HomeMy WebLinkAbout2015-07-09 ad Hoc - Library Building Committee MinutesOF Rai
f c 'I
� o
539, INCOR?0
Town of Reading
Meeting Minutes
R E C E '� 0
TOWN CLERK
READING, MASS.
Board - Committee - Commission - Council:
Ad Hoc Library Building Committee
.:. -C12 P4 =10�
Date: 2015 -07 -09 Time: 7:00 PM
Building: Reading Town Hall Location: Conference Room
Address: 16 Lowell Street
Purpose: General Business
Attendees: Members - Present:
Chairman David Hutchinson, Vice Chairman Rachel Baumgartner, Jane
Kinsella, Greg Stepler, Nancy Twomey, Cherrie Dubois
Members - Not Present:
Bob Newton and Marc Moll
Others Present:
Bob Labrecque, Joe Huggins, Alice Collins, Ruth Urell, Vicki Yablonsky, Barry
Berman, Steve Crook, David Neshat and Paula Schena
Minutes Respectfully Submitted By: Secretary
Topics of Discussion:
Approval of Minutes
A motion by Dubois seconded by Baumgartner to approve the minutes of June 4,
2015 as amended was approved by a vote of 6 -0 -0.
Discussion /Action Items
New Finance Committee Member - The Finance Committee's newest member David Neshat
was present and introduced himself.
Project Activity and Timeline Update - Bob Labrecque noted that they are working on site
drainage. The detention basin in the south parking lot was shifted east to avoid an
outcropping of ledge. There is a delay in getting some parts due to the relocation so the
ledge removal is now anticipated to commence next week. David Hutchinson asked if we
had tested for ledge and if we can go around it. Bob Labrecque noted the original site
borings were done in 2010 and the detention basin was just included in the recent design. It
was not economical to test for ledge in the south parking lot as it would have required
drilling every 10 feet to do that. It is unknown how big the ledge is but they are moving the
drainage to minimize the ledge removal. Nancy Twomey noted that the drainage was added
in by the Town Engineer.
David Hutchinson asked how much more site work needs to be dug up and Bob Labrecque
noted mostly just the drainage plus utility tie -ins at the streets.
Rachel Baumgartner noted that the Chronicle incorrectly ran a story saying we would be
blasting and she asked if someone will send a letter to correct that. David Hutchinson noted
that he doesn't want to get in the habit of sending letters back and forth to the Chronicle so
the minutes will stand as the record.
Page 1 1
Ad Hoc Library Building Committee Minutes - July 9, 2015 - page 2
Bob Labrecque noted that they will start the CMU walls at elevator shaft and mechanical
room. They will continue to rough in the plumbing for toilets. Interior structural wood
framing and seismic anchoring continues. They anticipate the start of ductwork installation
the week of July 13, 2015.
Bob Labrecque noted he anticipates the start of erection of steel on July 16, 2015. David
Hutchinson asked about a top off date and Bob Labrecque noted the top off will be
approximately two weeks after the start of erection of steel. The steel beam will be painted
white and people can stop by and sign it the morning of the topping off.
Bob Labrecque noted that change order # 3 was signed and includes; added snow guards,
an adjustment to the slab at the ground floor for deletion of stack shelving, CCD for east
turret foundation support and haunch at exterior walls, addition of a switchgear power
quality meter, removal of ACM damproofing at the south wall and credit for the change in
sanitary piping.
Cherrie Dubois asked if there will be snow guards on the turrets because snow has fallen off
of them in the past and someone was injured. Bob Labrecque indicated he will make sure
there are provided.
Ruth Urell asked about the cost to replace the south side masonry wall. Bob Labrecque
noted the cost is $60,000 - $70,000 because it has to be rebuilt section by section. A CCD
has been authorized to provide a sample panel to be repaired to establish quality and
identify the labor component for removal and rebuild. David Hutchinson asked about the
other sides and Mr. Labrecque noted the grading remains the same on the other sides so we
will leave those alone.
Nancy Twomey asked about foundation leaks. Mr. Labrecque noted that we had some
heavy rains last week and as the water percolated around the perimeter of the existing
building there was some leaks coming through the existing stone foundation that need to be
addressed. CBT has been requested to engage a consultant to provide a cost effective
solution for remedial work.
Rachel Baumgartner asked if the interior foundation surface inside the basement is going to
be pointed and Mr. Labrecque noted it will most likely be re- pointed from the outside.
Budget - Bob Labrecque noted that the budget update includes the following commitments;
Delphi change order #2 in the amount of $75,976.79, CBT Port Cochere re- design
amendment #8 for $24,300 and $100,000 reallocated for shelving and stacks. Mr.
Labrecque has reviewed the open changes to date and noted that the estimated cost of
changes is within the contingency budget.
Rachel Baumgartner asked about the change in the rent and David Hutchinson noted that
maintenance /utilities change monthly.
Bob Labrecque reviewed the change order log as follows; CCD 8 - structural modification for
2 replacement footings at the ground floor, CCD 13 - removal of original perimeter plaster
walls identified as not being well bonded to the lath and a mix of plaster and drywall
previously installed in the 1983 renovation, CCD 14 - south wall masonry fagade mitigation
and CCD 15 for relocation of detention basin and ledge removal.
David Hutchinson asked if CCD -15 in the amount of $25,000 to relocate the basin due to
ledge includes the removal of the ledge and Bob Labrecque indicated it does.
Page 1 2
Ad Hoc Library Building Committee Minutes - July 9 2015 - page 3
Ruth Urell asked about the cost of the screens and Bob Labrecque noted that the price for
the operable curtain wall screen appears high so they have request that CBT review this
with the manufacturer.
Bob Labrecque noted that replacing the Deering Street retaining wall and Middlesex curb
has been estimated at $108,756. CBT has been requested to move forward with the design
of that and to get firm pricing from the contractor. Rachel Baumgartner noted that she
checked the minutes and the committee voted to eliminate that as a bid alternate. David
Hutchinson noted that this is a budget choice and this group needs to discuss this. He also
noted that the contingency is for unforeseen expenses. Bob Labrecque noted that the
contract presently requires some repairs only to that wall. It was noted that the
construction of a new retaining wall will require excavation of portions of the parking lot as
well as removal and replacement of the sidewalk. It is recommended that the wall be
replaced now while the site is under construction as this is the most cost effective time to
do it. The wall has structural cracks and it is anticipated that additional repairs would be
needed again within 10 years. Rachel Baumgartner noted that the planters alternate had a
higher priority ranking than the retaining wall.
Ruth Urell noted there was much discussion over two to three design phase meetings as to
what do to but Bob Labrecque was not at those meetings. Rachel Baumgartner noted that
the thought was if money was left afterwards it would be done.
Bob Labrecque noted he will get the design and price. This would have to be done this fall
as this is an integral part of the construction. A decision needs to be made within one
month.
Barry Berman noted that he doesn't want to not replace the wall if this will have to be done
later. He suggests doing it now. This is very much part of the building project. The legacy
of this building is repair and patch jobs.
Timeline - Bob Labrecque noted that the schedule is tight. Steel erection for the addition
has pushed out and CBT is still finalizing the design on replicating the Porte Cochere. It is
possible the move date could go beyond July 1. It was suggested that the schedule duration
for Library move in be adjusted.
Furniture - David Hutchinson asked if we have a signed contract. Bob Labrecque noted that
Chris Coios is committed to get things moving next week and the contract has been signed.
David Hutchinson noted that $600,000 was the place holder for furniture and now we can
start plugging items. He asked how long that will take and Bob Labrecque noted there
should be another estimate due in 30 days or so but will confirm with CBT.
Technology-- Bob Labrecque noted there have been meetings and Chris Coios is working on
proposals for consultants both for technology and AV. A meeting was conducted with RCTV
and they will undertake the sound and video with their vendor in the community room and
they will lay out what they envision.
Ruth Urell noted that she gave STV everything to spec out the components. She's working
with IT to get new phones also.
Rachel Baumgartner noted that some of their computers are almost new and she asked if
they should get all new computers at once and if so how will they be replaced. David
Hutchinson noted that is part of the tech discussion.
David Hutchinson noted that the next meeting will be on August 6th unless people can't
make it.
Page 1 3
Ad Hoc Libras Building Committee Minutes - July 9 2015 - page 4
A motion by Twomey seconded by Baumgartner to adiourn the meeting at 8:30
gm was approved by a vote of 6 -0 -0.
Respectfully submitted,
Secretary
Page 1 4