HomeMy WebLinkAbout2015-11-05 ad Hoc - Library Building Committee MinutesOFF?
'6'�9r /MCORPOPP�
Town of Reading
Meeting Minutes
TOWN CLERK
RD'\GANG. M SS.
Board - Committee - Commission - Council:
cC a� P 501
Ad Hoc Library Building �ommitt e
Date: 2015 -11 -05 Time: 7:00 PM
Building: Reading Town Hall Location: Conference Room
Address: 16 Lowell Street
Purpose: General Business Session: Open Session
Attendees: Members - Present:
Chairman David Hutchinson, Vice Chairman Rachel Baumgartner, Greg
Stepler, Jane Kinsella, Bob Newton, Cherrie Dubois
Members - Not Present:
Nancy Twomey, Marc Moll
Others Present:
Town Manager Bob LeLacheur, Project Manager Bob Labrecque, Facilities
Director Joe Huggins, Library Trustees Alice Collins and Vicki Yablonsky,
Executive Assistant Paula Schena
Minutes Respectfully Submitted By: Secretary
Topics of Discussion:
Approval of Minutes
A motion by Dubois seconded by Newton to approve the minutes of October 8,
2015 as amended was approved by a vote of 6 -0 -0.
Discussion /Action Items
Project Activity and Timeline Update - Bob Labrecque noted that change order #7 will be
finalized on Monday in the amount of $106,422.14 and reflected in the change log for open
changes.
Ruth Urell asked why we are deleting the painting of the masonry wall in the reading room
and Bob Labrecque noted that the architect indicated painting the exposed brick and direct
the architect to delete the painting and leave the brick exposed to view without painting.
Some selective repoint has been done on the brick.
Bob Labrecque noted that the open change log on page 24 has some big ticket items. The
first four are masonry and items two through four should be done by the end of the month
and the price should drop. CCD #25 is to rebuild the brick work on the north and east walls
at two building corners. The deteriorated conditions of the brick work are similar in both
locations. Page 2 shows the porte cochere carpentry and masonry. David Hutchinson noted
that we originally thought it wouldn't have to be rebuilt but we found out otherwise.
Bob Labrecque noted that the lobby revisions price in PR 17 will come down. PR22 is for
floor leveling. PR27 is the Rittland Heaters at the turrets which were not included in the bid
documents. The architect specified curved fin tube heating elements in three locations and
it was found to be too expensive so they are looking at another option for less money but
the same BTU output. David Hutchinson asked why did this happen the Bob Labrecque
noted that the heating elements were not in the original design.
Page 1 1
Library Building Committee Minutes - November 5, 2015 - page 2
Bob Labrecque noted that PR37, brick staining will be done in the spring as needed. We are
waiting to see how it weathers over the winter months. The extent of the anticipated
staining may be able to be reduced.
Rachel Baumgartner asked how the water proofing worked out with the rain last week and
Bob Labrecque noted it's hard to tell until all the work is completed, but they didn't see any
leaks. The contractor did a great job waterproofing. There should not be any leaks
whatsoever.
Bob Labrecque noted that the book drop door in the lobby is being revised and there will be
added cost for the security gates to change them from RF to RFID. The stone ban around
the building needs to be re- pointed, but not included in this report. Also there is one more
masonry item to be added to include more re- pointing in the yellow brick areas, but it needs
to be quantified. It is anticipated to be approximately $20,000. There is also a structural
framing issue in the attic that is being addressed to sure up the floor framing to carry the
weights of the energy recovery units. It will cost $7,000 to $10,000 to reinforce the attic
floor. The design coordinate was not complete and the structural engineer didn't have the
information during design phase. Bob Labrecque noted that the second floor public restroom
floors needs to be re- leveled.
It is anticipated that the construction contingency will be spent based on everything we
know to date. It is possible that funding of construction changes will need to dip into soft
costs to cover some of these items.
David Hutchinson asked to have the report to Town Meeting or Board of Selectmen
explained by category. Ruth Urell asked if it is possible to capture the number spent on
masonry.
David Hutchinson asked about the timeline. Bob Labrecque noted that the existing building
is two weeks behind the original completion date - March. It is anticipated that the addition
will be complete in April as the contractor struggled to complete the steel as scheduled.
David Hutchinson noted that if it was their job then it is on their time and Mr. Labrecque
indicated yes, the schedule on the addition is on the contractor. Bob Labrecque noted that
March 18th was the original date for the substantial completion and the site work is
extending into mid -May. The contractor is planning to pave certain areas before
Thanksgiving and the mounds of dirt will be removed. David Hutchinson asked if
landscaping will be done now and Bob Labrecque noted that it is planned for the spring.
David Hutchinson suggested having a scope of cost due to slippage and Bob Labrecque
indicated he could do that including the retaining wall, drainage revisions, etc. He will also
look at competitive pricing for the signage design.
Bob Labrecque noted that he met with Kevin Furilla and the vendor for the audio visual.
They are concluding on the scope of work and will create a purchase order by mid - January
for installation in the spring. David Hutchinson noted there is a subcommittee who will look
at that.
Rachel Baumgartner asked if the shelving end caps are included in the $700,000 and Bob
Labrecque noted it is.
Furniture - Ruth Urell noted that they only did a first pass on the furniture and gave CBT
feedback on chairs that look like a classroom. They want the Town Manager and Nancy
Twomey to look at the furniture before the second round. She hasn't looked at adult
furniture yet. They asked for stackable chairs that aren't too heavy. Some elderly people
need arm chairs. Bob Labrecque asked if they have done any showroom visits or seen
samples and Ruth Urell noted they will be getting samples.
Page 1 2
Library Building Committee Minutes - November 5, 2015 - page 3
Rachel Baumgartner asked if we could mix in some things that we have that work well and
David Hutchinson thought that would be fine.
The Town Manager noted that he cannot make the December 3rd meeting but feels the
committee can meet without him and then he can meet offline to work on the presentation
to the Board of Selectmen. David Hutchinson agreed and noted that the committee will
meet on December 3rd as originally planned.
Rachel Baumgartner asked about the status of a wish list and Vicki Yablonsky noted that
they are setting up a committee and nothing will be done until after Christmas.
Ruth Urell noted that the turret cones will go on the tower the week of November 16th Bob
Labrecque noted that the trim band needs to be replaced and there has been a redesign on
some of the crickets for water drainage and they are looking at possibly adding gutters.
Vicki Yablonsky asked about the automation system and Bob Labrecque noted the P.O.
should be issued in January to deliver the system in May. He noted they are still working on
revision of the circulation area with the architect. Ruth Urell noted they have a quote from
a vendor for $186,781. They asked for the quotes from the vendors on the state list. The
one vendor they like is not on the list right now but might be added so they should wait.
Jane Kinsella noted we will know in December who the vendors are that are being added to
that list. Vicki Yablonsky asked if the money is set for this and Bob Labrecque noted the
money is in the budget for this. Vicki Yablonsky noted this is super important to the project
as it is part of the program now.
A motion by Baumgartner seconded by Stepler to adiourn the meeting at 8:25 a.m.
was approved by a vote of 6 -0 -0.
Respectfully submitted,
Secretary
Page 1 3