $20,625
W2 4906 940 2600 $127,808 $24,440
Totals 40,738 7,737 $580,623 $110,371
TRANSMISSION
The RMLD's total transmission costs for the month of June, 2018 were$1,106,831.This
is an increase of 19.75% from the May transmission Cost of$924,280. In June, 2017 the
transmission costs were$1,305,840.
Table 6
CuMM MPMh Last Month Last You,
Peak Demand(kW) 135,950 107,880 155,746
EneW(kWh) 58,792,691 54,050361 60,903,283
EneWS) $1,984.037 $1845,175 $2,520.199
Capacity(5) $2,145,249 $2,135,703 52379,893
Tansmiselon($) $1,10831 $924280 $1,305,840
TMdI $5,236,117 $4,905,156 $6205,931
To: Coleco O'Brien
Fro Maureen McHugh, Jane Parentea�
Date: l�1 September 10,2018
Subject: Purchase Power Summary—July,2018
Energy Services Division (ESD)has completed the Purchase Power Summary for the
month of July, 2018.
ENERGY
The PMLD's total metered load for the month was 71,666745, which is a 8.74%increase
from the July, 2017 figures.
Table I is a breakdown by source of the energy purchases.
Table 7
Amount of Cost of %of Total Total $asa
Resource Energy Energy Energy Costs %
(kWh) ($/MUM)
Millstone p3 3,656,197 $6.38 5.03% $23,320 0.82%
Seabrook 5,905.203 $5.92 8.13% $34.959 123%
Stanybrock Intermetiate 2,6811 $34A2 370% $92,520 3.26%
Shell Energy 13.098,600 $5770 18.031/6 $755,749 26.00%
NYPA 2,046,901 $5.25 2.82% $10,745 0.38%
Nextel 3,550,000 $38.96 4.89% $138,302 4.07%
ISO Interchange 15,789,480 $3524 2174% $556,434 19.58%
Nemo Congestion - sow 0.00% $548 002%
Coop Resates 6,110 $181.51 0.01% $1,109 004%
EDF 11272,800 $36.40 11,39% $301.170 10.80%
Hydro Prgecs' 2,008,171 $6935 276% $139.271 4.90%
Braintree Watsan DNt 351,111 $62.11 0.46% $21,806 077%
Sa Rfleback/Jadcho Wirel 1,070,934 $86.38 1.47% $92,509 3.28%
Community Solar 965,215 $73.10 1.33% $70,561 2.40%
Exalon 13,111,200 $44.15 18.05% $578.815 2037%
S"throok Peaking 118,581 $196.98 0.16% $23,358 082%
Monthly Total 72,638.493 $39.11 10000% $2,641,176 100.00%
IeAsoaraa, WMea.."anRiver,runner Falls.Collins,Pionear, iwy Mils,Asoinook Ryaro
Table 2 breaks down the ISO interchange between the DA LMP Settlement and the RT
Net Energy for the month of July, 2018.
Table 2
Amount Cost %of Total
Resource of Energy of Energy Energy
(kWh) ($/Mwh)
ISO DA LMP22,093,167 $35.58 30.42%
Settlement
RT Net Energy" (6,303,708) $36.26 -8.68%
Settlement
ISO Interchange 15,789,460 $35.24 21.74%
(subtotal)
l Mep rdmt System OWalor Day-Ahead Locational Ma,rW Price
JULY 2018 ENERGY BY RESOURCE
env
Exelor
18.05% i
�Y
Shell Energy I
18.03%
J
Hydro Prnlects
2.16%
ISO Interchange .�
1t J4%
CAPACITY
The RMLD hit a demand of 152,472 kW,which occurred on July 3, at 3 pm. The
RMLD's monthly UCAP requirement for July, 2018 was 233,627 kWs.
Table 3 shows the sources of capacity that the RMLD utilized to meet its requirements.
Table 3
Source Amount frWs) Cost($7kW-month) Total Cost$ %of Total Coat
Millstone#3 4,950 22.75 $112,623 5.49%
Seabrook 7,914 19.81 $156,747 7.65%
Stonybrook Peaking 24,980 1.98 $49,550 2,42%
Stonybrook CC 42,925 3.34 $143,515 7.00%
NVPA 0 0.00 -$16,011 -0.78%
Hydro Quebec 0 0 -$39,605 -1.93%
Braintree Walson Unit 0 0.00 $113,603 5.54%
ISO-NE Supply Auction 152,858 10.00 $1,529,165 7461%
Total 233,627 $8.77 $2,049,586 100.00%
Table 4 shows the dollar amounts for energy and capacity per source.
Table Cost of
%of Amt of Energy Power
Resource Energy Cill Total at Total Cost (kWh) (VI
Millstone#3 $23,320 $112,623 $135,943 2,78% 3.656,187 0.0372
Seabrook $3Q959 $151 $191,706 3.92% 5,905,203 00325
Stonybrook Intermediate $92,520 $143,515 $236.034 4.83% 2,688,020 0.0878
Hydra Quebec $0 -$39,605 -$39,805 -0.81% - 0.0000
Shell Energy $755,749 $0 $755,749 15.45% 13,098,600 00577
NextEmlEDF $138.302 $0 $138,302 2.83% 3,550,000 00390
` NVPA $10,745 -$1Q011 45266 -DA 1% 204Q901 4I0026
ISO Interchange $556,434 $1,529,165 $2,085.599 42.64% 15,781 0.1321
Noma Congestion $548 $0 $548 0.01% - 0.0000
EDF $301,170 $0 $31 6.16% 8,272,800 0.0364
` Hydm Projects $139,271 $0 $139,271 2.85% 2,008,171 00694
Beaman Watron Unit $21,806 $11303 $135,409 277% 351,111 0.3857
` Sainleback/Jedoho $92,509 $0 $92,509 1.69% 110701934 0.0864
` Burlington B Community Solar $70,561 $0 $70,561 1.44% 985,215 00731
Coop Resales $1,109 $o $1,109 0.02% 6,110 0.1815
Exebn Energy $578,815 $0 $578,815 11.83% 13,111,200 0.0441
Stonybrook Peaking $23.358 $49,550 $72,907 1.49% 118,581 0.6148
Monthly Total $2,841176 $2,049,586 $4,80.762 100.00% 72,638,493 00073
*Renewable Resources;per RMLD Board Policy,any Iii ere sold to offset energy cost,for all cmtwmera.
RENEWABLE ENERGY CERTIFICATES (RECs)
Table 5 shows the amount of banked and projected RECs for the Swift River Hydro
Projects through July,as well as their estimated market value.
Table 5
RECs Summary
2018
REC RECS RECs BID Revenue Rover.
Classification Projected Sold $ Potential Received
a2 9,229 1,726 12.50 $115,356 $21,575
Mn 1 2,455 459 12.60 $30,928 $5,783
Ma/ci/ai/NH1 16,631 2,988 1270 $211,214 537,948
Ma/RI/NH8,937 1,624 12.70 $113,500 520,625
Mot 5,022 940 26.00 $130,572 $24,440
Totals 42,273 7,737 $601,570 $110,371
TRANSMISSION
The RMLIJ's total transmission costs for the month of July, 2018 were$1,362,656. This
is an increase of 23.11% from the June transmission cost of$1,106,831. In July, 2017 the
transmission costs were$1,546,151.
Table 6
Current Monti Last Month Last Year
Peak Demand vW) 152,472 135,950 145.294
Energy(kWh) 12,638.493 58,792,691 66,553,229
Energy($) $2,841,176 $1,984,037 $2,709,058
Ca9aaty($) $2.049586 $2,145,249 $2,081,117
Transmission($) $1,362.656 $1106,831 $1,540151
Total $6,253,418 $5,236,117 $6,336,927
ENGINEERING & OPERATIONS REPORT
JUNE AND JULY 2018
ATTACHMENT 3
N
0
O
0Qy
S Y
0 O
O N O 0
040
O)
06 E O a w
U E O
N
_ 0 0
O
O Q c U
ND N
.i V) o
m �
o
.� C3
W
* ; ( § Ptf42 ; lf § § ! IP ! ! § § Z (
cn .
—
\ /�
� 7
� | } \ ` \ \ � \ \ \ \ � \ � r § \ \ \
0) [ .
— E
\
ACL 0 _
50 ga
u 5 \ j \
:
! - \ — —
' ( \ ! \ )
! ) § ! ) ; : \ \ f ! liKf / r ) ! ) ! / /
: ® : > !
O P P O W M o J
w MXIII
cli
64 fR tR fPr b4
V uJ VO V N P f�
N M b4 b4 Ji � Vi V
tR tR i i i i
N
c
O �
_ O
� J
N
LL � H
00 0
U
od o
•Q m a
C o o a
U — E
o
c E o V a
2 3
C � (D v O f a
O O ° Qr c a0i o
EO w 2
"O
W N `o o :
J C T t N C 2 .O C py
O O Z p 0 O c O U ° E
00 w o QU wo pT3
O O) 0 O� o °' N L -0 `' pa i v
� 01 p N m
] L N
-p Oo O =0CU p 0m3
U C_ = 0 Ou Ur C 0
N U Cp m Z O p LL m
O N u L E E � .
> O 0 O C
a O a N Q
p N
v P
n E
OO O O O C
fR tPr Q
P N cq /^
LO w
Z h °
co
o
n _ W
D P CL O a�
N J
_ ~ N
M O
V .a Q . .
- o K o
� U
� J a
� Q N
� N
o m O M
c
10
Js c C
O V d 7
� O Q
� p O
V N O C
o = � Z
0 0
N
N v
E
O
U
CL
c 3
N c
� v
� 3
v
C
o
t �
T U wC' O
L O 0 b L Q
C C O N c a m 7 C U p
a U om ° U E
O N N N
> Q
OU
O o N o C CLC
E Q a O °� Cl C� C O
o
O a C U
5 �
a -
F- d 5 a
. )\ o
\ \
c \
� \ \
0 C3` ! a
� -
� / 2 ( } 7 $
o0 13 3 &
\ \ \ k3
k 3f ! \
¢ S \ 0 \ / \ \
§ § 7, : / \
( ■ / aCL
/
= t & a
■ - -
ƒ � 2 a -
■ ■ t
H133
\� \ ay!• � d
,J t I �!i it � s i • � ���—.—,
0
IL
E a
o c
0 Q (1) p
O O >
C) O I p I O
� J N
> C
0 0
LO � o z 3
c
3 D
O O
I I
� � � . . . . . . . . . . . . . . „ �
� �) � � ! ,: ! !! r . • ! _ , | !` : ! ! ! ! | 1 . , : | ! ! ,
! , , ; . ,
ff )
\
\ \ ) ) § § \ ) z ! ) « !
(_ ! !
z a z
� 2 !
§ I . § (
! | ! § , $ / ]
~ , !
} | -
|
� - _
t ® a � 1111111 ..
00
1111111 '
Go
ciz
N $ N
? v � �
N 'a 7 .2
3 1A �
N II Loop � o
o � o�td
D
Ev3 � O
➢ gip O
Eu o
xii3o
ti
S
N
N
C
lid
� 3
N
0
N
00 3
O
w
d
7
u &
E
WV.
RMLD PROCUREMENT REQUEST
REQUIRING BOARD APPROVAL
ATTACHMENT 4
Reading
Municipal
wLight
,�x Deparment
e
RMLDxs
�- 230 AshStreet
ex
R().Box 150
Reeding,MA 0186/0250
TeL(781)9611340
Wm: twwmdd.c.
September 10,2018
Town of Reading Municipal Light Board
Subject: IFB 2019-01: 115kV Pole Replacement Project
Pursuant m M.G.L c.30§39M,on July 11,2018,an invitation for bid was placed as a legal notice in the
Middlesex East Section of the Daily Times Chronicle and in the Central Register requesting sealed bids for the
I I5kV Pole Replacement Project.
An invitation for bid was sent to the following seventeen companies'
Construct Connect Fischbach&Moore Electric Northeast Line Construction Corp.
Group,ITC
The Blue Book Building& Norlhiiner Utilities,LLC
Construction Network Harlan Electric Company
One Source Power, LLC
Dagle Electrical Construction Corp. Mass Bay Electrical Corporation
Power Line Contractors
Deltek Maverick Construction
ElecComm Corporation Project Dog
McDonald Electrical
Elcenor Hawkeye Corporation/MEC Power Group Sargent Electric Company
Sealed bids were received from five companies: Harlan Electric Company, Mass Bay Electrical Corporation,
Istothbne Utilities,LLC, One Source Power,LLC,and Sargent Electric Company.
The sealed bids were publicly opened and read aloud at 11:00 a.m. on August 1, 2018, in the Town of Reading
Municipal Light Department's Winfred Spurr AV Room,230 Ash Street,Reading,Massachusetts.
The bids were reviewed,analyzed and evaluated by staff and recommended to the General Manager.
Move that bid 2019-01 for: I I5kV Pole Replacement Project be awarded to:Mass Bay Electrical
Corporation for 5120,555.00,pursuant to M.G.L.c,30, §39M,as the lowest responsible and eligible bidder
on the recommendation of the General Manager.
The FY 19 "al et amount for this item is$160,000.
cDon r
Hamid JaRari
Colo.O'Brien
115kV Pole Replacement Project
IFS: 2019-01
Lump Sum Bid
Bidder Price Pricing Notes
Matting has been included in the Lump Sum pricing for access of the last
Harlan Electric Company $152,140.05 two structures in the ROW,leading into the substations. These are
structures 504-6 and 504-7. The matting price amounts to$20,00, If
this matting is not required,the bid may be reduced by this amount.
Mats Say Electrical corporation $120,585.00
Northllne Utilities,LLC $288,630.58
One Souris Power,LLC $257,000.00
Sargent Electric Company $401
BOARD MATERIAL AVAILABLE
BUT NOT DISCUSSED
3 `e
ME '^X mX �gX Y�X aX
e3
o
°� a €a nae rX o$X 'aX u4,ryX
E Ee3
N x Yr x
; � mX 'n$X nX rym mX
rs�
3z; nX nX 'n� 'OX mX
«$$ $ $
3
z.
o m ¢ 4iYW m �r mYs xjYW _ '-m � z
� ¢ ar zriX riX fart fiiX ; ii}
From: Traw S h lt,
To: RMLD Board Members Gmuo;"Dave Hennessy(Dd dhenna5yOamT Wnrl'
Subjed: "and Payroll Questions for 9-20-18 Board Book
Data: We maday,Septamber 12,2018 1:55:00 PM
Good afternoon,
AP:
On July 131h there were no Commissioner questions.
On July 201h there were no Commissioner questions.
On July 271h there were no Commissioner questions.
On August 3rd there were no Commissioner questions.
On August 101h there were no Commissioner questions.
On August 17th there were no Commissioner questions.
On August 24th there were no Commissioner questions.
On August 3151 there were no Commissioner questions.
On September 7th there were no Commissioner questions.
Payroll:
On July 231d there were no Commissioner questions.
On August 6 there were no Commissioner questions.
On August 201h there was a Commissioner question about "Extra Regular" pay.
This e-mail will be included in 9-20-18 Board Book.
Tracy Schultz
Executive Assistant
Reading Municipal Light Department
230 Ash Street. Reading. MA. 0186
Tel: 781.942.6489