HomeMy WebLinkAbout2015-08-06 ad Hoc - Library Building Committee MinutesOF Ri
c_ Town of Reading
i I Meeting Minutes
6391NORP�
Board - Committee - Commission - Council:
Date: 2015 -08 -06
Building: Reading Town Hall
Address: 16 Lowell Street
Purpose: General Business
Attendees: Members - Present:
Ad Hoc Library Building Committee
Time: 7:00 PM
Location: Conference Room
Session: General Session
RECLIVED
TOWN CLERK
READING, MASS.
Chairman David Hutchinson, Vice Chairman Rachel Baumgartner, Bob
Newton, Cherrie Dubois, Greg Stepler, Nancy Twomey
Members - Not Present:
Jane Kinsella and Marc Moll
Others Present:
Town Manager Bob LeLacheur, Library Director Ruth Urell, David Neshat, Joe
Huggins, Vicki Yablonsky, Bob Labrecque, Paula Schena
Minutes Respectfully Submitted By: Secretary
Topics of Discussion:
Approval of Minutes
A motion by Twomey seconded by Dubois to approve the minutes of July 9, 2015
as amended was approved by a vote of 6 -0 -0.
Proiect Update
Bob Labrecque noted that site drainage work including ledge removal continues. They will
bring in a drill rig next week because the granite bedrock is very tough. They moved the
drainage retention basin 40 feet to the east to avoid as much ledge as possible.
They are preparing shoring for the lobby floor. Interior wood framing and seismic anchoring
remains in progress. They installed spray foam in the attic and dry wall framing on the
second floor. The roof shingling work is delayed because the color was not in stock so we
needed to choose an alternate color. Duct work installation begins week of August 17.
In the new addition they continue erection, decking and detailing of structural steel. David
Hutchinson asked if the big steel deliveries are done and Bob Labrecque indicated they are.
Change order #4 was signed today by the Town Manager for $30,833.88 for changes in
process.
Future activities in August include complete the interior demolition. Selective demolition of
port - cochere. Place the ground floor lobby slab. Make repairs to the chimney. Bring on the
mechanical trades. Wash down the exterior masonry walls. The pointing that was done in
the 1980's was a band aid fix. The red putty mortar is now showing through the thin gray
mortar which had been re- pointed as observed after more wall areas have been washed
down. All of the red bricks need to be repointed. We are having a hard time matching up
the mortar. The red putty mortar that was previously used when the building was originally
built is only now made in France. A portion of the scope for re- pointing the red brick is in
the
Page 1 1
Library Building Committee Minutes - August 6, 2015 - page 2
contract; however there will be an increase in the scope of the work and a cost associated
with it.
Bob Labrecque noted that the leaks from the July 1 rain storm caused water to wick through
the walls' existing stone foundation walls. The only option to correct this is positive side
waterproofing on the exterior of the foundation wall. He is pursuing getting an estimate for
this additional work. Cherrie Dubois asked if there is another approach we could take and
Mr. Labrecque noted CBT brought in an expert envelope consultant SG &H and this is the
only way to correct it. Ms. Dubois asked if they will have to excavate and Mr. Labrecque
indicated yes because the mortar joints are porous, weeping and wicking water to the
interior of the wall.
Rachel Baumgartner asked if it will cost less to fix because they are on the top of the hill
rather than on the bottom and Mr. Labrecque indicated not necessarily due to all of the
ledge in the parking lot area that impacts the site permeability.
David Hutchinson asked if there was a way to forecast this and Mr. Labrecque noted that
the design plan is to shed the water away from the building, however this approach does
not waterproof the stone foundation walls.
Budget - Bob Labrecque noted that construction contingency was reallocated to cover the
cost of change order #3 in the amount of $80,149.29 and that another PO was required to
continue the general testing program in the amount of $9,500. A portion of the funds to
cover the PO amount was reallocated from Owner soft cost contingency to adjust the budget
line item. David Hutchinson asked why we needed additional testing and Mr. Labrecque
noted that the change on the underpinning required more testing on the concrete. We had
to do a plant inspection in Quebec to meet the requirements for the code and building
permit structural inspection requirements for the steel fabrication and other related items.
Ruth Urell asked why that is a soft cost and David Hutchinson noted because it is a
professional fee.
Expenditures - The contingencies have been adjusted and highlighted changes are in the
budget summary.
Change Order Log - Ruth Urell asked if the $64,709.15 for the ACM damproofing removal at
the south wall is for repair also. Bob Labrecque noted it is just for removal and there will be
additional cost for remedial work.
David Hutchinson asked if we are still okay with the budget and Mr. Labrecque noted it is
getting tight.
David Hutchinson asked about the Deering Street retaining wall. The Town Manager noted
that he did a contingency plan and talked to the Town Accountant about what can come out
of the general fund. He is looking at items and determining how core they are to the
project and how much it will cost if we do it later. If anything is considered, there will be
full discussion about it first. We can fund $40,000 for the phone system through Town
Meeting because that is for the whole Town. Technology equipment can be put on hold.
Rachel Baumgartner noted that we could vary the age of computers.
Joe Huggins noted that the Town will self - perform paving in the parking lot and site
landscaping will be done by the Parks Department if necessary.
Bob Labrecque noted it will be tough to complete all of the site work this fall depending on
the timing to complete all of the additional work related to the unforeseen site conditions.
Page 1 2
Library Building Committee Minutes - August 6 2015 - page 3
David Hutchinson asked if the timeline is in jeopardy. The Town Manager noted as far as
rent is concerned he would rather move it out six months. Bob Labrecque noted if the final
pavement is put down by December 1 then March 18th is the date.
Bob Labrecque noted that the builders risk needs to be renewed by September 15, 2015
and it might cost more money.
David Hutchinson noted that CBT is hiring a new furniture person in September.
Ruth Urell asked why we have to deal with the ledge now. Bob Labrecque noted it is for
storm water drainage. Ruth Urell asked if that was already in place and Joe Huggins
indicated it was not. Nancy Twomey noted that we are required to keep rainwater onsite
and percolate down. This is a federal mandate. Bob Labrecque noted they did not
encounter any ledge when they were installing the utilities on the north side of the site.
The Town Manager asked Ruth Urell if the audio visual has been worked out and she
indicated it has. The Town Manager noted that fundraising for new computers is a good
one.
David Hutchinson noted that making a list of what are the must haves and good to haves
may be a good exercise to go through. Bob Labrecque noted that honestly the majority will
stay in play. We could look at finishes for savings.
Nancy Twomey noted that we cut quality the last time and look where we are now.
Bob Newton noted that Bob Labrecque is doing his job and deciding what is needed.
Furniture - Ruth Urell noted she is looking at recommendations on material bins.
Other Business - David Hutchinson asked if there have been any neighbor complaints. Bob
Labrecque noted that two complaints were received. A complaint that trucks were idling at
6:30 a.m. and another when they pulled the excavator equipment on Monday night around
9:00 p.m. and loaded it out in front of the neighbor's house. Joe Huggins noted that the
neighbor was very nice though and it was more of an FYI. Joe Huggins noted that Evan
Warner handled another complaint and the neighbor was happy with the result.
A motion by Hutchinson seconded by Twomey to adjourn at 8:30 p.m. was
approved by a vote of 6 -0 -0.
Respectfully submitted,
Secretary
Page 1 3